20. FORCE MAJEURE
Neither Party shall be liable to the other for any delay in or failure of performance, nor shall any such delay in or failure of performance constitute default, if such delay or failure is caused by "Force Majeure." As used in this Section, Force Majeure is defined as: Acts of war and acts of God such as earthquakes, floods and other natural disasters, or actions of others, including but not limited to strikes, lockouts or other industrial disturbance, not within the control or arising from the fault of the Party claiming Force Majeure.
The Party affected by a Force Majeure Event ("Affected Party") shall be excused from performing its obligations under this Agreement to the extent that such performance is prevented or delayed due to the delay occasioned by a Force Majeure event; provided, however, that the suspension of performance is of no greater scope and of no longer duration than is required by such Force Majeure event. If a Force Majeure Event excuses the Implementer from performing its obligations under the Agreement, the Implementer will not be paid for the obligations that were excused because of the Force Majeure Event and must refund unspent dollars to the IOU for deposit in the balancing accounts that tracks the gas and/or electric Public Goods Charge fund.