5. First Round Issues
The following is a review of issues for each of the first-round issues.
a. Forecasting
In their previously submitted procurement plans, all three utilities presented fairly detailed determinations of their forecasted energy needs. Generally, utility forecasts have involved the use of econometric models using a variety of inputs (population, economic growth, expected end-use electricity prices, natural gas prices which are an input to forecasting end-use prices, and other variables.) Often this analysis is performed for each customer class, and in some cases even for large individual customers. Energy production models and load duration curves are also developed which, in theory, provide forecasted hourly data on energy supply and demand.
As a threshold issue, the Commission has determined that:
The utilities themselves are the ones responsible and accountable for meeting the loads and energy requirements of the customers in their service areas. The utilities, not the CEC, are required to meet an obligation to serve under several sections of the Pub. Util. Code.... Therefore, regulatory clarity and appropriate placement of responsibility requires that the utilities should have the responsibility of estimating their own future needs. (p. 96.)
During the procurement planning hearings in 2003, several parties complained of a lack of "consistency"4 between the utilities' load forecasts, although it is unclear what this means. As D.04-01-050 notes: "although parties have complained about the lack of consistency of the forecasts, no party has substantively challenged the results." (p. 44-45.)
To some extent, the Commission has addressed the parties' concerns by requiring that the utilities each provide forecasts for the same set of scenarios (e.g. CEC base case,5 core/non-core model, high gas prices,6 etc.), as well as use the most recent gas price forecasts. We've also required that the utilities justify the use of assumptions other than those of the CEC base case.
Our development of a reserve requirement will require some additional consistency between utility forecasts. For example, we propose that utilities should use a "1-in-2"year forecast as their base case.7 Additionally, the utilities and LSEs will need to address the issue of forecasting coincident peak demand (i.e. the time of highest demand upon the ISO system as a whole) as opposed to each utilities' non-coincident peak demand (i.e. the time when each individual utility reaches its peak demand which may or may not be the same as the ISO system).
Given the inherent complexity in forecasting, we are not sure what more can be done to achieve "consistent" results. As the decision notes:
As a general matter, SDG&E previously explained that there is an unnecessary preoccupation with `common' or `perfect' assumptions to be used by the utility in its long-term resource planning. In SDG&E's view, while assumptions clearly need to be reasonable, the more critical piece is the testing of the assumptions to accommodate uncertainty). In the end, the utilities must plan using the best data for their unique circumstances, as they are accountable for the results (p. 44-45 citing SDG&E's Reply Brief).
However, SDG&E, along with PG&E and SCE, are signatories to the Joint Recommendation and the issue of forecasting was included in the proposed scope of the workshops.
Therefore, parties should be prepared to discuss:
a) What additional guidance should be provided to the utilities in developing their forecasts in order to improve consistency?
b) How do LSEs propose to determine their coincident and non-coincident peak demands and what are the coordination issues associated with this?
c) How accurate have the utilities (as well as the ISO and CEC) been in forecasting demand?
d) Is "consistency" between forecasts more important than "accuracy"?
As part of this discussion, the utilities should submit appropriate descriptions and examples of how they currently prepare their forecasts. The ISO and CEC are also invited to make similar presentations.
b. Forecasting Load to Determine ESP Obligations
In order to provide reliable service, each Load Serving Entity within [the utility's] should have an obligation to acquire sufficient resources for their customer load. (Ordering Paragraph 2, p. 195)
............
In the workshop it will be necessary to identify the treatment of direct access load and who should be responsible for forecasting it. (p. 46.)
In their previous procurement filings, the utilities essentially performed a "top-down" forecast of load served by ESPs, first calculating total load for each customer class and then subtracting out the appropriate portion of each utility's load served by ESPs. An additional step that would need to be taken is to further assign to each individual ESP its proportionate share of load. An alternative to this approach would be a "bottoms-up" approach where each ESP would be responsible for forecasting its own load.
Both approaches have advantages and disadvantages. The utilities, for example, generally have access to much more sophisticated econometric and load profiling data while ESPs may have a better sense of usage trends among their particular customers.
Under either approach, the final result must ensure that all demand (utility and ESP) is fully accounted for. Additionally, under either approach, the final forecasts should be adopted by the Commission after the appropriate hearing and evidentiary process. This procedural process would ensure that the Commission, as well as other parties, will have a full opportunity to assess the reasonableness of any forecast as well as any attempts to "game" the forecast.
Therefore, parties should be prepared to discuss:
a) What is the preferred approach for forecasting ESP load requirements (top-down, bottoms-up, some combination, other)?
b) How could conflicting load forecasts be reconciled prior to the hearing process?
c) Other implementation issues as appropriate.
c. Phase-In
In D.04-01-050, the Commission largely adopted the Joint Recommendation's proposal for a 15% Planning Reserve Margin (PRM) to be phased in by 2008, except that the Commission adopted a somewhat higher reserve margin of 15-17%.
