Schedule
Attached as Appendix A is a proposed schedule for the conduct of the proceedings on the applications. The parties should address any suggested changes to these schedules in their PHC Statements.
As part of the CEQA review process for A.04-12-007, the Commission's Energy Division will be scheduling Public Scoping Meetings in early June, 2005, to take comments from members of the public on SCE's proposed project, preferred route, and alternative routes. The Commission's Energy Division anticipates issuing a Draft Environmental Impact Report (EIR) addressing Segment 1 of the Antelope Transmission Project in September 2005, with a Final EIR in December 2005.