4. Discussion

4.1 Definition of Renewable Fuel

4.3 Eligible Project Costs

For Renewable Fuel Systems

4.5 Assurances Against Fuel Switching

4.6 Other Issues

Findings of Fact

Conclusions of Law


"Under the self-generation program authorized today, program administrators shall offer the following incentives on a uniform, statewide basis:

Incentive category

Incentive offered

Maximum percentage of project cost *

Min. system size

Max. system size

Eligible Technologies

Level 1

$4.50/W

50%

30 kW

1 MW

_ Photovoltaics

_ Fuel cells operating on renewable fuel

_ Wind turbines

Level 2

$2.50/W

40%

None

1 MW

_ Fuel cells operating on non-renewable fuel and utilizing sufficient waste heat recovery

Level 3-R

$1.50/W

40%

None

1 MW

_ Microturbines operating on renewable fuel

_ Internal combustion engines and small gas turbines operating on renewable fuel

Level 3-N

$1.00/W

30%

None

1 MW

_ Microturbines operating on non-renewable fuel, utilizing sufficient waste heat recovery and meeting reliability criteria

_ Internal combustion engines and small gas turbines operating on non-renewable fuel, both utilizing sufficient waste heat recovery and meeting reliability criteria


"For the purpose of the self-generation program adopted today, `renewable fuel' is defined as follows:


"A renewable fuel is a non-fossil fuel resource other than those defined as conventional in Section 2805 of the Public Utilities Code, that can be categorized as one of the following: solar, wind, biomass, digester gas, or landfill gas. A facility utilitizing a renewable fuel may not use more than 25 percent fossil fuel annually, as determined on a total energy input basis for the calendar year."


"In addition, applicants for Level 1 fuel cell projects and Level 3-R projects are required to:


· Provide a written affidavit stating that the unit will comply with the program renewable fuel requirements. The length of this commitment shall be the same as the equipment warranty requirement discussed above for each category. The document signed by the applicant shall represent a binding legal contract with an enforcement mechanism, such as a payment retraction clause. The working group described in this decision shall develop the affidavit language, in consultation with Energy Division.


· Within 90 calendar days of the date the program administrator issues a Conditional Reservation Letter, submit an equipment purchase order that indicates the fuel cleanup equipment as a separate invoice item.


· Demonstrate the availability of an adequate average flow rate of renewable fuel to produce electricity at the unit's full rated capacity, or an appropriate de-rated capacity if supplemented with fossil fuel. This information shall be collected on the program application as well as verified during the on-site inspection prior to approval of the incentive. Units whose annual fuel consumption exceeds the available renewable fuel plus the allowable nonrenewable supplement will not qualify for a differential incentive.


"Although the utilities may exercise full discretion in moving funds from the Level 2 and 3 incentive categories to Level 1, a utility must seek approval through advice letter prior to shifting additional funds into either the Level 2 or 3 categories."

9. Program administrators shall file the first on-site monitoring report on fuel-use within six months of the effective date of this decision, and every six months thereafter until further notice by the Commission or Assigned Commissioner.

10. The Assigned Commissioner may, for good cause, modify the filing dates required by today's decision.

11. Unless otherwise indicated, all filings shall be filed at the Commission's Docket Office and served electronically on all appearances and the state service list in this proceeding. Service by U.S. mail is optional, except that one hard copy shall be mailed to Judge Meg Gottstein at P.O. Box 210, Volcano, CA 95689. In addition, if there is no electronic mail address available, the electronic mail is returned to the sender, or the recipient informs the sender of an inability to open the document, the sender shall immediately arrange for alternate service (regular U.S. mail shall be the default, unless another means-such as overnight delivery-is mutually agreed upon). The current service list for this proceeding is available on the Commission's web page, www.cpuc.ca.gov.

Introduction

Background


"...electricity generation facilities using power sources other than those defined as conventional in Section 2805 of the Public Utilities Code, provided no more than 25 percent fossil fuel is used by the facility annually, as determined on a total energy input basis for the calendar year. Specifically: biomass, digester gas, geothermal, landfill gas, municipal solid waste, small hydropower (30 MW or less), solar photovoltaic, solar thermal, and wind."


