RESOLUTION E-4034
Resolution E-4034. Southern California Edison (SCE). This resolution approves SCE's Advice Letter 2005-E submitting notice pursuant to General Order 131-D (GO 131-D), Section XI, Subsection B.4 of the Construction of Facilities that are exempt from a Permit to Construct. GO 131-D was adopted by the California Public Utilities Commission (Commission) in Decision D. 94-06-014 and modified by D.95-08-038.
By Advice Letter 2005-E. Filed on May 23, 2006.
__________________________________________________________
This Resolution approves SCE's Advice Letter 2005-E submitting notice pursuant to General Order 131-D (GO 131-D), Section XI, Subsection B.4 of the Construction of Facilities that are exempt from a Permit to Construct. GO 131-D was adopted by the California Pubic Utilities Commission (Commission) in Decision D. 94-06-014 and modified by D.95-08-038. This Resolution is effective immediately.