Word Document PDF Document |
ALJ/DUG/avs Date of Issuance 3/27/2009
Decision 09-03-031 March 26, 2009
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application of Southern California Edison Company (U338-E) for Recovery of Peaker Costs. |
Application 07-12-029 |
DECISION ALLOCATING RECOVERY OF PEAKER COSTS BY
SOUTHERN CALIFORNIA EDISON COMPANY TO ALL BENEFITING SERVICE CUSTOMERS
This decision allocates the costs and resource adequacy benefits of Southern California Edison Company's (SCE) four peaker units, which are owned and operated by SCE, to all benefiting customers. The issue of whether the requested costs are just and reasonable for recovery in rates will be determined in a subsequent decision. This proceeding remains open.