Word Document PDF Document |
CALIFORNIA PUBLIC UTILITIES COMMISSION
WATER DIVISION
PREPARING RESULTS OF OPERATION REPORTS
FOR GENERAL RATE INCREASE REQUESTS
OF WATER UTILITIES
OTHER THAN MAJOR COMPANIES
Standard Practice U-3-SM
SAN FRANCISCO, CALIFORNIA
Revised October 2003
STANDARD PRACTICE FOR PREPARING
RESULTS OF OPERATION REPORTS
FOR GENERAL RATE INCREASE REQUESTS OF WATER UTILITIES
OTHER THAN MAJOR COMPANIES
1. The purpose of this standard practice is to provide guidance to staff engineers and analysts (analyst) in the preparation of Results of Operation (RO) reports for Class B, C and D water companies' General Rate Case (GRC) requests. This report format may also be used for certification or investigation reports. RO reports constitute the principal staff showing of the basis for determining reasonable rate levels by the Commission for small water companies and must be completed prior to entering into negotiations with the utility.
2. This Standard Practice provides the basic information needed to prepare a simple GRC analysis. As with all Commission work the aspects of analysis described in this document are subject to change, may not be appropriate in a particular instance or may be too simple to adequately answer the questions the Commission is addressing. The analyst is responsible for taking whatever action is necessary to prepare as sophisticated a report as is required to meet the assignment. The analyst is also responsible for taking into account all available and relevant information in preparing all staff reports. This is best done by maintaining an active dialog with your immediate Senior and Supervisor. In all instances where their advice and guidance differ from this Standard Practice, that advice and guidance shall govern.
3. This document will be revised and updated as necessary and those updates will be available in the Water Division Standard Practices folder and on the Website.
4. Each staff member working on a GRC is responsible for doing a comprehensive study of the utility's operations, investment, financing arrangements, plans for the future and relations with its customers, as assigned. All of these factors are a part of the RO report.
5. In dealing with water company personnel, staff should always approach them in a friendly, helpful manner, avoiding any unnecessarily burdensome requests or directives where it is possible to do so and still properly exercise the Commission's jurisdiction.
6. Preparation of the report begins when the utility submits acceptable workpapers or, for outreach GRCs, when the staff member completes the workpapers. See U-9-W, Standard Practice for Processing Informal General Rate Cases of Water Utilities for the steps in processing a GRC. Of the five to six months allotted for a GRC, the analyst has three months to complete the RO report itself. Each report will normally take about 160 to 240 working hours. If the situation is complex, the report may take more time. If you need additional time to prepare the report, inform your Senior and Supervisor of the reasons and the expected delay and inform the company representative and the Branch Chief of the new due date.
7. Information for writing the report comes from the utility's filing, historical information about the utility, the staff visit, the public meeting and written comments, and from data requests. Data requests can be made either by telephone or in writing to the contact person shown on the first page of the utility's workpapers. If data requests are made over the telephone, record that information in your workpapers. Keep a copy of each formal data request and all responses in your workpapers.
8. The objective of an RO report is to present information for the Commission and interested parties that summarizes the operations and earnings of the utility, that explains the evaluation done by the staff and that formalizes the recommended actions to the Commission. Often the RO report will be the only record of the facts and methods used to determine reasonable rates. Thus the report should be as complete and professional as possible. A copy of the report and all workpapers must be filed by company name in the "Work Files" file cabinets in the storeroom, and an electronic version of the RO report must be made available to other staff by saving it as a PowerDocs document.
9. Each staff member shall keep his or her workpapers in reasonable order, properly identified and indexed, in an appropriate binder or folder and reasonably available to the Senior or Supervisor. The workpapers should include copies of information from prior rate cases when applicable. Please keep your workpapers available in your workspace while working on the case in case someone needs to refer to it when you are absent. Don't lock it up in your file drawer.
10. RO reports will follow the seven-part format shown in Attachment A. The report must include the name(s) of the staff member(s) who wrote the report and the sections each person was responsible for, if applicable. Paragraphs shall be numbered sequentially throughout the entire report. Tables should be embedded in the report as much as possible. Charts and maps, however, may be at the end.
(A) Section I, Introduction, includes a brief summary of the application and any history that is necessary to allow the reader to understand the company and the evaluations made in the report.
(B) Section II, System Description, is a description of the system itself, the personnel who operate the system, other business interests of the owner and any other situations that exist today that bear upon the elements of the RO Report.
(C) Section III, Summary of Earnings, is the section in which the allowable revenues are calculated. The Summary of Earnings table calculates the revenue requirement and thus determines the just and reasonable rates that the water company may charge. The revenues are calculated for a future test year under the anticipated operating conditions. Consequently the components that make up the rates are estimates. The purpose of a rate case is not to "make the utility whole" for incurred expenses, except for memorandum account and balancing account protection that was provided prospectively. The report should contain sufficient information and explanation to enable the Commission to set rates that will be reasonable in the near future to both the utility and its customers.
(D) Section IV, Rate Design, contains the details about how the rates were designed, including any deviations from the Commission's adopted design as described in Standard Practice U-6.
(E) Section V, Service, Field Visit, Notice and Public Response, describes these items.
(F) Section VI, Compliance, reviews any outstanding compliance orders of the Commission or DHS.
(G) Section VII, Recommendations contains boilerplate and any specific recommendations that apply in this case.
11. The analyst shall estimate the test year expenses for each category of expense applicable to the utility's operations. The Uniform System of Accounts (D.85-04-076, April 17, 1985) specifies what expense items should be included in each account.
12. Initially, consider the expenses booked by the utility and shown on its annual reports. (If the utility hasn't filed one or more annual reports, you should halt the processing of the GRC until the reports have been filed.) These expenses should be verified by audit during the site visit. Generally the staff should adopt the utility's estimate of expenses if the amounts are within 5% of the staff's estimate. If the booked expenses seem too high or too low, you may start your estimate of reasonable expenses based on what was adopted in the last GRC.
13. There are many ways of estimating expenses. The analyst or engineer is free to use the most appropriate that is acceptable to the Senior and Supervisor.
14. If the operations of the utility have changed (more people have been hired, some employees have been promoted, work has shifted from contract to in-house) then you must modify the estimates in each account accordingly. Since these estimates must be forward-looking, take into account any changes in expenses that will occur in the test year (if new DHS requirements are expected, include enough in rates to cover them, etc.)
15. The following methods are all valid approaches to estimating expenses:
(A) Constant dollar averaging. Using the audited figures for the accounting category being estimated, escalate all amounts to test year dollars. Use the escalation rates provided by ORA and use the labor or non-labor figures as appropriate. Take the average of these amounts. The calculation is as follows:
Acct. 650 Contract Work
Year Amount Esc 90-91 Esc 91-92 Esc 92-93 Total
1990 5,243 1.0375 1.0450 1.03 5,855
1991 7,045 1.0450 1.03 7,583
1992 17,012 1.03 17,552
------
Total 30,960
Test Year 93 (average) 10,320
(B) Trending. Looking at the example above, the analyst might be concerned that $10,320 wouldn't be enough for contract work, since the utility spent over $17,000 in 1992. If the analyst felt sure that the increase in contract work would continue, the proper procedure might be to trend, rather than average. The disadvantage of trending is that while averaging will make the utility whole in the long run, trending may overshoot or undershoot the correct figure. Nevertheless trending is also a valid way of estimation. The correct approach to trending is to do a least-squares estimate for the test year. The procedure for trending is as follows:
Method: Using a spreadsheet program or regression program, become familiar with the "Regression Analysis" section. For trending, regress the amounts being trended (dependent variable) against year, number of customers or water delivered (independent variable) as appropriate. Using the example numbers given above the table will look something like this:
A B C D E F
1 5,855 1 Regression Output
2 7,583 2 Constant -1367
3 17,552 3 Std. Err of Y Est. 3364.374
4 R Squared 0.858031
5 No. of Observations 3
6 Degrees of Freedom 1
7
8 X Coefficient(s) 5848.5
9 Std. Err of Coef. 2378.972
The calculation for the fourth year (1993) is:
-1364 + 4 x 5848.5 = $22,030
(C) Regression against multiple variables. Sometimes an expense will logically depend on more than one thing. For example, office expense may depend on number of metered customers, total number of customers and time. If you feel comfortable with it, you may use regression against more than one variable to calculate estimates. Discuss this procedure with someone who is familiar with it first, however. The Water Branch in ORA uses E-Views to estimate water sales and can provide advice and assistance. Using this method, you might identify customer-related costs, facilities-related costs and production-related costs and scale the allowable expenses by the number of customers, total plant or water delivered.
