Draft Schedule

December 12, 2005 Comments due on this ACR

December 14, 2005 9:30 a.m. - 2:00 p.m. - Commission Workshop on Long-Term Procurement Planning

January 5, 2006 Post Workshop Comments

January 12, 2006 Post Workshop Reply Comments

January 2006 CAISO issues draft Transmission Study

Late January 2006 Establish New Long-Term Proceeding Rulemaking

Late January 2006 Staff Workshop on Need for New Generation (with Post Workshop Comments and Reply Comments Cycle)

February 2006 Prehearing Conference on new Rulemaking

Late February 2006 Staff Workshop on Integrated Resource Planning (two-day) + Staff Workshop on Procurement Policies to be considered in 2006 Filings (with Post Workshop Comments and Reply Comments Cycle)

Late February 2006 Parties File Briefs on Cost and Benefit Allocation of New Generation

March 2006 Staff Workshop on Long-Term Resource Plan Filings. All respondents will present draft proposals on contents of filings based on February workshops; each IOU will present draft plans in half-day workshops

Spring 2006 Draft decision in Confidentiality OIR Phase I

April 2006 Interim Draft Decision on New Generation + Cost and Benefit Allocation

April 2006 Ruling on Resource Plan Filings (if needed)

May 2006 Long-Term Resource Plans Filed Staff Workshops Hosted for Respondents to Present Plans

June 2006 Results of Quarterly Transaction Report Audits

July 2006 Hearings on Procurement Plans

August/Sept. 2006 Post hearing briefs and reply briefs

November 2006 Draft Decision to approve long-term procurement plans

(END OF APPENDIX A)

APPENDIX B

Transmission Planning Collaboration

This draft slides attached herein will be discussed in a workshop on December 14, 2005, from 2:00 p.m. to 5:00 p.m., at the Commission's Auditorium, 505 Van Ness Avenue, San Francisco. The workshop will be jointly hosted by the CAISO, Commission, and CEC.

CERTIFICATE OF SERVICE

I certify that I have by mail this day served the Notice of Availability a true copy of the original attached Assigned Commissioner's Ruling Regarding Next Steps in Procurement Proceeding on all parties of record in this proceeding or their attorneys of record.

Dated December 2, 2005, at San Francisco, California.

NOTICE

Parties should notify the Process Office, Public Utilities Commission, 505 Van Ness Avenue, Room 2000, San Francisco, CA 94102, of any change of address to insure that they continue to receive documents. You must indicate the proceeding number on the service list on which your name appears.

* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

The Commission's policy is to schedule hearings (meetings, workshops, etc.) in locations that are accessible to people with disabilities. To verify that a particular location is accessible, call: Calendar Clerk (415) 703-1203.

If specialized accommodations for the disabled are needed, e.g., sign language interpreters, those making the arrangements must call the Public Advisor at (415) 703-2074,

TTY 1-866-836-7825 or (415) 703-5282 at least three working days in advance of the event.

Peevey Brown NOA to Ruling

Previous PageTop Of PageGo To First Page