4. Principles for Tariff and Program Design

This portion of the working group agenda involved three different levels of discussion:

1. CEC recommendations7 on development of "default" tariff options for various customer classes, such as:

Finally, staff presented principles related to achieving revenue neutrality and ensuring that the new tariffs reflect the costs of serving customer classes. These are listed below.

During the working group meeting, there was also significant discussion on the issue of how any given rate design could achieve revenue neutrality. There is general consensus that the current rate designs for particular customer classes do not reflect the underlying costs of serving those customers, because a substantial portion of rates is collecting revenues designed to repay historic utility procurement costs or Department of Water Resources emergency purchase costs incurred during 2000 and 2001. Thus, in order to achieve revenue neutrality by customer class and minimize cross-subsidization, a significant question exists as to whether any new rate options should be designed by utilizing existing total revenue requirements or whether new component-based revenue requirements should be developed that distinguish between current generation procurement costs and historic sunk costs of procurement incurred by utilities and the Department of Water Resources. We invite parties' (especially the utilities') comments in response to this ruling on the "pros and cons" of the two approaches.

Following discussion of these general principles, consensus emerged that could logically lead to the conclusion that the reports generated by Working Groups 2 and 3 should address the following issues:


· A summary of the tariff forms recommended and their expected load impacts


· A summary of nontariff program options designed to achieve similar demand reduction objectives


· Design principles used to construct the tariffs or programs.


· Metering and communication requirements to support the tariffs


· Need for additional building controls and or intelligent systems to enhance customer response


· Information sources/systems for customers needed to support the tariffs or programs, including program/tariff marketing efforts required to recruit customers


· Potential need to upgrade utility billing system capabilities to support the tariffs or programs


· How these options support customer preferences or customer choice

Though formal assignments for Working Groups 2 and 3 were not discussed at the policy group meeting, Working Group 1 suggests that the following deliverables for those groups could also flow logically from the matters discussed. We seek parties' written comments on the proposed assignments detailed further below.

Specific Guidance to Working Group 2 (Large Customers)

1. Design at least one dynamic tariff (beyond time of use) ready for implementation after issuance of a PUC decision at the end of Phase I. This would represent our best bet for a "quick win" suggested by several parties. This plan should include all of the following:

2. An analysis of how any existing pilot efforts could be improved to provide more information for further program or tariff development. This activity should include:

3. Recommended next steps for large customers, to be addressed in Phase II of this proceeding

Specific Guidance to Working Group 3 (Small Customers)

4. Recommended next steps for developing more demand responsiveness in the small customer sector, to be addressed in Phase II of this proceeding

7 We concur with the CEC that the types of dynamic tariffs listed above should be discussed and analyzed by the working groups but believe it is premature to specify which tariff forms should be considered the default tariff for any specific customer class. We expect the working groups to make recommendations on both the form, specific tariff values and default status of all tariffs recommended in their report.

8 Item 6 is entitled "Design Principles for a Demand Responsive Electric Grid" and was prepared by CEC staff. Item 7, prepared by CPUC staff, describes "Past CPUC Principles Regarding Real Time Pricing Programs." Item 8, a discussion of "DR Programs that Enhance Reliability..." was prepared by CPA staff.

Previous PageTop Of PageNext PageGo To First Page