A renewable fuel is a non-fossil fuel resource other than those defined as conventional in Section 2805 of the Public Utilities Code, that can be categorized as one of the following: solar, wind, biomass, digester gas, or landfill gas. A facility utilizing a renewable fuel may not use more than 25 percent fossil fuel annually, as determined on a total energy input basis for the calendar year.


"While it is logical to consider such facilities as providing renewable power, the incentives, that we are offering here, relate to capital cost." (p. 27, emphasis added)

Incentive category

Incentive offered

Maximum percentage of project cost

Minimum system size

Maximum system size

Eligible Technologies

Level 1

$4.50/W

50%

30 kW

1 MW

_ Photovoltaics

_ Fuel cells operating on renewable fuel

_ Wind turbines

Level 2

$2.50/W

40%

None

1 MW

_ Fuel cells operating on non-renewable fuel and utilizing sufficient waste heat recovery

Level 3-R

$1.50/W

40%

None

1 MW

_ Microturbines operating on renewable fuel

_ Internal combustion engines and small gas turbines operating on renewable fuel

Level 3-N

$1.00/W

30%

None

1 MW

_ Microturbines operating on non-renewable fuel, utilizing sufficient waste heat recovery and meeting reliability criteria

_ Internal combustion engines and small gas turbines operating on non-renewable fuel, both utilizing sufficient waste heat recovery and meeting reliability criteria


"Although the utilities may exercise full discretion in moving funds from non-renewable self-generation categories to the renewable category, a utility must seek approval through advice letter prior to shifting additional funds into either of the non-renewable categories."
(p. 21).


"Although the utilities may exercise full discretion in moving funds from the Level 2 and 3 incentive categories to Level 1, a utility must seek approval through advice letter prior to shifting additional funds into either the Level 2 or 3 categories."


"In order to qualify for incentives, a fossil-fired facility must make a demonstrable contribution to the reliability of the transmission or distribution system. We expect the utilities to work with those customers seeking incentives for fossil-fueled facilities to determine whether a proposed facility will enhance transmission or distribution reliability and document those benefits prior to approving an incentive payment."
(D.01-03-073, pp. 25-6)


A renewable fuel is a non-fossil fuel resource other than those defined as conventional in Section 2805 of the Public Utilities Code, that can be categorized as one of the following: solar, wind, biomass, digester gas, or landfill gas. A facility utilizing a renewable fuel may not use more than 25 percent fossil fuel annually, as determined on a total energy input basis for the calendar year.


We note that organic material in a form that requires processing beyond the cleanup procedures described above does not constitute a renewable fuel for purposes of this program.


"Although the utilities may exercise full discretion in moving funds from the Level 2 and 3 incentive categories to Level 1, a utility must seek approval through advice letter prior to shifting additional funds into either the Level 2 or 3 categories."

 

2001

   

2002

   
     

weighted

   

weighted

Administrator

# apps

average

average

# apps

average

average

PG&E

27

$9.18

2.986265

25

$8.33

2.509036

SCE

4

$9.24

0.445301

12

$10.88

1.573012

SDREO

5

$8.96

0.539759

3

$9.99

0.361084

SoCalGas

3

$8.15

0.294578

4

$9.09

0.438072

             

Total number applications:

 

83

     

Sum of weighted averages:

$9.15

     
             

Level 1 project specific data points not available. Average for Level 1 was computed

using weighted averages for summary data supplied for program years 2001 and 2002.

             
             

Project No.

$/W Cost

Administrator

     
             

Level 2 Projects

         
             

Project 1

$5.74

SCE

       

Project 2

$6.25

PG&E

       

Project 3

$6.99

'

       

Project 4

$8.50

'

       

4 projects

$6.87

average

       
             

Level 3 Projects

         
             

Non-renewable fuel microturbines - SGIP data

     

Project 1

$1.16

PG&E

       

Project 2

$3.35

'

       

Project 3

$3.50

'

       

Project 4

$5.05

'

       

Project 5

$1.60

SDREO

       

Project 6

$1.71

'

       

Project 7

$1.87

'

       

Project 8

$2.25

'

       

Project 9

$2.54

'

       

Project 10

$2.64

'

       

Project 11

$2.85

'

       

Project 12

$3.14

'

       