(D) Budgeting Do an actual budget based on historical expenses as modified by expected future conditions. One common example of this approach is the practice of taking the actual regulatory costs for the GRC you are working on and allowing the utility to recover an identical amount over the next three years as an estimate of future regulatory expenses. Again, you are not paying the utility back for the costs of the rate case you are working on, but rather you are using those costs to estimate future costs.
(E) Benchmarking Compare the utility you are working on with other utilities that are similar. We do not do "comparative ratemaking", that is, we do not raise or lower rates just because an nearby utility has higher or lower rates, but your personal knowledge of small water companies and information gleaned from investigating similar recent GRCs can provide valuable insight for estimating reasonable expenses.
(F) Consistency It is also important that the estimates you develop are consistent. For example, you will derive certain adopted quantities, such as projected sales. Since the purchased power expense will be proportional to expected sales, you shouldn't average or trend past purchased power costs, but rather, starting from expected sales, calculate, based on pump efficiency and existing electric rates, the expected purchased power costs. This makes these two figures consistent.
16. Purchased Power Expense Purchased power is calculated by taking the past three to five years of electric bills and analyzing them to see if there are any trends. The bills for the electricity for pumps are also evaluated separately based on the pump efficiency1. If the pump efficiencies are poor, staff should make an adjustment to the purchased power expense. If the efficiency is fair no adjustment is required, but the utility should be directed to improve the efficiencies of poor or fair pumps to good or excellent.
Table One: Plant Efficiency Ranges-Percent Wire to Water (from Case No. 10114)
Motor HP |
Poor |
Fair |
Good |
Excellent |
3-5 |
41.9 or less |
42-49.9 |
50-54.9 |
55 or above |
7.5-10 |
44.9 or less |
45-52.9 |
53-57.9 |
58 or above |
15-30 |
47.9 or less |
48-55.9 |
56-60.9 |
61 or above |
40-60 |
52.9 or less |
53.59.9 |
60-64.9 |
65 or above |
75 and above |
55.9 or less |
56-62.9 |
63-68.9 |
69 or above |
Contract Work, One big problem in estimating expenses for some small water companies occurs in the area of affiliate transactions. Some small water companies are affiliated with a well drilling company, or the owner may also run a development company or construction business. You must be extremely careful to make sure the ratepayers are paying only for work done for the utility and are paying only reasonable charges for supporting activities such as contract work, especially when the work is done by an affiliated company.
17. By far the best protection is for the utility to get at least three competitive bids for all major contract work. If the utility doesn't, it should present some kind of proof that the charges were reasonable. Similarly if the utility employs relatives of the owner for office work, you should include all reasonable office salaries (don't reduce salaries just because the employee is a relative) but the utility should present some kind of evidence that the salary level is reasonable.
18. Normally we allow in rates any formal contract that the utility has signed such as a lease for rent, or a contract with a union for wages. As a matter of policy these contracts are generally considered reasonable. If you disagree with the reasonableness of these contracts you have the burden of proof that the utility signed the contract imprudently. Either the utility was conspiring with the company contracted with to charge higher than normal fees (see affiliated transactions above) or the utility was generally imprudent and allowed itself to sign a contract that was unreasonable, figuring it could just pass the costs on in rates. Imprudence usually means that the company did not follow normal managerial or negotiation techniques when it negotiated the contract. Higher than normal costs compared to other contracts for similar services in the same area can indicate imprudence also.
19. Transportation. Transportation expense can be controversial if the owner is charging some or all of his (or his family's) automobiles to the utility. Similarly with rent, when the utility shares space or staff with the owner's other businesses. Often you will have to determine a "reasonable" expense base upon a similar utility's allowable expense to separate these costs out. If actual costs are not available, or if the employees use their own vehicles for company work, the allowable IRS cost per mile should be used to calculate that part of the expense.2
Example Calculations:
The estimates below are based on a 2-year lease agreement for a small passenger car/pickup. Other items taken into consideration are as follows:
1) Total cost $7,000
2) Leasing cost per month 200
3) Allowed mileage per year 15,000 miles
4) Gasoline cost per gallon $1.20
5) Estimated mileage per gallon 25
6) Insurance is part of the lease
7) Maintenance is part of the lease except dealership offers 2 year or 24,000 mile warranty.
Annual cost of lease $2,400
Insurance 300
Maintenance (miscellaneous items) 150
Fuel cost ($1.20/25 miles per gal. X 15,000) 720
Total cost $3,570 per year
1) Cost $6,200
2) 6.5% Sales Tax 400
3) License 250
Total cost $6,850
4) Principal and interest (7.5% for 8 yrs) 490
5) Assume 8 year life for vehicle
6) Allowed mileage per year 10,000
Annual principal and interest $5,880
Insurance (annual) 300
Fuel cost $1.20/25 mi per gal x 1000 480
Maintenance
2 tune-up @ $50 100
3 lube/oil @ $25 75
Tires (4 tires every 3 years at $300) 75
Battery (one in 8 years @ $80) 10
Brakes (one in 8 years at $400) 50
Transmission and misc. 150
Total cost $7,120
20. Management Expenses. Management Salaries are Account 671 and are described as "the portion of salaries of managers, owners, partners or principal stockholders of a utility chargeable to utility operations." This requires that the individuals whose salaries are being estimated must be owners or stockholders in the company, or designated as managers by their job title.
(A) The most important item here is to be sure that the time spent by the manager is really chargeable to the utility's operations. Especially with smaller water companies where the managers have other interests, you must separate activities that assist the water company from those that promote the other interests of the owner. It is even possible for an owner to delegate so much of the water company management to others that a management salary of zero is reasonable. Also remember that some part of the manager's (or an employee's) salary may be classified as capitalized labor, because it related to construction of facilities, and should be capitalized and not used in calculating the management salary.
(B) Management Salaries is an Administrative and General Expense and as such is not directly allocable to either plant or operations, so you can't rely on any one parameter (such as number of customers or total plant) to use when scaling the management salary. Consequently management salaries are somewhat subjective, but even so they need to be factually based.
(C) Past experience shows that we actually have few confrontations over management salaries. Commonly, the owner asks for a reasonably low salary because he is aware that his customers have a limit on what they can pay. If the owner has not requested a management salary at all, you should encourage him or her to do so.
(D) In order to evaluate the proper management salary, you should get as good an idea as you can about what the manager actually does typically. A manager who is planning the expansion of the company's service territory, negotiating with developers, arranging for low interest loans and interviewing prospective employees probably deserves a higher salary than a manager who is reading meters and writing out bills, although each activity can be a reasonable one for management.
(E) A good source of this kind of information is copies of the appointment book, daily log or diary of the owner or manager. You should identify the individuals named in the notebook or appointment pad and call some of them to ask about what went on at the meetings. This "audit" approach to verifying utility documents is a valid regulatory activity and not an intrusion into the owner's personal life, and verifying data should be a standard part of your approach to regulation.
(F) You can also ask for copies of an owner's or manager's timecard or other internal salary tracking document. Remember, however, that the temptation when a person is working for both regulated and unregulated firms is to bill as much work as possible to the regulated firm. Since there is no real way of double-checking timesheets, this method of tracking work cannot be used in isolation.
(G) The Association of California Water Agencies (ACWA) publishes a book of salaries paid by various government water agencies in California. This document can be a valuable source of reasonable salary level information. We have one available for reference.
(H) Another source of information is recent RO reports done by other water branch engineers and analysts. As mentioned above, generally you will find that management salaries as requested were found to be reasonable, but some reports will include the justification for the analysis that resulted in different levels.