In D.03-12-062 the Commission approved the Joint Recommendation's proposal that for 2004, the utilities would meet a 7% Operating Reserve Margin (ORM) and that this margin would not include "reasonably expected resource outages." This means that the Planning Reserve Margin for the utilities in 2004 (which includes expected outages) was quite likely higher than 7% (See discussion at the end of Section IV.A.5 of D.01-04-050).
D.04-01-050 requires that:
...[T]he utilities and LSEs should meet this 15-17% [planning reserve] requirement by no later than January 1, 2008, with interim benchmarks established starting in 2005. The starting point for compliance will be determine[d] in the workshops. (p. 23.)
Therefore, parties should be prepared to discuss:
a) What is the appropriate starting point for phasing in the 15-17% planning reserve requirement?; and,
b) What are the appropriate interim benchmarks for 2005 through 2008?
d. Development of "peak demand"
for applicable summer monthsD.04-01-050 requires that each LSE must forward contract one year ahead for 90% of their peak needs for the Summer months of May through September. This will require the development of peak demand estimates for each of these months. As previously mentioned, much of the data to calculate these peak demands may already exist in each utility's existing load forecasts. A question that needs to be addressed is for how much of the month must each LSE meet this 90% requirement.
In their original FERC filing, the ISO examined this issue and offered several options for meeting it. These options included either developing a load duration curve for each hour of the month or (as the ISO recommended) requiring LSEs to be able to meet the peak demand requirement for a set number of hours each month (e.g. the forecasted highest 1, 5, or 10 hours).8
This latter approach appears preferable and is the approach that we would recommend.
Therefore, parties should be prepared to discuss:
a) What is the appropriate method to determine peak monthly demand?
b) What is the appropriate coverage of this peak demand that LSEs must demonstrate?
e. Counting Resources - General Observations
As D.04-01-050 states:
To the extent possible, the workshop also should develop a common approach, or "template" as WPTF calls it, for evaluating each LSE's resource adequacy. While complete consistency between all LSEs' may not be feasible, at a minimum the workshop process should result in common approaches so that decision-makers and interested parties can evaluate and compare resource adequacy both between utilities and between all entities under Commission jurisdiction. (p. 44.)
As part of the Resource Adequacy Working Group (RAWG), an initial list of questions (attached) begins to address the issues associated with "counting" resources. Although preliminary and still a "work-in-progress" this document serves as a useful starting point to begin discussions over the evaluation of resources.
Additionally, we offer the following guidance and observations.
1. "Counting" of URG Resources
In their written comments, the utilities should show how they have determined the availability and dependable capacity of their resources and clearly document the underlying assumptions.
2. Treatment of QF Resources
As noted in D.04-01-050, in "reviewing the utilities' filings, it appears that they already implicitly discount QF availability by using historical deliveries to the grid"(p. 170). This approach appears desirable in that it already takes into account that at any given time some proportion of QFs are either not operating or are dedicating their energy use primarily to their host facility. Use of this approach thus appears consistent with the use of a "net" methodology to determine reserve requirements associated with QFs adopted in this decision (Finding of Fact 41 p. 195).
As part of the RAWG process, participants offered two modifications to this approach to better reflect QF operating conditions: (1) separating out QFs that are located outside of the utility's service territory (thus raising deliverability issues); and (2) new QFs (that lack a history of operation.) Parties should be prepared to discuss adoption of these modifications.
Issues associated with the long-term future of QF resources nearing their contract expiration dates will not be considered in this workshop as the Commission has announced its intent to develop new procedural forums to address this issue.
3. "Counting" of DWR Contracts
D.04-01-050 concluded that:
California should receive full credit and value for the long-term contracts entered into by the DWR to help California meet its energy needs during the crisis. (Finding of Fact 22, p. 182)
Parties should be prepared to discuss how the utilities will implement this mandate.
4. Availability of Spot Capacity
A better approach to ensuring reliable service is to limit each utility's reliance on spot market purchases less than a month in advance to be based on reasonable (and perhaps even conservative) estimates of the energy available in this market...Thus, reasonable estimates, taking into account expected loads/resources in the Western region, and the procurement strategies of energy purchasers in the West would be helpful to define a reasonable estimate of appropriate reliance on the short-term energy markets. It is precisely this sort of issue that the CEC is examining as part of the Western Resources Assessment Team (WRAT) and as part of its IEPR process. (Findings of Fact 14,15 at p.180.)
