LEGISLATIVE SUBCOMMITTEE RECOMMENDATION: SUPPORT WITH AMENDMENTS
SUMMARY OF BILL
The bill establishes as state policy the modernization of the state's electrical grid to maintain reliable and secure electrical service with infrastructure that can meet future growth in demand while achieving several other objectives such as integration of distributed generation resources, demand-side resources and `smart' technologies.
SUMMARY OF SUPPORTING ARGUMENTS FOR RECOMMENDATION
This bill codifies various smart grid related policies and activities that the California Public Utilities Commission (CPUC) has already initiated. The bill gives proper latitude to CPUC in determining cost-recovery for Smart Grid investments as appropriate. The recommended changes below are intended to provide the CPUC the necessary flexibility to properly scope and assess its regulatory approach and timing.
DIVISION ANALYSIS (Energy Division)
Title XIII of the Federal Energy Independence and Security Act of 2007 (EISA) addresses Smart Grid technology and provides specific objectives for the Smart Grid. There are three main components in the Smart Grid provisions of the EISA:
1) Section 1305(a) gives primary responsibility to the National Institute of Standards and Technology (NIST) to "coordinate the development of a [Smart Grid interoperability] framework that includes" standards and protocols.
2) Section 1306(a) of the Act creates a matching Smart Grid Investment Program up to 1/5 of qualifying Smart Grid investments.
3) Sec. 1307 requires states to consider smart grid investment by regulated utilities and recovery of associated Smart Grid investments.
Regulatory Approach: The bill establishes a regulatory approach for the CPUC and the investor-owned utilities (IOUs), to follow for consideration and deployment of Smart Grid technology. Specifically the bill directs the CPUC, in consultation with the CEC and the CAISO, to determine the requirements of a Smart Grid deployment plan by July 1, 2010. The IOUs are then required to submit plans to the CPUC (by July 1, 2011) in accordance with those requirements. The bill also allows Smart Grid infrastructure to be deployed incrementally, and directs the CPUC (in consultation with the CEC, the CAISO and the IOUs) to evaluate the impact of deployment on major state initiatives and policies such as implementation of the Advanced Metering Initiative (AMI), achievement of a Renewables Portfolio Standard (RPS), and achievement of reducing Green House Gas (GHG) emissions.
The CPUC opened a Rulemaking on December 18, 2008 on its own motion and in response to federal legislation, to consider policies for California investor-owned utilities (IOUs) to enhance the ability of the electric grid to support policy goals such as reducing GHG, increasing EE and DR, and expanding use of renewable energy and improving reliability.
The CPUC has the authority to begin a formal proceeding on Smart Grid issues in the absence of legislation and has already done so. However, the legislation is helpful in establishing Smart Grid functionality guidelines that the Legislature believes are important to pursue.
One of the key objectives of the CPUC's Smart Grid OIR is determining an appropriate regulatory approach to support the development of a cost-effective Smart Grid. Related to that determination are specific issues, such as how shall the CPUC assess cost-effectiveness of Smart Grid expenditures, what are the characteristics or requirements for a Smart Grid, and how shall benefits of the Smart Grid be quantified or otherwise assessed? The Smart Grid OIR also seeks stakeholder input on questions about deployment strategies and on how the CPUC should assess progress. The regulatory approach established by the bill may indeed turn out to be the best approach for the CPUC, but the CPUC should have the flexibility to make a final determination on both process and timeline after receiving stakeholder input.
Smart Grid Standards and Protocols: The bill directs the CPUC to "adopt standards and protocols...developed by public and private entities including, but not limited to, the National Institute of Standards and Technology, Gridwise Architecture Council,..." In its rulemaking, the CPUC recognizes the importance of setting policies with respect to functionality and interoperability, but will consider whether standards and protocols are actually needed. Rather than require the CPUC to adopt standards developed by other entities, the bill should be amended so that the CPUC has the flexibility to make a final determination, after receiving stakeholder input, if and how such standards should be adopted.
Publicly-owned Utilities: The bill directs publicly-owned utilities (POUs) with more than 100,000 service connections to develop a Smart Grid deployment plan by July 2011 consistent with federal law. SB 17's requirement that POUs be compliant only with federal law could be interpreted to mean that they only consider Smart Grid investments, and not be required to actually deploy any Smart Grid infrastructure.
IOU plans must be deployed and also be consistent with Section 8360 of SB 17. Section 8360 establishes as state policy the modernization of the electric grid and provides ten objectives of the Smart Grid such as the integration of renewable power, incorporation of demand-side resources, and deployment of cost-effective technologies to increase efficiency, security and reliability.
POUs are exempt from the overarching policy and specific objectives in the bill, which could lead to a fragmented grid that could be less effective in meeting statewide energy objectives.
Rate-Recovery: When an investor-owned utility procures equipment for the purpose of providing electric service to its ratepayers, the CPUC has the authority to determine what expenditures will be recoverable from ratepayers and the method by which the expenditures will be recovered. This bill maintains the CPUC's discretion in the area of IOU cost-recovery relative to Smart Grid deployment as well.
