6. The RA Confirmations

SCE and CES negotiated and executed three separate RA Confirmations as part of the CSA. They are for 2007, 2008 and 2009-2011. For 2008 and 2009-2011, SCE procured Local RA capacity from the Pastoria Energy Facility as a trade for Local RA capacity from the Geysers units, although the Geysers units will continue to provide energy to SCE as an RPS resource.

Previous PageTop Of PageNext PageGo To First Page