(I) Naturally, everything else being equal, the larger the number of customers, the higher the management salary level, because the job requirements are probably more sophisticated and complex. Also, running a six employee utility is more complex than running a two employee utility, again, all other things being equal. However, most often, all other things aren't equal. A company that "farms out" much of its management work to consultants or contract employees might not justify as high a salary as the owner-manager who does much of the work herself.
(J) Customer satisfaction is also an important indicator of management capability. If the utility fixes leaks quickly, that indicates good management. Such indices as the location of the owner's home could have an impact, since absentee ownership is rarely as responsive as a concerned local owner who might even be providing water to his or her own household. The public meeting can give you an idea of the overall management quality. If customer complaints are being dealt with quickly and effectively, the manager is probably doing a better job than if problems languish for long periods. Overall rates are a factor as well. Prudent management can lower rates. If you believe that management has worked hard to keep overall rates low, a higher management salary might be appropriate.
(K) Professionalism and certifications are also significant. If the owner has an operator's permit and has been active in professional organizations that relate to water service, her expertise and value to the customers probably exceeds that of the owner who has no particular qualifications or professional or regulatory knowledge. This information is available by conversation with the owner.
(L) The quality of the management will have an impact on the salary level (as explained above), and it will also have an additional impact in that it might justify a higher allowed rate of return. This "double whammy" might at first seem to be unfair, but it is not. Part of the Commission's job is to substitute for the free market. In a competitive market, a utility that was run poorly would likely be unprofitable, and should pay its manager less. Conversely you should have no qualms about a utility paying an excellent utility manager what she is worth, and allowing a return near the high point of the range as well, to recognize excellent service.
(M) Preparation of the management expense estimate begins with an evaluation of the amount requested in the filing. If the owner has not requested a management salary, you should encourage him or her to do so. Conversely, you may find that the owner is requesting what you may consider an exorbitant amount for management salary. This claim actually may make sense if the owner is making a profit and taking the profit out in salary, for tax purposes, instead of as dividends, since dividends are taxed twice3. For our purposes though, you should separate the owners' management salary estimate from the return on ratebase estimate and use a reasonable salary in the Summary of Earnings.
(N) Most owners will be very happy to describe their system, the changes they have made and planned, and the troubles they have had. Listen carefully, both for the information you will get and for the evaluation you can do of the owner's knowledge and ability.
(O) Talk also, during the site visit, to as many employees as possible about the quality of utility management. Even though most employees are very loyal, they will still have opinions and desires that they have not satisfied. As with all verbal evidence, you should never rely on just one item or assertion. Claims and opinions must be verified by some factual or corroborating evidence before they are ever used in determining rates.
21. Regulatory Expenses. In accordance with usual practice4 we allow the utility to recover actual regulatory expenses for processing a GRC over three years as an estimate of the next GRC cost. Because the small water GRC procedure was created to try to minimize costs, you should avoid including regulatory expenses for meetings with staff, arguments and appeals that the utility makes in an attempt to increase its rates over what the staff finds reasonable. However if the utility "wins" the appeal, than the expense is reasonable. This rule gives the utility the proper incentive to look closely at the areas with which it disagrees and to see whether it is worth appealing them. If we didn't have this limitation, the utility or consultant would have the incentive to automatically appeal everything, since those extra costs would become part of the revenue requirement.
22. All other regulatory expenses should be included in rates, including postage and advertising expense for notices, rent for public meetings, etc. All costs of notice and compliance with Department of Health Services requirements should also be allowed. Generally, anything we or DHS impose on the utility should be funded in rates. Only if these expenses are impossible to estimate should they be recovered using a memorandum account.
23. Dues. Small water companies can be members of various professional organizations: California Water Association, American Water Works Association, National Association of Water Companies, etc. To the extent that participation helps the ratepayer, by making the owner or employees more knowledgeable, these costs should be allowed. For class B companies you should disallow the percentage of the association's budget that is used for lobbying or other non-educational activities, just as we do for Class A companies. For class C and D water companies probably no part of CWA or AWWA dues are really used for lobbying for the small companies. For those companies you should include 100% of CWA dues and dues for other associations if the amount isn't too high and if the utility employees are actively involved so that the ratepayers get something for their investment.
24. Fees. All franchise fees that the utility has to pay as a normal business expense should be included in rates, but they may require special treatment. If a municipality imposes a fee as a utility tax, the Commission has held that this should be listed separately on the bill, not hidden in rates, and should be paid by only those ratepayers that live within the municipality. This requirement for separate listing continues until surrounding municipalities or counties have raised similar fees to approximately the same level. This may be applicable to small companies if their billing system is sophisticated enough to do it, but is not required.
25. Contributions. Charitable contributions are not allowed in rates5. The Commission has held that if ratepayers want to contribute to a charity they can do so themselves. Any contributions the utility makes should come out of return on rate base. Dues and membership fees in recognized trade, technical and professional associations are allowed in rates if the amounts are reasonable and the utility is getting some benefit from them
26. Advertising and Public Relations. These expenses can be allowed to the extent that they benefit customers. This would include safety messages, essential customer service messages and conservation messages.
27. General Office. A General Office or headquarters of a Class B or C company provides administrative and general functions to its districts/regions. Its expenses need to be charged to the individual companies or districts. This is done by the "four factor" method. This calculates the revenues for the four factors of the company or district divided by the revenues of the four factors for all districts (the utility as a whole).
The four factors are:
a. gross plant
b. payroll
c. active connections
d. O&M expense
c. These costs are allocated based on the ratio of active connections in each district to the total of all districts
d. The three major expense items of a GO report are O&M, A&G, and Ratebase.
(1) O&M Examples: Payroll, Transportation, Purchased Services and Stores
(2) A&G Payroll, Pensions and Benefits (P&B), Transportation, Office Supplies, Property Insurance, Franchise requirements, Regulatory Commission Expense, Outside Services, Miscellaneous General Expenses, Maintenance of General Plant, Amortization, and Dues and Donations Adjustment. Payroll and P&B are the two biggest expenses.
(3) Rate base = plant - depreciation reserve - deductions + additions
For example: Plant Additions could be furniture, tools, equipment, automobiles, PC, software, etc. Depreciation reserve is the accrued depreciation on GO plant. Deductions are such items as deferred taxes, unamortized ITC. Additions are usually working capital.
28. Depreciation. Calculating depreciation can be a profession all its own. The Commission uses the straight-line remaining life method of calculating depreciation. This means that an item which cost $100 and is initially thought to have a 10 year life would undergo depreciation of $10 per year. If after 5 years ($50 remaining value) the Commission determined that the item had 8 years of remaining life instead of five, the depreciation over the last eight years would be $6.25 per year. The actual depreciation is included in rates as depreciation expense. The accumulated depreciation is subtracted from the original cost of the item to get the amount that is included in rate base. Standard Practice U-4-W describes the steps you should use to figure the allowable depreciation. Land, water rights, etc. are not depreciable.
29. For small water companies we use a flat 2.5% depreciation rate on total plant in service. This means that we believe that the average life of all of the facilities is 40 years. Some utilities may be able to justify a faster depreciation (greater than 2.5% per year). If the Commission has adopted a higher or lower depreciation figure in a previous rate case, that percentage should apply unless a new depreciation study is done. Obviously the depreciation used by the Commission and the depreciation used for income tax are not at all the same. You may have to explain this difference to the utility or the utility's accountant. For the larger utilities the difference between the taxes paid using tax (accelerated) depreciation and the Commission's straight-line depreciation can be significant. For these large companies the Commission "normalizes" this difference. This means that the utility books the difference between the taxes used for ratemaking and the taxes actually paid to an account (called the Deferred Tax Reserve Due to Depreciation account). The amount in this account is subtracted from working cash and results in a reduction in rate base. In this way the ratepayers get something back for the timing difference between ratemaking income taxes and income taxes actually paid. We normally do not bother normalizing taxes for class C and D utilities, because additions to plant, hence new depreciation expense, are not usually inform throughout a 12 month period, or even over two to three years, but it should be done for class B companies.
30. Note that with many new water systems the costs of operating and maintaining the whole system may be higher than reasonable due to there being a small number of customers for the built-out facilities. In this situation a "saturation adjustment" should be made to plant in service to include only plant that is used and useful6. For older system, inventory the plant to make sure retired plant has been removed.