5. "Counting" of other long-term contracts
This issue was raised by AReM and identified as a workshop issue. Parties should specifically identify "other" long-term contracts and discuss how each type of contract should be counted.
f. Treatment of Energy Efficiency,
Demand Response, Distributed GenerationIn D.04-01-050 we stated that:
In guiding the workshops, we reiterate our concern that these non-traditional resources be fully and fairly evaluated, and that any resource adequacy framework not unintentionally limit the procurement of these resources or bias resource procurement solely toward generation-only resources. Not counting these type of "soft" resources in the traditional resource adequacy frameworks could result in California having to pay twice for capacity thus limiting the cost-effectiveness of these programs. (p. 46)
We also noted that the workshop process should not be used to duplicate work that is currently being conducted in other Commission proceedings. For example, measurement and evaluation (M & E) criteria for energy efficiency are currently being developed in R.01-08-028. We do not see significant benefit in duplicating work already being performed elsewhere. Instead, parties should focus on how the results of these other proceedings can be incorporated into a resource adequacy framework.
D.04-01-050 already recognizes these other on-going proceedings, directing that:
We require utilities to present to the Commission in this rulemaking within twenty-days of this decision the methodologies they will use to ensure that forecasted measured savings of energy efficiency savings and demand reductions in utility long-term plans in this rulemaking are equivalent to the savings calculated for measures used in utility savings assumptions for procurement related energy efficiency programs submitted in R.01-08-028. (Ordering Paragraph 8, p. 196.)
And that:
In D.03-06-032, the Commission adopted demand response goals for each utility and directed that the IOUs include the MW targets for calendar years 2003 through 2007 in their procurement plans, specifically stating the filings in this proceeding should include: numeric targets coinciding with the findings in this decision; documentation of the amount of demand response (price-triggered) to be achieved by July 1 of each calendar year (with the exception of 2003, where the goals shall be met by the end of the calendar year); which programs and/or tariffs the IOU will rely upon to achieve the targets; and a contingency plan for covering capacity needs should the utility fall short of meeting the demand response goals. (Finding of Fact 64.)
Therefore, parties should be prepared to discuss:
a) What work is being done in other proceedings that is useful here?
b) How can this work be incorporated here?
c) What additional work is needed?
g. Deliverability Requirements
(initial discussion)The initial workshop will be used to begin the discussion of deliverability issues associated with energy resources, with particular emphasis on identifying options to be explored in the next April workshops.
Therefore, IT IS RULED that:
1. The respondent utilities, and any interested parties, shall file and serve written comments on all discussion issues identified above by March 4, 2004. Electronic service should be provided James Henry at jeh@cpuc.ca.gov.
2. All interested parties shall file and serve reply comments on March 11, 2004. Parties should focus their comments on identifying areas of potential consensus agreements.
3. A workshop will be held at the Commission's San Francisco offices on Monday, March 15, 2004, beginning at 9:00 a.m.
4. Further workshops will be held at the Commission's San Francisco offices on Monday, April 12, 2004 and Tuesday, April 13, 2004. If necessary, an additional workshop will be held on Wednesday, April 14, 2004.
5. Following the workshops, a written status report and recommendation for the Commission should be prepared by the workshop coordinator, James Hendry of the Division of Strategic Planning.
Dated February 13, 2004, at San Francisco, California.
/s/ Christine M. Walwyn
Christine M. Walwyn
Administrative Law Judge
ATTACHMENT 1
ATTACHMENT 2
CERTIFICATE OF SERVICE
I certify that I have by mail and by e-mail this day served a true copy of the original attached Assigned Administrative Law Judge's Ruling on the Scope and Schedule of Resource Adequacy Workshops on all parties of record in this proceeding or their attorneys of record.
Dated February 13, 2004, at San Francisco, California.
/s/ Antonina V. Swansen
Antonina V. Swansen
NOTICE
Parties should notify the Process Office, Public Utilities Commission, 505 Van Ness Avenue, Room 2000, San Francisco, CA 94102, of any change of address to insure that they continue to receive documents. You must indicate the proceeding number on the service list on which your name appears.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
The Commission's policy is to schedule hearings (meetings, workshops, etc.) in locations that are accessible to people with disabilities. To verify that a particular location is accessible, call: Calendar Clerk (415) 703-1203.
If specialized accommodations for the disabled are needed, e.g., sign language interpreters, those making the arrangements must call the Public Advisor at (415) 703-2074,
TTY 1-866-836-7825 or (415) 703-5282 at least three working days in advance of the event.
4 See for example, Sheffrin Tr. 4453-4454.
5 "The CEC's IEPR "information and analyses" should form the base case. If a utility does not find it appropriate to use that as its base case, it should include the IEPR case along with its preferred base case. The utility should report how and why the assumptions underlying its forecasts differ from those of the CEC forecasts." (Finding of Fact 51, p. 185.)
6 "We direct that future long-term procurement plans should reflect fully the expected range of prices of fuel and costs of purchased power at least up to the 95th percentile of the expected distribution." (p. 96.)
7 This requirement is consistent with the methodology used by the CEC in its IEPR.
8 The relevant excerpt of the ISO's filing is appended to this document at Attachment 1.