Discussion of Transmission Project

We discussed several transmission projects at the start of the PHC, and interested parties met informally with Energy Division to explore them further and report on their status after the lunch hour. I briefly summarize these projects below.

There is not consensus among the parties whether this upgrade would be economic to ratepayers, relative to other approaches to relieving congestion (e.g., a remedial action scheme), and there has been no analysis to date on the magnitude of the economic benefits. Upgrades to the Miguel-Mission line are estimated to cost in the range of $25 to $30 million. The project involves replacing conductors on existing structures, with an existing right of way. SDG&E will be discussing the environmental and certification requirements associated with this upgrade with Energy Division. 6

Tie Line 649

Coral Power proposes that the Commission consider reconductoring of approximately 5 ½ miles of a 69 kV line (tie line 649) to accommodate 140 MW of new generation coming on line this fall under three-year contracts. SDG&E argues that this project does not belong in this proceeding, due to its size and scope. In addition, SDG&E contends that the upgrade is not needed until the third unit comes on line and, to date, that project has not broken ground or signed a contract. According to SDG&E, the remedial action scheme that would be needed if the third project comes on line would only be required during off-peak periods. The ISO has just sent SDG&E a letter to look at potentially reinforcing the line for the third unit, and SDG&E is reviewing that letter. 7

San Francisco-Peninsula Area

A stakeholder group continues to meet to discuss upgrades to the Jefferson-Martin 230 kV line that are needed for reliability reasons and that may also have potential economic benefits by reducing reliability must-run (RMR) requirements. The stakeholder group process was initiated in response to an ISO report: San Francisco Peninsula Long-Term Electric Transmission Planning Technical Study, issued in October 2000. That report, in turn, came out of a study of the December 8, 1998 outage that was also the subject of a Commission proceeding. The group had their most recent meeting in June and another one is set for late September. PG&E reports that it is working very closely with the City of San Francisco to develop a proposed route for the project. Since much of the line is anticipated to be underground through the City, there are a number of challenges to finding a route and defining feasible alternatives and associated costs. The schedule developed during the stakeholder meetings still calls for the project to be operational by September of 2005. PG&E plans to file a CPCN application at the Commission in September of 2002. PG&E considers this to be among their highest priority projects and states that they are taking all necessary steps to move it forward as expeditiously as possible. None of the parties at the PHC believed that this project could be ready for evaluation during fall hearings. 8

Greater Bay Area

The City and County of San Francisco also brought up the Greater Bay Area project that PG&E has been exploring for both reliability and economic (RMR) reasons. This project is in very early stages of planning, and the alternatives are not yet defined. 9

Techachapi

1 See PHC Reporter's Transcript (RT) at 108-109. Also, see RT at 114-115, 148-149 from the summer evidentiary hearings. 2 PHC RT at 169-176. 3 Ibid. at 116. 4 Per D.01-03-077, Southern California Edison Company was directed to increase Path 26 transfer capability by 200 MW by installing wave traps, and this work was completed in May, 2001. 5 Ibid. at 117, 154-159. 6 Ibid. at 113-114, 159-162. 7 Ibid. at 162-169. 8 Ibid. at 117-118, 137-144. 9 Ibid. at 144-145. 10 Ibid. at 118-122, 146-154.

Previous PageTop Of PageNext PageGo To First Page