31. Retirements are booked by decreasing Plan-In-Service by the original costs of the facilities being retired and decreasing Accumulated Depreciation by the same amount.
32. If facilities have been acquired by purchasing an existing mutual or municipal utility, the law requires that the Commission use purchase price for ratebase. The difference between the purchase price and the depreciated cost is entered as an "acquisition adjustment" that is amortized above the line for a period of time.
33. Rate base is the net dollar investment of the utility. Determine Utility Plant in Service (UPIS) by determining the original cost of the property to the person or entity first devoting it to public utility service. If the utility's records do not properly represent such original cost, it will be necessary to adjust the booked costs or to request that the utility have an original cost appraisal made. In the case of class D utilities the engineer or analyst may make such an appraisal and reserve study if approved by the Supervisor. Where an earlier appraisal has been made, that appraisal should form the starting point for the inclusion of subsequent plant improvements, additions and retirements. Once you have the Plant in Service, subtract the accrued depreciation (depreciation reserve), deferred tax reserve (if any), contributions and advances, and add working cash and materials and supplies (M&S) and any other adjustments. Accrued depreciation is the sum of the depreciation expense booked each year at that year's depreciation rate. Working cash is calculated using the method in Standard Practice U-4-SM. M&S is estimated by the engineer or analyst based upon the utility's actual operating needs. Rate Base ordinarily contains the following items, with appropriate adjustments or estimates:
Original Cost of Organization, Franchises, Water Rights and other Intangibles
Original Cost of Land that is used and useful for utility service
Original Cost of Depreciable Properties that are used and useful for utility service
Reasonable Allowance for Materials and Supplies
Allowance for Working Cash
Less: Contributions in Aid of Construction
Less: Unrefunded Advances
Less: Depreciation Reserve
Less: Deferred Tax Reserve (if any)
principal and interest surcharge.
34. Income Taxes. Income taxes are calculated on a pro-forma basis by applying the applicable tax rates to the utility's net revenue based on straight-line depreciation. If the GRC includes two test years, the prior year's state income tax is used as a deduction from the current year federal income tax for the second test year.7
35. Determining Rate of Return. The Audit and Compliance Branch of the Water Division will provide you with the latest values of allowable Rate of Return on equity (ROE) for each class of water company. For class C and D utilities this value will have a range of 50 basis points (one basis point is .01%) such as 13.8% to 14.3%. You should choose a value from this range based upon your best determination of the quality of service the utility is providing. If the utility is doing a good job of meeting the needs of its customers, it should receive a return near the high end of the range. If the utility responds poorly to customer complaints and is not meeting its public utility obligations, it should receive the minimum allowable return. For Class B utilities the Audit and Enforcement Branch will determine a utility specific reasonable ROR.
36. If the utility is financed in part by long-term debt, the situation is more complicated. You need to determine the capital structure, which considers the percentage of equity that is financing the company and the percentage of debt. For large utilities the capital structure normally ranges from 40% investment and 60% debt to about 60% investment and 40% debt. After you have determined the capital structure, you multiply the percentage of debt by the actual average cost of debt and the percentage of capital by the reasonable return on equity and add these two quantities to get the rate of return on ratebase. For example, assume a 70% equity, 30% debt class B utility is paying an average of 9% on its debt. Finance Branch informs you that the return on equity should be 11%. The rate of return is:
weighted cost of equity .70 x .11 = .077
+ weighted cost of debt .30 x .09 = .027
----
rate of return .104 = 10.4%
If the utility capital structure were 100% equity the ROR would equal the ROE and be 11%.
37. Operating Ratio This ratemaking method develops a revenue requirement where little or no rate base exists. The operating ratio is the ratio of operating expenses to operating revenues. Operating expenses include operations and maintenance expenses, annual depreciation on noncontributed facilities, amortization of multiyear expenses and applicable taxes. During the proceeding that approved the operating ration method an operating ratio of 80% was discussed, but there is no official "approved" operating ratio. The Pennsylvania Public Service Commission developed the following considerations:
(A) The operating ratios of comparable water or wastewater utilities.
(B) Coverage of actual hypothetical, or both, interest expense.
(C) A comparison of the cost of service with the cost of service of similar companies that do not employ an operating ratio rate methodology.
(D) Current market conditions, including price inflation.
(E) The quality of service and efficiency of operations.
(F) The rate case history.
(G) Whether there is any rate base and, if so, whether any depreciation expense is being claimed in the filing.
(H) An acquisition adjustment, if any.
(I) Financial resources.
(J) The fairness of the resulting return.
An increase or decrease in operating revenues shall be determined by dividing the utility's reasonable and legitimate operating expenses by the target operating ratio determined in paragraph (2), and subtracting that amount from the test period operating revenues.
38. Calculating the Net-to-Gross Multiplier. The net-to-gross multiplier is calculated as follows:8
1. Uncollectables 0.00752% ___________% 0.07520%
2. 1 - uncollectables ___________% 99.92480%
(100% - line 1)
3. Local franchise 0.77470% ___________% 0.77412%
(.77470 x line 2)
4. Business license 0.10216% ___________% 0.10208%
(.10216 x line 2)
5. Subtotal ___________% 0.95140%
(line 1 + line 3 + line 4)
6. 1 - subtotal ___________% 99.04860%
Remaining amount subject to California Corporation Franchise Tax (CCFT) and Federal Income Tax (FIT)
7. CCFT 8.84% ___________% 8.75589624%
(line 6 x 9.3%)
8. FIT 34% ___________% 33.676524%
(line 6 x 34%)
9. Total taxes paid ___________% 43.3838202%
(line 5 + line 7 + line 8)
10. Net after taxes ___________% 56.6161798%
(1 - line 9)
11. Net-to-Gross multiplier ___________% 1.7662795%
(1 / line 10)
41. Revenues. Once you have determined the reasonable expenses and depreciation, calculate the return by multiplying the ROR by the ratebase. Using these figures, you can now calculate the revenue requirement. Simply multiply the return by the net to gross multiplier, add the expenses and depreciation and you have the revenues. If the utility has contracts to provide water, assume that the utility can renegotiate the same percentage increase for those contracts as for tariffed service9. This will lower the revenue requirement because only the revenues from tariffed customers are included.
PROCEDURE FOR CALCULATING THE SECOND TEST YEAR
FOR WATER UTILITIES WITH THREE YEAR RATE CYCLE
In general rate cases for most large water utilities, there are two test years and one attrition year. The calculation for the revenue increase for the first year is the difference in revenues between the adopted present rates and the authorized increased rates at the adopted number of customers and sales of all the service classes. The revenue increase for the second test year is adjusted for customer growth in the second test year, so it is not just the mathematical difference between revenues of the first and second test years. The revenue for the attrition year is calculated by applying the operational attrition plus financial attrition times the adopted rate base times the net-to-gross multiplier. The revenue increase for the attrition year is the difference in revenues between the attrition year and the second test year.
For the second test year, the increase in gross annual revenues consists of two parts: increase due to customer growth and the increase due to results of operation such as increases in expenses and rate base. However, an increase in gross annual revenues due to customer growth is not an increase in rates, even though it increases gross annual revenues. This increase in customers therefore, needs to be compensated for in determining the annual dollar and percent increases. The method shown on the attached sheets shows how to calculate the actual gross revenue increase without the influence of customer growth.
TO DETERMINE REVEUE INCREASES
1. Obtain number of customers and total consumption for each block for both test years.
2. For First Test Year
(a) Obtain adopted present revenues from decision. ($2,383,200)
(b) Obtain authorized revenues from decision. ($2,533,900)
(c) Calculate revenue and percent increase. ($150,700; 6,32%)
3. For Second Test Year
(a) Calculate revenue using second test year customers and first test year authorized rates. ($2,555,672)
(b) Obtain authorized revenue from decision. ($2,649,800)
(c) Calculate dollar and percent increase using (a) and (b).