The CPUC has approved advanced metering projects for the three largest investor-owned electric utilities. The CPUC will need to ensure that investments in the Smart Grid infrastructure are appropriately aligned with current investments in advanced meters. This can best be done via a CPUC-led proceeding where the technical functionalities of the Smart Grid are completely vetted and understood in the context of the advanced meters that will be deployed.
Demand Response proceedings: The CPUC has initiated several proceedings over the past 5 years that have focused on increasing demand response as a resource for the IOUs. As a result, the IOUs operate various demand response programs and dynamic pricing tariffs that are designed to incent customers to reduce their electricity usage during peak hours. As of December 2008, the IOUs have approximately 3,000 MWs of demand response potential capacity.
General Rate Case (GRC) proceedings: IOUs typically seek ratepayer funding for capital investment projects, such as improvements to the grid, via their GRCs which occur every three years. In these proceedings, the CPUC endeavors to make sure that the IOUs' requests for cost recovery are reasonable and that the IOUs do their best to keep costs at a minimum consistent with the mandate to ensure reliable service and to meet the energy policy goals set by the Energy Action Plan. All of the IOUs' requests for cost recovery and rate increases are examined closely following a rigorous public process that provides for fact finding and public participation.
Distributed Generation: The CPUC regulates distributed generation on both the customer and utility wholesale side of the electric meter. Customer-side of the meter distributed generation incentive programs includes the California Solar Initiative and the Self-Generation Incentive Program. These programs are supported by the CPUC's oversight of Net Energy Metering and Interconnection policies. Wholesale side of the meter distributed generation includes energy generated for sale to utilities and includes feed-in tariffs for both small renewables and combined heat and power (CHP) generators.
SB 1438 was introduced in the 2008 legislative session. That bill, like SB 17, sought to establish as state policy the modernization of the grid. It contained many of the same components as SB 17.
As noted earlier, Congress passed the EISA 2007 in December 2007 that set up a Smart Grid framework and directed states to begin consideration of Smart Grid by December 2008 and make a determination regarding Smart Grid deployment by December 2009.
Activities by other states are unknown.
Scheduled to be heard in Senate Committee on Energy, Utilities and Communications on April 21, 2009.
STAFF CONTACTS:
Alicia Priego, OGA (916) 322-8858 arp@cpuc.ca.gov
Date: April 7, 2009
BILL LANGUAGE:
BILL NUMBER: SB 17 INTRODUCED
BILL TEXT
INTRODUCED BY Senator Padilla
DECEMBER 1, 2008
An act to add Chapter 4 (commencing with Section 8360) to Division
4.1 of the Public Utilities Code, relating to electricity.
LEGISLATIVE COUNSEL'S DIGEST
SB 17, as introduced, Padilla. Electricity: smart grid systems.
Under existing law, the Public Utilities Commission has regulatory
authority over public utilities, including electrical corporations,
as defined. Under existing law, the governing board of a local
publicly owned electric utility, as defined, generally has authority
over the activities of the utility.
This bill would require the commission, by July 1, 2010, and in
consultation with the State Energy Resources Conservation and
Development Commission (Energy Commission) and the Independent System
Operator (ISO), to determine the requirements for a smart grid
deployment plan consistent with the policies set forth in the bill
and federal law. The bill would require that the smart grid improve
overall efficiency, reliability, and cost-effectiveness of electrical
system operations, planning, and maintenance. The bill would require
each electrical corporation, by July 1, 2011, to develop and submit
a smart grid deployment plan to the commission for approval and would
authorize the commission to authorize an electrical corporation to
recover reasonable costs of deploying smart grid technologies and
services from ratepayers. The bill would authorize a smart grid
deployment plan that is adopted to provide for deployment of smart
grid products, technologies, and services by entities other than
electrical corporations. The bill would authorize smart grid
technologies to be deployed in an incremental manner to maximize the
benefit to ratepayers and to achieve the benefits of smart grid
technology, would authorize the commission to modify or adjust the
bill's requirements for an electrical corporation with fewer than
100,000 service connections as individual circumstances merit, and
would require the commission in consultation with the Energy
Commission, the ISO, and electrical corporations, at each step of
deployment, to evaluate the impact of deployment on major initiatives
and policies.
The bill would require a local publicly owned electric utility, as
defined, to develop by July 1, 2011, a smart grid deployment plan
consistent with the policies set forth in federal law. By placing
requirements upon local publicly owned electric utilities, the bill
would impose a state-mandated local program.
The California Constitution requires the state to reimburse local
agencies and school districts for certain costs mandated by the
state. Statutory provisions establish procedures for making that
reimbursement.
This bill would provide that no reimbursement is required by this
act for a specified reason.
Vote: majority. Appropriation: no. Fiscal committee: yes.
State-mandated local program: yes.
THE PEOPLE OF THE STATE OF CALIFORNIA DO ENACT AS FOLLOWS:
SECTION 1. Chapter 4 (commencing with Section 8360) is added to
Division 4.1 of the Public Utilities Code, to read:
CHAPTER 4. SMART GRID SYSTEMS
8360. It is the policy of the state to modernize the state's
electrical transmission and distribution system to maintain reliable
and secure electrical service, with infrastructure that can meet
future growth in demand and achieve all of the following, which
together characterize a smart grid:
(a) Increased use of cost-effective digital information and
control technology to improve reliability, security, and efficiency
of the electric grid.