Project 13

$3.40

'

       

Project 14

$3.43

'

       

Project 15

$4.36

'

       

Project 16

$5.64

'

       

Project 17

$1.13

SoCal

       

Project 18

$1.22

'

       

Project 19

$1.40

'

       

Project 20

$1.55

'

       

Project 21

$2.00

'

       

Project 22

$2.00

'

       

Project 23

$2.11

'

       

Project 24

$2.11

'

       

Project 25

$2.14

'

       

Project 26

$2.14

'

       

Project 27

$3.47

'

       

Project 28

$3.69

'

       

Project 29

$3.84

'

       

Project 30

$5.67

'

       

30 projects

$2.77

average

       
             

Renewable fuel microturbines - SGIP data

     

Project 1

$2.59

SDREO

       

Project 2

$3.08

'

       

Project 3

$3.33

'

       

Project 4

$4.33

PG&E

       

4 projects

$3.33

average

       
             

Renewable fuel microturbines - Capstone supplied bids

   

Project 1

$3.27

         

Project 2

$4.20

         

2 projects

$3.74

average

       
             
6 Refer to D.01-03-073, quoted in Section 1 above: "While it is logical to consider such facilities as providing renewable power, the incentives, that we are offering here, relate to capital cost." (p. 27; emphasis added.) 7 To date, the only active Level 1 applications are for photovoltaic systems. Program-wide system costs average approximately $9.15 per installed watt. See Attachment 1,  

8 For example, if the per-watt cap is increased to $10/watt, and a project that produces 100,000 watts costs $9/watt, the 50% limit becomes binding at a subsidy level of $450,000. However, if capital costs escalate to $9.50/watt under this incentive structure, the 50% limit is no longer binding at $450,000. Rather it becomes binding at a higher subsidy level ($475,000). 9 Attachment 1, p. 5. 10 Ibid., p. 6. 11 D.01-03-073, p. 24. 12 Petition, p. 5. 13 Capstone attempts to quantify the "environmental benefits" of micro-turbines operating on landfill gas by stating NOx emission levels. However, the record still lacks adequate data on the environmental characteristics of renewable fuel micro-turbines, engines and fuel cells (the only Level 1 technology with operational emissions). Therefore, we do not have a reasonable basis for applying the 50% incentive level adopted for Level 1 technologies to Level 3-R technologies. 14 We specifically include these type of costs to reflect the preference given to renewable or super clean technologies, per Assembly Bill 970, and do not extend this treatment of clean up costs to projects that utilize nonrenewable waste gases. 15 Per D.01-03-073, the program administrators are required to perform program evaluations and load impact studies for the self-generation program by outsourcing to independent evaluation consultants. (pp. 35-36.) The schedule for the consultants' evaluation reports is set forth in the Administrative Law Judge's Ruling On Schedule For Evaluation Reports, dated April 24, 2002. 16 Attachment 1, p. 9. 17 Ibid., p. 10. 18 See D.01-03-073, pp. 25-26, D.01-06-035, p.9. 19 D.01-03-073, p. 26. 20 See Attachment 1, pp. 10-12. 21 Ibid., p. 15. 22 D.01-03-073, p. 21. 23 Codified as Public Utilities Code Sec. 399.15(b)(6) and (7). 2 In this report we apply equal treatment to all Level 3 technologies operating on renewable fuel. Capstone's petition addresses only microturbines, but a differential incentive for renewable fuel operation should also apply to engines and small gas turbines. 3 D.01-03-073, p. 26 fn. 7. 4 Capstone attempts to quantify the "environmental benefits" of microturbines operating on landfill gas by stating NOx emissions levels. However, the record still lacks adequate data on the environmental characteristics of renewable fuel microturbines, engines, and fuel cells (the only Level 1 technology with operational emissions). Therefore, we do not have a reasonable basis for applying an incentive appropriate to Level 1 technologies to Level 3 technologies. 5 We note that the reply comments incorrectly indicated "kWh" instead of "kW" units.

6 The dollar per Watt costs for Level 2 fuel cell projects range from $5.74 to $8.50, for an average of $6.87/W.

7 The program administrators have jointly selected a single consultant to conduct the program evaluation.

Previous PageTop Of PageGo To First Page