4. See appendix C.
42. If the utility is new, often there will be installed facilities that are not yet used and useful. The facilities are removed from rates by use of a "saturation adjustment"10. A saturation adjustment is a procedure whereby excess or overbuilt utility plant, financed or installed with equity capital, is excluded form rate base in determining the rates a utility is authorized to charge for service. Water Division procedures and Commission policy are based on precedent set in Decisions No. 50971 (1/10/55) and No. 56261 (2/18/58) in Application No. 34541 by Big Bear Pines Water Company. The Commission reasoned that an adjustment was proper to protect the interests of rate payers in those situations where an extensive water system has been constructed but with a significant portion of the lots to be served remaining undeveloped for an extended period following initial construction of the water system. This adjustment, in time, became known as a saturation adjustment and has been used by the Water Division and adopted in numerous proceedings. Recent uses of this adjustment occurred in Decision No. 92796 (3/17/81) in Application No. 59530 by Freshwater Valley Estates Water Company and in Resolution No. W-3004 (7/21/82) for Bear Trap Ridge Water Company.
Over Build Utility Plant
The first unit of a new development when a water system is certificated by the Commission has customarily been financed with equity capital. Most of these developments are soon fully developed with homes; and additional tracts are added with the extension of the water system being financed under the water main extension rule. When this occurs, there is no basis for a saturation adjustment. However, in some cases, water systems have been initially installed in large tracts with equity capital; and have not subsequently been fully developed, resulting in a large rate base per customer. Even if the developer has left the scene, it is reasonable to assume that most developers would attempt to recover development costs including the water system in the sale of the lots. The fact that there is an extensive water system with a resulting large capital investment per customer should not be allowed to result in excessive rate base and rates. Usually, such developers transfer these water systems to some local individuals. Except under extreme hardship conditions, (operating losses), the new owners should not expect the water customers to bear all the costs of operating such a water system until the tract is almost fully developed. Almost fully developed is defined as a tract which is 85% developed, with the remaining 15% to be developed within the next five (5) years.
During the 1960s, Boise Cascade and a few others developed very extensive lot type-land subdivisions. They were largely located in the Sierra foothills with clubhouses and recreational facilities. While the lots were soon sold by very extensive sales promotion activities, construction of homes has been at a slow rate in most of these areas. Most lot purchases spend many years making the monthly payments on their lots before deciding to build a home. Since the water systems for most of these developments were installed with equity capital and many are still less than 50 percent developed, the required saturation adjustment has a major effect upon the recommended rate increase.
Application of Saturation Adjustments
The assigned Analyst, in all general rate proceedings, should review the files on all previous rate proceedings to check if a saturation adjustment had previously been used. The need for a saturation adjustment requires a through analysis in each individual situation where there is partial development in the utility's service area. The need for saturation adjustment should be based on a single, fixed percentage of development:
a. The requested rate increase is based upon revenues to cover operating expenses for the entire utility plant and full rate of return on the entire utility plant (rate base)
b. A distinct portion of the service area has plant facilities (mains, services, source of supply, treatment plant, and/or tanks) installed, but the vast majority of the lots in that portion are undeveloped.
c. The plant facilities (mains, services, source of supply, treatment plant, and/or tanks) are installed and in rate base; but less than one-half of the lots are developed.
A saturation adjustment should not be used in the following situations where there is a partial development (however the Analyst should make a rough estimate of the effect of a saturation adjustment on the requested rate increase):
a. The original tract (unit) may be only partially developed; but the utility is serving a considerably larger number of customers in other tracts financed under the water main extension rule. For example, if the original tract is only 70 percent developed, a 30 percent saturation adjustment on the water system necessary to serve that tract, while technically applicable, might have no practical effect on the rates.
b. The utility is requesting little or no return on its investment or simply a reduction in its operating losses, making it obvious that a saturation adjustment would not result in any rate adjustment. In such cases, the decision or resolution should state that the low rate of return or large operating loss at the requested or authorized rates would be subject to a saturation adjustment if the utility as requesting rates which might give the utility an excessive return on the adjusted rate base.
c. There is a solid indication that a substantial commercial or industrial facility will be developed in the community within one year of the pending rate increase. That is, there is reason to believe that the proposed new facility would increase the work force in the area and create a demand for additional housing in the utility's service area. In this circumstance, the application of a saturation adjustment might not be appropriate.
Mechanics of Saturation Adjustment
As stated above, the saturation adjustment factor should not be based upon a rigid adherence to a single, fixed percentage of development, i.e: number of residences divided by total number of lots. This percentage is a good starting point, but the Analyst should analyze the apply good judgment to adjust the percentage in obtaining a reasonable adjustment factor.
Case 1 -- Large portions (Tracts) of service area
with no development.
a. Exclude all utility plant facilities (sources of supply, treatment plants, tank, and/or transmission mains) in those portions if none of the facilities are required to serve the developed portion of the service area.
b. If some of the utility plant facilities are required to serve the developed portion, the Engineer needs to analyze each of those individual plant facilities to determine the amount to be excluded from rate base. The way to accomplish this is to:
(1) Determine the required sizes of the transmission main (diameter), source of supply (gpm), treatment plant (gpm), and storage tank (gallons) to serve the developed portion.
(2) Determine the reasonable cost of those smaller sized plant facilities (using same time value of dollars as installed plant facilities); and
(3) Excluded plant is then total cost minus the reasonable cost form Item (2). In this analysis, the Engineer/Analyst should determine if it would be a prudent investment to have an oversized facility as compared to the cost to augment that facility at some later date.
Case 2 -- Scattered development throughout the service area.
a. There are situations where the undeveloped lots have been caused by the actions of the homeowners. In some subdivisions with small minimum width lots, some homeowners have purchased three adjoining lots and then built on the middle one. The total number of lots in the service area may then be artificially too high and unrealistic because the homes would be too densely packed for a rural type of living environment. The Engineer/Analyst should analyze the water supply demand requirements of the plant facilities for the lesser number of homes to determine if the plant facilities are indeed excessive or over-built for the existing type of development. The saturation adjustment if applicable, would then be based upon the realistic, existing type of development rather than the initially proposed development.
b. Where development follows the pattern that was initially proposed, a saturation adjustment based upon the number of homes to the number of total lots is satisfactory for most situations. However, the Analyst should analyze the development to determine if, for example, 50 percent of the plant facilities are necessary to provide service to a 40 percent development.
Appendix B shows a simple example of the mechanics of using a saturation adjustment factor in a rate proceeding. Since the Commission's water regulatory lag plan is predicated upon a general rate proceeding every three years, the Analyst should use a three year growth period. The Analyst should use the number of connections (completed homes) at the midpoint of the three year growth period. Once the Analyst determines the percentage of saturation of completed homes, the net investment in water facilities (original cost less depreciation) should be reduced by that percentage. Similarly, depreciation expense and ad valorem taxes related to these facilities should be reduced by this percentage for ratemaking purposes only. This type of adjustment does not result in any adjustment to the records of the utility.
43. A percentage of the fixed costs (costs that don't vary with water use) is used to calculate the service charge. For Class D companies the percentage is 100%, for class C companies it is 65% and for Class B companies it is 50%. The rest of the fixed costs and all variable costs are included in the quantity charge. Service charges are scaled by the capacity equivalent of the service connection. All adjustments should be rounded to the nearest cent.
44. The detailed procedures for classifying and calculating rates are discussed in Standard Practice U-7, "Rate Design." Any change in the utility's current rate structure should be tempered by considering the impact on the customers at various usage levels. One desired attribute of rate design is rate stability so new rate designs are usually phased-in. The standards for this are that no customer should receive over 200% of the system average rate increase and that the rate increase is usually held to not more than a 50% increase in the first test year, with the rest being made up in a second test year. Small systems with low existing rates are generally exempt from this requirement.
45. Normally, Class C and D utilities request increases for the second and third year by using the CPI process (see Standard Practice U-27-W), but Class B, C and D utilities are also eligible to file for a second test year and an attrition year.11 If a Class C or D utility has noticed its customers a larger increase than it finally gets, and if there is justification for a "larger than CPI" increase for the subsequent years that is still less than the noticed amount, staff can authorize the utility to file for those higher increases in those years.12 Of course, the resolution can authorize a Class B utility to file for CPI increases in lieu of a second test year and attrition year also.
