ALJ/VSK/hl2 Date of Issuance 9/13/2007
Decision 07-09-014 September 6, 2007
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a permit to Construct Electrical Facilities With Voltages of Between 50 kV and 200 kV: Riverway Substation Project. |
Application 06-06-004 (Filed June 1, 2006) |
OPINION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY
A PERMIT TO CONSTRUCT ELECTRICAL FACILITIES
TABLE OF CONTENTS
Title Page
OPINION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY
A PERMIT TO CONSTRUCT ELECTRICAL FACILITIES 11
6. Proposed Facilities Description 44
7. Environmental Review and EMF Compliance 55
9. Categorization and Need for Hearing 1212
10. Waiver of Comment Period 1212
11. Assignment of Proceeding 1313
OPINION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY
A PERMIT TO CONSTRUCT A NEW POWER LINE
This decision grants Southern California Edison Company (SCE) a Permit to Construct (PTC) the project known as the Riverway Substation Project (Project). The Project consists of: (1) construction of a 66/12 kilovolt (kV) substation (Riverway Substation) in Visalia, California; (2) construction of a 0.2 mile 66 kV subtransmission line to connect the Riverway Substation with an existing 66 kV overhead transmission line; and (3) installation of fiber optic cable and communications equipment to connect the Riverway Substation to SCE's existing telecommunications system. SCE sought Commission approval for a PTC for the project pursuant to General Order (GO) 131-D. As the Lead Agency for environmental review, we find the Final Mitigated Negative Declaration (Final MND) prepared for this project meets the requirements of the California Environmental Quality Act (CEQA). This proceeding is closed.