3. Zonal Capacity Requirements

3.1. The Need for Zonal RA Procurement

Forecasted load. The CAISO states that use of a "1-in-5 year peak forecast" is required under its Grid Planning Standards when conducting regional studies, and it asserts that a 1-in-5 standard is the minimum that should be used for zonal RA requirements. The CAISO anticipates using coincident zonal load forecasts prepared by the CEC.

Import capability. The CAISO proposes an import capability calculation that maximizes the quantity of imports into a zone. The calculation starts with the aggregate transfer capability from outside the CAISO control area into each zone that is calculated as part of the existing import capacity allocation process, and also includes import capacity between CAISO zones over Path 26. The CAISO notes that it will be necessary to coordinate the import allocation process with the zonal requirement. The CAISO further notes that in the case of SP 26, the proposal does not assess specific changes to flows on individual branch groups.

Generation outages. While the CAISO generally does not permit planned outages during peak demand periods, historically there have been a small number of such outages that are unavoidable. The CAISO estimates generator outages by examining historic outage data on peak summer conditions at hour-ending 1600. The CAISO notes that including an outage component in the zonal methodology does not constitute double-counting of outages in relation to the PRM.

Single largest contingency. The CAISO determined that the single largest contingency for SP 26 is the loss of 2,000 megawatts (MW) related to the loss of the Pacific DC Inter-tie. For NP 26 the largest single contingency is the loss of a Diablo Canyon Unit at 1,160 MW.

3.2. Zonal RA Implementation Proposals

3.2.1. Path 26 Counting Constraint (Joint Parties)

Step 1. The CAISO determines the amount of Path 26 transfer capacity available for RA counting purposes after accounting for Existing Transmission Contracts (ETCs) and loop flow.3 The CAISO calculated the Path 26 transfer capability as 3,430 MW north-to-south and 2,583 MW south-to-north.

Step 2. The CAISO determines the baseline amount of Path 26 counting capacity that an LSE is eligible to receive in the allocation process without consideration of the impact of netting the north-south and south-north RA counting "flows" on Path 26. This baseline amount is the higher of (1) the LSE's load-ratio share of load in the zone or (2) the sum of the LSE's existing commitments-ETCs, Transmission Ownership Rights (TORs), and RA resource agreements in effect as of February 21, 2007 (Grandfathered RA Commitments). If an LSE has such Grandfathered RA Commitments that exceed its load-share ratio, other LSEs in that zone will receive a baseline allocation that is less than their load-ratio share. While we find the proposal unclear on this point, it appears that this reduced allocation for LSEs without Grandfathered RA Commitments reflects a pro rata share of the total amount by which the allocations for LSEs with Grandfathered RA Commitments exceed the load-ratio shares for those LSEs. The CAISO will notify LSEs of their baseline allocations by mid-July. An LSE will be able to receive more than its baseline share if additional capacity becomes available through the netting process identified in Step 3. Once the Grandfathered RA Commitments expire, an LSE's baseline share will revert to its load-ratio share.

Step 3. Once the baseline quantities are determined, LSEs will have an opportunity, but not an obligation, to submit RA resource contract commitments (Preliminary Path 26 Submittals) that exist as of July 31 of each year, including Grandfathered RA Commitments, that need to use Path 26 to deliver to the LSE's loads (Existing RA Commitments). The CAISO will use these Preliminary Path 26 Submittals to "net" the north-to-south and south-to-north Path 26 RA counting impacts associated with the Existing RA Commitments. An LSE's Preliminary Path 26 Submittal cannot exceed its baseline Path 26 RA counting capacity. Once submitted, the Preliminary Path 26 Submittals will create a binding obligation on the LSE to include the Existing RA Commitments in its year-ahead and month-ahead RA compliance filings. The Existing RA Commitments submitted and accepted by the CAISO through the Preliminary Path 26 Submittals process will also be subject to all CAISO Tariff offer obligations. This Preliminary Path 26 Submittal process will take place each year.

Step 4. The CAISO will allocate the additional Path 26 RA counting capacity that was made available due to netting of existing commitments. This additional counting capacity will be allocated to LSEs based on load-ratio shares, and will be additive to the LSEs' baseline allocations. However, LSEs whose baseline Path 26 RA counting capacity exceeds their load-ratio shares because of Grandfathered RA commitments will only receive additional Path 26 RA counting capacity after all other LSEs have been "topped off" by being allocated additional Path 26 RA counting capacity in an amount that causes them to exceed their respective load-ratio share by the same percentage that the initial LSE receive because its baseline allocation exceeded its load-ratio share.

Step 5. The CAISO will notify LSEs of the final results of the Path 26 RA counting capacity process within 5-7 business days of July 31 of each year. This final notification can only increase the amount initially allocated to each LSE by mid-July in Step 2, but cannot decrease that initial allocation. In order for an LSE to count an RA resource that requires the use of Path 26 to be delivered to its load zone, an LSE would have to have sufficient Path 26 RA counting capacity.

3.2.2. Minimum Percentage Requirement (DRA)

3.2.3. Discussion - Adopted Approach for Zonal Reliability

2 Path 26 is composed of transmission lines between northern and southern California. The two constrained zones identified by the CAISO are the electrical footprint north of this path (NP 26) and the electrical footprint south of it (SP 26).

3 The transfer capacity on Path 26 must be de-rated to accommodate ETCs that are used to serve load outside the CAISO control area. "Loop flow" is common to large electric power systems and must be accommodated to prevent overloading of lines.

4 Although DRA referred to "ESP" in presenting its proposal (DRA Zonal Capacity proposal, p. 4), we understand the intended references are to "LSE."

Previous PageTop Of PageNext PageGo To First Page