46. Branch policy requires a field investigation of the applicant's system and service area before the RO report is finalized. This gives the staff a chance to review the operation of the water system, inspect the company's records and talk to the employees and customers. Branch also requires a public meeting. At the public meeting the utility should describe the need for the increase and staff should discuss the ratemaking process. Staff should not commit to any request made at the public meeting, except a request for a copy of the final staff report, but keep good notes and carefully review all requests and information. Discuss any service problems with the utility and, if necessary, require a follow-up report on the resolution of these problems.
47. The Branch requires compliance with Standard Practice U-9-W with respect to Notice. When the utility's filing is complete, staff provides a notice of the rate increase to the utility and the utility mails and the time, date and place of the public meeting to each customer. A subsequent notice is required when the rate case is completed and the new rates go into effect.
48. Check with the Consumer Affairs Branch of the Public Affairs Division on complaints. Check the correspondence file for the utility for letters we have received. Discuss in the RO report the number and types of letters Branch received after the notice was published and how you dealt with them.
49. Check out a pressure meter before you make your field trip and compare the tested pressures to G.O. 103. Discuss any pressure or other service problems with the utility.
50. Check the Compliance Report to see if there are any outstanding compliance items. All items must be cleared, or an acceptable plan must be proposed, before any rate increase can be allowed.
51. As mentioned before, the utility must file annual reports. If any annual reports haven't been filed, the utility must file them prior to receiving a rate increase.
52. The recommendations may be just standard boilerplate, (see Attachment A) but if there are any special requirements, they should be spelled out clearly. Examples include:
Filing of up-to-date rules, current service area maps, and sample forms.
Installation of metering devices on sources of supply.
Refunding of any overcharges or billings at non-tariffed levels.
The rate increase may be made contingent on the utility completing repair or replacement of deficient facilities.13
53. Once you have completed all sections, provide the draft report to the Supervisor for review. After the report has been approved, forward it to the Branch Chief, change your PowerDocs security on the document to All DocsOpen Users, Read Only, and put a hard copy version in the files.
California Public Utilities Commission
Commission Advisory and Compliance Division
Water Utilities Branch
STAFF REPORT ON THE ADVICE LETTER
GENERAL RATE INCREASE OF
REGULATED WATER COMPANY
Report written by
I. M Goode
Assistant Utilities Engineer
October 199_
I. INTRODUCTION
Regulated Water Company (RWC), filed a Advice Letter 13-W with the Water Utilities Branch (Branch) on August 5, 199_. RWC requested authority under General Order 96 and Section 454 of the Public Utilities (PU) Code to increase rates for water service by $12,330, or 112.46%. The purpose of the rate increase is to recover mounting operating expenses and costs relating to plant improvements. RWC's request shows that 199_ gross revenues of $10,964 at present rates would increase to approximately $23,294 at proposed rates, allowing a rate of return on rate base of 4.76%. RWC serves approximately 62 flat rate, and 10 metered rate customers in its service area in and around the community of Any City, Sierra County.
The current rates were established on August 24, 1926 pursuant to Resolution No. W-____ which authorized an increase in revenue of $7,100 or a general rate increase of 121.7%.
II. SYSTEM DESCRIPTION
RWC is a corporation owned by John M. Smith serving approximately one square mile of territory located in the foothills of the Verygreen National Forest. The utility's administrative and operations staff consists of John M. Smith, Manager and Operator and June Smith, Office Secretary. Thirty five of the seventy two customers in the service area are part-time residents, while the remaining customers are moderate to low income families who reside there year around. The system has lost four customers over the past three years but the Branch believes that this decline has stabilized. RWC may have an opportunity to connect two other systems to the current facilities. These systems are located on either side of the utilities service area, and, if inter-connection is made, the utility will have an additional 14 customers.
RWC's water source is a natural spring that flows out of the side of the mountain. The utility pipes the water about 400 feet down the hill to two filtration tanks. The first tank uses a ten micron rated filter bag to remove any impurities in the water. The second tank contains a five micron rated filter bag for further purification. The water then flows about thirty feet to a 5,000 gallon redwood storage tank. The utility is currently installing an additional 6,500 gallon steel tank to supplement the current storage and to more closely meet the Department of Health Services' (DHS) Waterworks Standards. There is no meter at the water source; however, through monitoring, RWC estimates the spring can deliver about eighty gallons per minute (gpm). Because there have been no apparent water outages in the system, it is assumed that the combination of source and storage capacity is adequate. RWC is seeking new water sources. The system does exhibit sub-standard pressure in homes near the storage facilities. The utility is placing additional storage to alleviate this problem. Most of the distribution system consists of two inch pipe installed in the early nineteen hundreds. RWC is working to update the system to meet current standards of design and construction as outlined in General Order 103. The system is not looped and contains three dead ends that Mr. Smith flushes twice a year.
About 2,000 feet of the distribution mains run underneath State Highway XX. Since this system is in a logging area, trucks running on the highway often cause breaks in the lines, due to their heavy loads. The cost of relocating these lines is about $22,000. Because this amount will increase RWC's rate base by more the twenty-five percent, Mr. Smith is seeking Commission authority to make the improvement. Mr. Smith has a unique opportunity to split the cost of the replacement with the area fire department. By using a dual trench both RWC and the fire department can substantially reduce the cost of the project, thus easing the burden on ratepayers. Without the necessary replacement the system runs the risk of costly repairs and possible water outages for extended periods of time.
III. SUMMARY OF EARNINGS
The Branch made an independent analysis of RWC's summary of earnings for the test year 199_ as seen in appendix A. The appendix illustrates RWC's and the Branch's estimates for the 199_ test year operating revenues, operating expenses and rate base at both present and proposed rates.
The Branch analyzed each operating expense category listed in appendix A. The Branch's estimate differs with RWC's estimates in contract work, transportation, insurance, employee pensions and benefits, professional services, regulatory commission expense and taxes other than income.
RWC's system is entirely gravity operated, therefore the Branch agrees with the utility's estimate for purchased power.
The utility estimates test year materials expense by averaging the past two years' data. Due to inadvertent accounting discrepancies in this category the Branch was unable to compute a three year average. The Branch reviewed RWC's materials expense account for 199_ and discovered additional errors. The Branch notes that the account contains expenses that should either be included as a rate base item under material and supplies, or that are inappropriate expense items. The Branch believes its estimates is more reliable because it removes the utility's accounting errors and uses actual 199_ data.
RWC's and Branch's estimates for contract work differ. The utility hires an individual to clear snow blocking the access road to the storage and filter location during the winter months. The utility did not include this expense in any account. RWC also did not include water testing costs in its estimate. The Branch includes both these expenses in its contract work category and thus believes its estimate is more accurate.
The utility's estimate for the other plant maintenance category is inconsistent with the three year recorded average. The Branch has reviewed this estimate and believes it is accurate because existing accounts contain all other expenses for the test year.
The utility's bases its office supplies and expense category estimate on projected costs. The three year average is inappropriate due to inadvertent accounting errors. Specifically, the utility occasionally booked costs associated with organizational dues to this category. RWC correctly removed these costs for the test year estimate, therefore, the Branch believes the utility's estimate is reasonable.
RWC's estimate for office services and rentals is the costs for a room in the Smith's home dedicated for utility use. Furthermore, the basement of the Smith home serves as a storage area for RWC's inventory. The Branch believes this estimate is justifiable because it is based on actual square footage, and reasonable per square foot charges.
Office salary and Management salary estimates by RWC cover time spent operating and maintaining the utility. The Branch has reviewed the estimates and believes they are reasonable.
RWC's transportation expense estimate uses 199_ recorded and 199_ expected costs. The Branch's estimate differs in that the utility included the cost of insurance for the vehicle. Moreover, some estimated expenses are non-recurring, thus the Branch amortized these expenses over three years. The Branch feels its estimate is more accurate due to the utility's bookkeeping errors.
The utility's test year insurance estimate is the 199_ recorded cost for property and general liability. The Branch also used 199_ recorded costs but added the cost of vehicle insurance to its estimate. The Branch believes its estimate is more accurate because it adheres to the current Uniform System of Accounts (USOA) guidelines.