(b) Dynamic optimization of grid operations and resources, with
cost-effective full cyber security.
(c) Deployment and integration of cost-effective distributed
resources and generation, including renewable resources.
(d) Development and incorporation of cost-effective demand
response, demand-side resources, and energy-efficiency resources.
(e) Deployment of cost-effective smart technologies, including
real time, automated, interactive technologies that optimize the
physical operation of appliances and consumer devices for metering,
communications concerning grid operations and status, and
distribution automation.
(f) Integration of cost-effective smart appliances and consumer
devices.
(g) Deployment and integration of cost-effective advanced
electricity storage and peak-shaving technologies, including plug-in
electric and hybrid electric vehicles, and thermal-storage
air-conditioning.
(h) Provide consumers with timely information and control options.
(i) Develop standards for communication and interoperability of
appliances and equipment connected to the electric grid, including
the infrastructure serving the grid.
(j) Identification and lowering of unreasonable or unnecessary
barriers to adoption of smart grid technologies, practices, and
services.
8361. For purposes of this chapter, the following terms have the
following meanings:
(a) "ISO" means the Independent System Operator operating pursuant
to Article 3 (commencing with Section 345) of Chapter 2.3 of Part 1
of Division 1.
(b) "Energy Commission" means the State Energy Resources
Conservation and Development Commission.
8362. (a) By July 1, 2010, the commission, in consultation with
the Energy Commission and the ISO, shall determine the requirements
for a smart grid deployment plan consistent with Section 8360 and
federal law, including the provisions of Title XIII (commencing with
Section 1301) of the Energy Independence and Security Act of 2007
(Public Law 110-140). The commission shall institute a rulemaking or
expand the scope of an existing rulemaking to adopt standards and
protocols to ensure functionality and interoperability developed by
public and private entities, including, but not limited to, the
National Institute of Standards and Technology, Gridwise Architecture
Council, the International Electrical and Electronics Engineers, and
the National Electric Reliability Organization recognized by the
Federal Electric Reliability Commission. An adopted smart grid
deployment plan may provide for deployment of cost-effective smart
grid products, technologies, and services by entities other than
electrical corporations. The smart grid technologies and services
shall improve overall efficiency, reliability, and cost-effectiveness
of electrical system operations, planning, and maintenance.
(b) This section does not require or authorize the commission to
delay action on an application by an electrical corporation that is
submitted prior to the commission determining the requirements for a
smart grid deployment plan.
8364. (a) By July 1, 2011, each electrical corporation shall
develop and submit a smart grid deployment plan to the commission for
approval.
(b) The commission may authorize an electrical corporation to
recover reasonable costs of deploying smart grid technologies and
services from ratepayers. Costs may include capital investment,
including a reasonable rate of return on the capital expenditures,
operating expenditures, and other reasonable costs of the electrical
corporation made for the deployment of the qualified smart grid
system. The commission may modify or adjust the requirements of this
chapter for an electrical corporation with fewer than 100,000 service
connections, as individual circumstances merit.
(c) This section does not require or authorize the commission to
delay action on an application by an electrical corporation that is
submitted prior to the commission's approval of the electrical
corporation's timely filed smart grid deployment plan.
8366. Smart grid technology may be deployed in an incremental
manner to maximize the benefit to ratepayers and to achieve the
benefits of smart grid technology. At each step of deployment, the
commission in consultation with the Energy Commission, the ISO, and
electrical corporations, shall evaluate the impact of deployment on
major initiatives and policies including:
(a) Implementation of new advanced metering initiatives.
(b) Achievement of the renewables portfolio standard program
requirements and the need to operate the smart grid of the future
with a substantial increased percentage of electricity generated by
eligible renewable energy resources.
(c) Achievement of state goals for reducing emissions of
greenhouse gases reduction goals as set forth in the Global Warming
Solutions Act of 2006 and other state directives.
(d) Achievement of the energy efficiency and demand response goals
as required by Sections 454.5 and 454.55 and other state directives.
(e) Modernizing the aging utility grid infrastructure.
(f) Meeting the future energy growth needs of the state with new
and innovative technologies and methods that utilize the existing
assets more efficiently, result in less environmental impact on the
state, meet stringent costs versus benefit assessments, and provide
the ratepayers with new options in meeting their individual energy
needs.
8367. Each local publicly owned electric utility with more than
100,000 service connections, shall, by July 1, 2011, develop a smart
grid deployment plan, that is consistent with federal law, including
the provisions of Title XIII (commencing with Section 1301) of the
Energy Independence and Security Act of 2007 (Public Law 110-140).
SEC. 2. No reimbursement is required by this act pursuant to
Section 6 of Article XIII B of the California Constitution because a
local agency or school district has the authority to levy service
charges, fees, or assessments sufficient to pay for the program or
level of service mandated by this act, within the meaning of Section
17556 of the Government Code.