The utility used payroll taxes as an estimate for the employee pension and benefits expense category. The Branch removed this inadvertent bookkeeping error for its estimate and thus believes its estimate is reasonable.
RWC used the cost of accounting and bookkeeping and the cost associated with filing the rate increase request as its estimate of professional services. The utility also used 199_ recorded data. The Branch removed the costs of filing for the rate increase and used 199_ recorded data for the other expenses. The Branch feels its estimate is more plausible because of the utilities accounting error.
The Branch used the utilities recorded expense for filing this rate increase request as its estimate for the regulatory commission expense. The Branch spreads this cost over three years. Since the utility placed this expense in the professional services category the Branch believes its estimate is reasonable.
The utility's general expense estimate uses the cost of 199_ membership dues to various water organization. It is inconsistent with the three year average; however, the Branch has reviewed the estimate and considers it reasonable.
The Utility's estimate and the Branch's estimate for taxes other than income differ in that the utility included additional property tax on land purchased in 1989. After the investigation the Branch learned that the current county property tax bill includes tax on this property. The Branch used the current tax bill and the payroll tax calculation as its estimate for this expense and thus considers this estimate sound.
The Branch helped the utility determine an accurate estimate for depreciation expense and average depreciation reserve. The Branch's investigation and calculation is attached as Appendix E.
RWC's summary of earning submitted with its rate increase request shows a rate of return on rate base of 4.76%. The Branch's recommended revenue increase will produce a rate of return of 7.77%, below the 13.9% and 14.4% standard rate of return range recommended by the Finance Branch of the Commission Advisory and Compliance division for small, 100 percent equity financed water utilities. The utility requested the rate increase be limited to 100 percent for all classes of ratepayers. The utility realizes that the new rates will not generate the authorized return on rate base.
IV. RATE DESIGN
The utility's current rate structure consists of two schedules: Schedule No.1, General Metered Service, Schedule No. 2, Residential Flat Rate Service. The Metered Service Schedule contains one rate block for all water quantity sold.
The Branch helped the utility in the rate design process and thus no differences exist. The new rate schedules can be seen in Appendix B. The Branch applied a 100 percent increase to the flat rate schedule, the 3/4 inch readiness to service charge and the water quantity charge. The remainder of the metered rate service charges are adjusted using the current service charge allocation ratios as outlined in Standard Practice U-7. All adjustments are rounded to the nearest cent. Because almost all of RWC's operating expenses are fixed costs, and most of the customers use the flat rate schedule, the Branch did not apply the one hundred percent of fixed costs policy for metered service charges when designing rates. Additionally, the Branch discovered four flat rate customers being charged rates that are not in the flat rate schedule and corrected for this oversight.
V. SERVICE, FIELD VISIT, NOTICE AND PUBLIC RESPONSE
Branch staff members A. Perfect and I. Goode conducted a field investigation of RWC's system and service area on August 28 and 29, 199_. Mr. Smith directed a tour of the service area and explained the operation of the water system. Ms. Smith made the company's records available for inspection and provided other assistance. Sally Jones, RWC's Accountant, provided additional expense information after the public meeting.
The utility mailed a notice of the proposed rate increase to each customer on August 9, 199_. Over the past three years, the Consumer Affairs Branch of the Public Affairs Division received no complaints regarding the RWC system. The Branch received four letters of complaint regarding the proposed rate increase. The complaints dealt mainly with the amount of the increase, citing a similar rate increase three years ago, but others claimed that part-time residents receive unfair treatment. All letters were responded to.
On August 28, 199_ the Branch held an informal public meeting in RWC's service area. A. Perfect, Senior Utilities Engineer, explained Commission rate setting procedures and Mr. Smith explained the need for the rate increase. Mr. Wrainey Storm, and Ms. Pat Hand of the State Office of Drinking Water (ODW), attended to answer any questions regarding water quality and service. They spoke about the new monitoring requirements imposed by the State and the impact these regulations would have on RWC.
Of the twenty one ratepayers present, ten spoke out during the meeting. All stated they are satisfied with the water quality and service, and commended Mr. Smith on the job he was doing. Most of those who spoke said they felt part time users should not pay the same rate as full time residents. Additionally, most customers thought rates are getting too high, or that Mr. Smith may be making unnecessary investments.
Pressure tested in the area ranged from 18 psi at the higher elevations of the system to 165 psi at the lowest end of the system. Mr. Smith has installed pressure reducers in those homes that exceed current standards.
RWC is violating two provisions of G.O. 103. Section II.3.a. states that the utility shall maintain normal operating pressures of not less than 40 p.s.i.g, and not less than 30 p.s.i.g at times of peak seasonal loads. Certain residents at the higher elevations receive only 18 to 20 psi. Section II.4.a of G.O. 103 states that the utility shall install a suitable measuring device, or otherwise determine the production at each source of supply. At this time RWC is unable to determine its water production. Mr. Smith is currently working on solving the low pressure problem by installing a supplemental storage tank at a higher elevation. The Branch recommends RWC install a meter or otherwise devise a method to measure the production capacity of the water source.
VI. COMPLIANCE
There are no outstanding Commission orders requiring system improvements.
The utility has been filing annual reports as required.
VII. RECOMMENDATION
The Branch recommends that the Commission authorize an increase of $12,042 or 107.02%, which would increase estimated annual revenue from $11,252 at present rates to $23,294 at adopted rates. A residential flat rate customer would realize an increase on a monthly bill from $12.00 to $24.00, or 100%. This increase will produce a 7.77% return on rate base.
Proposed Findings:
After investigation by the Branch:
a. The Branch's recommended Summary of Earnings (Appendix A) is reasonable and should be adopted.
b. The rates recommended by the Branch (Appendix B) are reasonable and should be authorized.
c. The quantities (Appendix D) used to develop the Branch recommendations are reasonable and should be adopted.
d. The Branch recommends that a meter be installed at the water source or other means of measuring the production capacity as required be Section II.4.a of G.O. 103, and RWC be allowed to file for an offset rate increase to recover costs upon completion of the project.
e. RWC should be allowed to make the 2000' main replacement and file for an offset rate increase to cover costs and reflect the new rate base.
f. Any offset rate increase request should be analyzed using an 11.00% return on investment.
Regulated Water Company, Inc. | |||||||||||
Water Division | |||||||||||
Summary of Earnings | |||||||||||
Test Year 1999 | |||||||||||
Utility Estimated |
Branch Estimated | ||||||||||
Present |
Requested |
Present |
Requested |
Recommended | |||||||
Item |
Rates |
Rates |
Rates |
Rates |
Rates | ||||||
Operating Revenue |
|||||||||||
Metered |
$ 61,856 |
$ 82,551 |
$ 68,017 |
$ 82,405 |
$ 61,400 | ||||||
Operating Expenses |
|||||||||||
Purchased Power |
$8,370 |
$ 8,370 |
$ 8,370 |
$ 8,370 |
$ 8,370 | ||||||
Employee Labor |
9,428 |
9,428 |
- |
- |
- | ||||||
Materials |
5,195 |
5,195 |
5,025 |
5,025 |
5,025 | ||||||
Contract Work |
1,596 |
1,596 |
1,596 |
1,596 |
1,596 | ||||||
Transportation |
2,397 |
2,397 |
1,403 |
1,403 |
1,403 | ||||||
Other Plant Maintenance |
172 |
172 |
172 |
172 |
172 | ||||||
Office Salaries |
4,188 |
4,188 |
2,465 |
2,465 |
2,465 | ||||||
Management Salaries |
12,570 |
12,570 |
11,975 |
11,975 |
11,975 | ||||||
Employee Pension & Health Benefits |
2,633 |
2,633 |
1,793 |
1,793 |
1,793 | ||||||
Uncollectibles |
354 |
354 |
170 |
206 |
154 | ||||||
Office Services & Rent |
494 |
494 |
494 |
494 |
494 | ||||||
Office Supplies |
1,930 |
1,930 |
1,930 |
1,930 |
1,930 | ||||||
Professional Services |
1,417 |
1,417 |
1,294 |
1,294 |
1,294 | ||||||
Insurance |
1,380 |
1,380 |
1,877 |
1,877 |
1,877 | ||||||
Regulatory Expenses |
1,250 |
1,250 |
748 |
748 |
748 | ||||||
General Expenses |
430 |
430 |
430 |
430 |
430 | ||||||
Subtotal |
$53,804 |
$ 53,804 |
$ 39,743 |
$ 39,779 |
$ 39,727 | ||||||
Depreciation |
6,984 |
6,984 |
4,440 |
4,440 |
4,440 | ||||||
Property Taxes |
3,334 |
3,334 |
829 |
829 |
829 | ||||||
Payroll Taxes |
2,232 |
2,232 |
1,392 |
1,392 |
1,392 | ||||||
Income Tax |
267 |
3,647 |
4,866 |
8,097 |
3,380 | ||||||
Total Deductions |
$ 66,621 |
$ 70,001 |
$ 51,270 |
$ 54,537 |
$ 49,768 | ||||||
Net Revenue |
$(4,765) |
$ 12,550 |
$ 16,747 |
$ 27,868 |
$ 11,632 | ||||||
Rate Base |
|||||||||||
Average Plant |
$177,538 |
$177,538 |
$ 167,238 |
$167,238 |
$ 167,238 | ||||||
Ave. Accumulated Depreciation |
89,054 |
89,054 |
85,414 |
85,414 |
85,414 | ||||||
Net Plant |
$ 88,484 |
$ 88,484 |
$ 81,824 |
$ 81,824 |
$ 81,824 | ||||||
Plus Working Cash |
4,489 |
4,489 |
3,312 |
3,315 |
311 | ||||||
Materials and Supplies |
- |
- |
1,000 |
1,000 |
1,000 | ||||||
Rate Base: |
$ 92,973 |
$ 92,973 |
$ 86,136 |
$ 86,139 |
$ 86,135 | ||||||
Rate of Return |
-5.13% |
13.50% |
19.44% |
32.35% |
13.50% | ||||||
APPENDIX B
Regulated Water Company, Inc.
Water Division
Schedule No. 1
Applicable to all metered service.
Green Terrace and vicinity, adjacent to Highway No. 1,
located approximately one mile northwest of Delta, Gamma County.
Per Meter
Quantity Rates: Per Month
All Water, per 100 cu. ft. $ 0.20 (R)
Service Charge:
(D)
For 3/4-inch meter $ 16.40 (I)
For 1-inch meter 27.15 (I)
The Service Charge is a readiness-to-serve charge which is
applicable to all metered service and to which is to be added
the monthly charge computed at the Quantity Rates.
SPECIAL CONDITIONS:
1. All bills are subject to the reimbursement fee set forth in Schedule No. UF.
APPENDIX C
Page 1
Regulated Water Company, Inc.
Water Division
Expenses: Per Year
1. Purchased Power:
Southern California Edison Company
Quantity 65,388 Kwh
Average Cost per Kwh $ 0.1280
Total Purchased Power $ 8,370
2. Purchased Water None
3. Payroll:
Labor None
4. Ad Valorem Taxes:
Tax Rate 1.001216%
Assessed Value $82,824
Total Tax $829
5. Service Connections:
Meter Connections 251
Flat Rate Connections None
6. Water Sales(ccf) 59,989
California Corporate Franchise Rate : 8.84% |
|||
State Tax |
Federal Tax | ||
Item |
1999 |
1999 | |
1 |
Operating Revenue |
$ 61,400 |
$ 61,400 |
2 |
Operating Expenses |
$ 39,727 |
$ 39,727 |
3 |
Property Taxes |
$ 829 |
$ 829 |
4 |
Payroll Taxes |
$ 1,392 |
$ 1,392 |
5 |
Depreciation |
$ 4,440 |
$ 4,440 |
6 |
Taxable Income for CCFT |
$ 15,012 |
|
7 |
State Tax, $800 minimum |
$ 1,327 |
$ 1,327 |
8 |
Taxable Income for FIT |
$ 13,685 | |
9 |
Federal Income Tax |
$ 2,053 | |
10 |
Total Tax |
$ 1,327 |
$ 2,053 |
APPENDIX D
Regulated Water Co., Inc.
Escalation Factors
l. Office of Ratepayer Advocates: Estimate of Non-Labor and Wage Escalation Rates for 1998 through 2000 from the August 1998 DRI/McGraw-Hill Review of U.S. Economy, dated August 31, 1998
2. ORA August 1998 Summary of Compensation Per Hour, dated August 31, 1998.
SAMPLE SATURATION ADJUSTMENT CALCULATION
1. A 100-home tract was developed with equity capital in 1964.
2. Analysis indicates that 85% of the homes require 100% of the plant, therefore 85 homes (.85 x 100) is the number that reasonably should have been developed.
3. Only 31 homes have been constructed and connected to the water system.
4. Currently, about 2 customers are being added to the water system annually.
5. The growth at the midpoint of a three year period is 3 additional completed homes, ie. (3 x 2)/2.
6. For future test year, tract is (31 + 3)/85 or 40% saturated14
7. Net Investment = Initial Investment-Depreciation
= $28,614 - 15,306
= $13,308
8. Saturated Net Investment = $13,308 x 0.40
= $ 5,323
9. Rate Base
Average Net Plant $ 5,320
Contributions (1,300)15
Working Cash 700
M & S 170
Rate Base $ 4,890
Rate Base/customer = $4,890/34 = $144/customer
So-Cal Water Co.
San Gabriel District
TOTAL METERED SERVICES
----------------------1988--------------------------:-------------------1989---------------------------------
Number Authorized : Number @1998 Rates Authorized
Customers Rates Revenue : Customers Rates Revenue Rates Revenue
5/8 10023 4.60 553270 : 10271 4.60 566959 4.80` 591610
3/4 44 4.90 2587 : 44 4.90 2587 5.10 2693
1 870 7.00 73080 : 872 7.00 73248 7.30 76387
1 1/2 84 9.25 9324 : 84 9.25 9324 9.60 9677
2 178 14.00 29904 : 178 14.00 29904 14.60 31186
3 16 25.50 4896 : 16 25.50 4896 26.50 5088
4 9 33.00 3564 : 9 33.00 3564 34.00 3672
6 3 63 2268 ; 3 63.00 2268 66.00 2376
8 0 87 0 : 0 87.00 0 91.00 0
10 0 126 0 : 0 126.00 0 169.00 0
sub 11227 678893 : 11477 692750 722689
:
3 332600 0.5853 194684 : 334100 0.5853 195562 0.6055 202284
Over 3 2805500 0.5853 1642171 : 2817500 0.5853 1649195 0.6055 1705884
sub 3138100 1836855 : 3151600 1844758 19088168
:
Total Meter Rev. 2515748 : 2537508 2630856
:
:
Flat Rate Rev. :
Prv.Fire 35 27.70 11664 : 27.77 11664 27.77 11664
Other 6500 : 6500 7300
Total Flat Rev. 18164 : 18164 18964
:
TOTAL REVENUE 2533912 : 2555672 2649819
:
--------------------------------------------------------------------------------------------------------------
1988 Present Rev. 2383912
1988 Auth. Rev. 2533900
$ Increase 150700
% Increase 6.32
1989 Rev. @ new 1988 rates 2555672
1989 Auth. Rev 2649800
$ Increase 94128
% Increase 3.68
1 Memorandum from John D. Reader to Anand V. Garde, June 13, 1980, Subject: Rate Making Adjustments for Pump Efficiency Ratings 2 Memorandum from Wesley M. Franklin to the Hydraulic Branch Technical Staff, April 17, 1985, Subject: Vehicle Expense - Standard Mileage Rate of 20.5 Cents 3 . Corporate profits are taxed at the corporate tax rate. If any of the remaining profits (retained earnings) are distributed as dividends, those dividends are taxable to the recipient as personal income. 4 Memoranum from Bruno A. Davis to Tony Irving, Advisor to Commissioner Grimes, December 8, 1982, Subject: Ratemaking Treatment Accorded Utilities' Regulatory Commission Expense 5 D.67369, June 11, 1964, Pacific Telephone and Telegraph Company 6 D.62183, June 27, 1961, Hesperia Water Company Finding of Fact 5: