A. Overview of Positions of Parties
PG&E's primary criterion for setting any cap is to ensure DA CRS payback by the expiration of the DWR contract term in 2011. PG&E argues that the DA CRS shortfall should be recovered as quickly as possible to minimize risk to bundled customers, and tying the payback duration to DWR contract length is consistent with approach applied to CTC recovery in AB 1890. PG&E thus proposes that the cap be set at 4 cents per kWh based on its analysis that full payback to bundled customers of the DA CRS obligation can thereby be achieved by 2011. PG&E's recommendation for a 4 cents cap is predicated on the Navigant base case run that assumes Off System Sales (OSS) at only 50% of Market Clearing Price (MCP). If the Commission concludes that a different scenario or set of forecast assumptions are more reasonable that would still enable the DA CRS shortfall to be paid off by 2011 with a cap lower than 4 cents, then PG&E agrees that such a lower cap should be considered. PG&E recommends that the DA CRS assumptions used be consistent with those DWR uses to develop the 2003 DWR power charge revenue requirement. For 2003, PG&E calculates the DA CRS indifference amount to be $310 million.
SCE proposes an increase in the cap to 3 cents per kWh, with the provision for further increases thereafter if the DA CRS undercollection for SCE ever exceeds $500 million. SCE believes its proposal would avoid making DA uneconomic and would achieve payback by 2011 when most DWR contracts expire. SCE's proposed assumptions for evaluating the cap correspond most closely to DWR's Base Case Scenario 5, which assumes a 100% Market Clearing Price (MCP) for excess energy sales, and a 9% interest rate. Under Scenario 5, SCE is predicted to accumulate a maximum undercollection of $498 million and to recover the undercollection by year 2010. SCE's proposes to recover the undercollection as quickly as possible, but in no event extending beyond 2011. Using Scenario 5 as a guide, therefore, SCE recommends increasing the DA CRS cap to 3.0 cents per kWh to guard against a High Case CRS scenario occurring (Scenario 21), which would create a maximum undercollection of $674 million for SCE.
SDG&E supports continuation of the 2.7 cents cap, and believes that DA CRS undercollections resulting from the current cap will be manageable and permit payback within a reasonable timeframe. SDG&E believes that Scenario 6 incorporating the Base Case with OSS at 100% of MCP at a 4% interest rate reflects the most realistic set of assumptions for forecasting multi-year DA CRS impacts.8 SDG&E warns that there is a substantial, immediate risk in setting the cap too high, in that once DA viability is impaired, perhaps even modestly, parties and the Commission may not realize the harm until it is too late-"when DA customers' businesses evaporate, relocate, or are emaciated sufficiently that they cannot pay their electricity bills in due course." (See Exh. 181, p. 6.)
TURN's primary position is that no cap be permitted unless it is financed by DWR bonds rather than by bundled ratepayers. TURN believes that imposition of any CRS cap with bundled ratepayer financing of the shortfall results in cost shifting in violation of the intent underlying AB 117. Assuming that the Commission chooses to continue imposing some level of cap, however, TURN proposes that its duration be as short as possible. In any event, TURN argues that all outstanding DA CRS obligations due to bundled customers should be fully repaid within the term of the DWR contracts, which expire in 2010 or 2011.
TURN believes that the existing undercollections should not be allowed to grow any larger. TURN proposes that the CRS cap be set at least high enough to recover current year CRS charges even if there is no immediate recovery of the undercollections already accrued. To meet these conditions, TURN argues that the cap must be set at no less than 4 cents per kWh. TURN expresses concern that any lower cap would create an unacceptable risk that bundled customers would never be repaid. TURN also contends that now is the better time to collect DA CRS costs rather than later since bundled rates are still quite high for all of the utilities.
ORA supports the proposals of PG&E and SCE to increase the cap to 4 cents for PG&E, and 3 cents for SCE. ORA believes these cap levels address the risks associated with what it characterizes as an involuntary loan that bundled customers must bear. ORA also believes that a cap of 3 cents for SDG&E "may be justified" because SDG&E's retail rates are currently closer to those of SCE than of PG&E. ORA takes no position favoring any one Navigant scenario over another, but objects to DA parties' general characterizations of DWR's forecasts as being overly "conservative" in order to satisfy bondholders. ORA argues that DWR's witness characterized the forecasts as a "best guess" that were not biased.
Farm Bureau represents approximately 90,000 members in California that are overwhelmingly on bundled service. Farm Bureau proposes replacing the current DA CRS with two separate components: (1) a "Local Utility" (LU) surcharge consisting of CTC that would be levied without being subject to a cap, and (2) a DWR surcharge consisting of DWR bond charges and going-forward charges that would be capped at the current level of, which would be capped at 2.7 cents. Farm Bureau originally proposed the LU surcharge include the HPC (for SCE only), but now proposes that SCE's 2.7cents per kWh cap include the HPC.
Under this approach, the current DA CRS cap would be separated out prospectively to acknowledge the responsibility of all customers for CTC payments.9 Farm Bureau argues its proposal offers shorter payback periods, and thus greater intertemporal equity for both bundled and DA customers. If its proposal to bifurcate the surcharge is denied, Farm Bureau supports a 4 cent per kWh cap. Farm Bureau argues that segregating the surcharge into two components simplifies the administration of a cap on collection of the shortfall.
Farm Bureau argues that except for a somewhat low gas forecast, the base case provides the best tool to analyze impacts from the OOS and interest rates on varying cap levels. Nonetheless, Farm Bureau believes that no one particular scenario is reliable enough to form the basis for establishment of a cap. To the extent a particular scenario is selected, Farm Bureau believes the base case should be used with a 75% Off System Sales factor.
Parties representing DA interests propose no change in the existing 2.7 cents cap. CLECA witness Barkovich believes that the existing cap will yield a payback period of less than 10 years under the most reasonable set of assumptions underlying the Navigant modeling scenarios. CLECA believes that both URG and DWR forecasts are overstated, and that accordingly, the actual DA CRS payback period will be considerably less than Navigant's forecasts indicate. CLECA argues that raising the cap as high as 4 cents would render many DA contracts uneconomic. However, CLECA presented no evidence to support this assertion.
AReM likewise argues that the current 2.7 cents cap can be maintained while keeping DA undercollections to a minimum and achieving payback of the DA CRS obligation within three to five years, depending on the utility involved. AreM based its analysis on a hybrid approach that it calls "Scenario 25." This hybrid combines the gas price, market entry, and CTC assumptions from the ProSym low case with the DA penetration rate assumptions from the ProSym base case. AreM also assumes a 100% MCP and an average interest rate based on three-month commercial paper.
Strategic Energy believes that Scenario 14, incorporating the "low" ProSym case and OSS priced at 100% of MCP, represents the most likely set of assumptions modeled by Navigant. Strategic Energy argues that this scenario provides for payback within eight years or less under the existing 2. 7 cents cap. Strategic thus advocates no change to the existing cap, but expresses the concern that even under the current 2.7 cents cap, DA customers are experiencing a serious fiscal impact. We note, however, that the utilities have not reported any substantive migration of DA customers back to bundled service despite impact of the current 2.7 cent DA CRS.
CMTA believes that Scenarios 6 and 14 are the most plausible of those presented by Navigant. The only difference between these two scenarios is that Scenario 6 represents the base case while Scenario 14 represents the low case. Between Scenario 6 and 14, the longest payback period is forecast to be between eight and 11 years for PG&E.
CMTA opposes linking the cap to a required payback of the undercollection by the end of the DWR contract term or to any maximum permissible undercollection level. CMTA argues that in numerous cases, the collection of revenues authorized by the Commission is not concurrent with the incurrence of costs. For example, the DWR Bonds will not be paid off before the end of the DWR contract term in 2011. CMTA also disputes the claim that a higher cap is needed now to accelerate the payback period and thereby reduce bundled customers' risk of default. CMTA argues that an immediate increase in the cap could drive some DA customers out of business and exacerbate the risk even more that those customers would not contribute toward paying off the undercollection.
B. Discussion
As a basis for setting an appropriate cap, we first address the appropriate criteria to balance the dual goals of bundled customer indifference and DA economic viability. We next consider the range of DA CRS forecast scenarios and their relative likelihood of being accurate. Then, based upon our assessment of the range of forecasts, we determine the level of cap for each utility that would be required to satisfy our identified criteria.
1. Cap Criteria for Assuring Bundled Customer Indifference
As mentioned above, our criteria for setting a cap must preserve bundled customer indifference. To meet this goal, we must provide assurance that undercollections from DA customers resulting from the cap will be repaid in full to bundled customers, with compensatory interest, over a reasonable period of time. We conclude that a reasonable time period for full repayment of the DA CRS undercollection should not exceed, at the longest, the term of the DWR contracts, due to expire in 2011. Preferably, the payback period will be much shorter. The longer the DA CRS is required to be in place, the longer the DA market will have to bear those costs, and the harder it will be for DA to compete in the future. We do not wish to be penny wise and pound foolish, preserving DA now, only to annihilate DA in the future through prolonged charges of the DA CRS.
We disagree with those parties that claim there is no reason to tie the duration of DA CRS repayment to any particular term, including the duration of the DWR contracts. As a general principle of regulation, it is desirable to charge customers based on the costs to serve them, thereby matching customer charges with the costs of service rendered to serve them. There are sometimes unusual situations, however, where the matching of costs incurred with service rendered is problematic. Due to the extraordinary magnitude of the DWR contract costs incurred during 2001, for example, current customers were not charged for the full level of such costs. The unrecovered portion was deferred to future periods and financed through long-term bonds.
Similarly, a portion of DWR power charges that are not financed by the DWR bonds result in an additional extraordinary cost responsibility attributable to DA customers. In the interests of preserving DA as a viable economic option, it is appropriate to defer some portion of the full obligation of such power charges by financing them through the DA CRS cap. Nonetheless, in order to balance this goal against the requirement of bundled customer indifference, the period of deferral should be no longer than is absolutely necessary. The fact that a portion of DWR costs incurred during 2001 are being financed over the life of DWR Bonds is not a precedent or rationale for extending the repayment period for the DA CRS undercollections beyond the minimum term that is absolutely necessary.
Requiring repayment of the DA CRS undercollection within the DWR contract time frame promotes better matching of costs paid with service rendered. Since the costs in question arise from the contracts, the time frame for their repayment bears some relationship to the term of those contracts. Limiting the repayment to the term of the contracts is also desirable to minimize the period that bundled customers fund any DA CRS undercollections so as to mitigate bundled customer risk. The lower the cap, the longer the time for repayment of the undercollection, and the greater the risks imposed on bundled customers relating to repayment. Accordingly, we shall adopt the requirement that the caps be set at levels that assure full repayment of the DA CRS undercollection no later than the termination of the DWR contracts in 2011.
With the term limitation on the repayment period in place, we do not find it necessary to adopt a specific dollar figure at this time for a maximum cumulative DA CRS undercollection. An arbitrary DA CRS undercollection limit has limited meaning or basis for evaluation in isolation. A more relevant criterion would be the maximum increase in bundled customer charges that would be allowable resulting from financing DA CRS undercollections. No party has offered a specific proposal in this phase based on a specific maximum permissible bundled customer charge increase as a criterion for measuring the cap. While we adopt no specific figure at this time for the maximum percentage increase in customer charges attributable to the financing of the cap, we reserve the option to revise the cap, as deemed necessary in subsequent periodic reviews, in order to prevent unreasonable increases in the level of bundled customer charges.
2. Evaluation of Forecast DA CRS Payback Period Scenarios
We next turn to the question of the likely level of DA CRS over time as a basis to measure the payback period under alternative cap scenarios. As previously discussed in D.02-11-022, we remain cognizant of the limitations and caveats inherent in drawing inferences from multi-year forecasts. As the time horizon extends further into the future, the potential for unforeseen events and variances in forecasting grows. This uncertainty, in turn, has implications for the risks associated with the manner and timing of repayment of the CRS funds advanced by bundled customers.
While forecasts of DA CRS obligations will always be subject to the uncertainties of future years' conditions, the scenarios presented by Navigant still provide a basis for informed judgment concerning the expected payback period and levels of undercollection faced by bundled customers. For purposes of our analysis, we consider the effects of alternative caps on the risk, duration, and magnitude of payback of DA CRS undercollections.
In this context, Navigant's 24 scenarios represent a range of potential outcomes to evaluate forecasting sensitivities, rather than as a basis to precisely determine the future level of DA CRS costs and revenues. The range of sensitivities can be weighted in the form of a probability distribution. The fact that we cannot precisely predict the future thus does not preclude making informed judgments about the relative likelihood of future trends based upon facts known today. However, we note that even amongst those scenarios that are more likely to occur, there is a huge difference with the estimated pay-off period and potential maximum undercollections.
Parties offered little or no support for the high case scenarios produced through by Navigant as likely outcomes or guides for evaluating the cap. Some parties favored the base case assumptions while others favored the low case, or a hybrid of low and base case assumptions. While parties' differ somewhat in their opinions on the likeliest scenario, we find the most defensible support for those scenarios based upon the low ProSym case. While some parties support use of the base case, no basis had been laid to show that the base case assumptions are as likely or more likely than either the low or high case. While no party offered a defense of the high case assumptions, we find that it provides useful guidance on the level of the undercollection and timing of recovery should circumstances change significantly from their current status. For example, if gas prices return to the levels of last year.
PG&E defends the base case because DWR used it in preparing its 2003 DWR revenue requirements in A.00-11-038 . The mere fact that the base case was used for the DWR revenue requirement, however does not require reliance upon it here. PG&E offers no independent analysis of the reasonableness of DWR's base case assumption, but believes consistency is needed between the resource assumptions underlying the DWR proceeding and this proceeding. PG&E's support for the base case appears to be premise that this phase of the proceeding is about setting the total DA CRS revenue requirement.
We agree that consistency with the DWR revenue requirement proceeding is warranted for purposes of determining the total DA CRS revenue requirement obligation for past periods through 2003. To the extent that bundled ratepayer costs are based in part on the DWR revenue requirements resulting from use of the base case assumptions, it makes sense to use comparable assumptions for setting the costs that will be borne concurrently be DA customers. One of our main purposes here in setting those costs and implementing a cap is to ensure DA's ability to compete with bundled service rates. Using comparable data to set charges for bundled and DA customers will facilitate that goal, and ensure fair competition between bundled and DA providers.
Since we are not setting a total revenue requirement in this phase, the inputs that the utilities have provided concerning CTC are relevant here for the purpose of evaluating long term DA CRS forecasts, incorporating CTC costs into the total portfolio indifference calculation. We do not approve or adopt the CTC figures offered by PG&E as final figures nor prejudge any further review of the utilities' CTC that may be conducted in other proceedings.
We conclude that the scenarios presented by Navigant reflect a wide range of possible outcomes. Many of the factors underlying these forecasts, such as natural gas costs, are outside the control of the Commission and utilities and are subject to extensive fluctuation. Even narrowing the scenarios to those that reflect more likely assumptions, we are left with choices about the possible maximum undercollection and potential pay-off period that trouble us. For example, at 2.7 cents per kWh and 4 % interest rate, there is only one or two cases that would provide a for a pay-off period consistent with our stated intention of recovering all costs by 2011 and minimize the magnitude of the potential undercollection for PG&E. The scenarios for SCE and SDG&E also mainly include very prolonged payback periods.
Given the sensitivity of the assumptions underlying the Navigant calculations, we cannot justify relying on any one scenario (or even a limited subset of scenarios), which barely meets our criteria to ensure proper pay-off period and minimum undercollections. We find that the best approach is to be adopt a cap of 4 cents per kWh for PG&E, SCE and SDG&E.
The need to minimize the undercollection is important to protect the bundled customers who are being required to pay these costs that should be borne by DA customers, both the historical and going-forward undercollections. A small business, commercial or industrial customer taking bundled service will face rates that would otherwise be lower if DA customers were obligated to pay their entire cost responsibility surcharge immediately, or in a more timely manner. Amazingly, no party has offered an assessment of the economic viability of these bundled customers, as compared to the comments provided on ensuring the viability of DA customers . There is no basis to assume that one customer needs more economic protection than another simply because one contracts with a utility and another with a DA provider. We note that the majority of businesses in California are in fact customers of the investor-owned utilities. Those businesses which will be impacted by bearing the costs of protecting DA customers.
As such, we find that while the need to recover the total costs within a reasonable time period is an important criteria, an equally important, if not more important, criteria must be that we minimize the size of the potential undercollection to protect the bundled customers.
3. Determination of the 2001-2002 Undercollection
Several parties take issue with the manner in which DWR has depicted the DA CRS undercollection for the 2001-02 past periods because of the wide divergence of hypothetical values, representing a undercollection range from $431 to $822 million for the three utilities. CMTA argues, for example, that DA-in/out methodology must not produce different results for past periods due to uncertainty in future conditions. Moreover, the 2001-2002 historic undercollection represents a significant portion of the total undercollection carried forward to the entire forecast period. In 20 out of 24 scenarios run by Navigant, the undercollections accrued through 2001-02 represent the majority of the eventual maximum undercollection. In at least 10 of the Navigant scenarios, the maximum undercollection for each utility occurs in 2002 or 2003. No later than 2004, the DA customers are projected to begin paying down the maximum undercollection.
We agree that the methodology used by Navigant in computing hypothetical ranges of the 2001-2002 DA CRS undercollection fails to provide a reliable basis to determine the actual level of the undercollection. While it is necessary to forecast future events and to test the sensitivity of a range of differing scenarios, there is no logical reason why multiple hypothetical scenarios need to be devised for past periods. The assumed resource input values that may be appropriate for forecasting 2003 are not necessarily applicable to the actual recorded transactions that transpired during the 2001-2002 period. The broad variance in the range of hypothetical undercollections makes it difficult to draw meaningful conclusions concerning the resulting effects on payback period based upon the actual undercollection through the end of 2002.
In order to rectify this problem, DWR/Navigant provided a supplemental calculation of the actual undercollection attributable to DA CRS requirements for the 2001-2002 recorded period. By ALJ ruling dated May 12, 2003, this supplemental calculation was served on parties with opportunity to review and comment. DWR provide subsequent updates and corrections on May 13 and 15. Parties participated in a conference call to discuss these model updates and had the opportunity to file comments on May 19, 2003.
In its supplemental responses, DWR provided revised approximations of the recorded undercollection that did not vary based upon prospective scenario assumptions. DWR developed four alternative methods to true up the 2001-02 undercollections to actual. DWR discarded the first method because it produced illogical results.
The second and third true up methods attempt to bound the CRS undercollection. Method 2 sets off-system sales to zero, which means that all would-be direct access load that is treated as bundled for the DA-in case is met through the reduction in off-system sales and additional spot purchases, where necessary. Using Method 2, the 2001-2002 undercollection is $311 million for PG&E, $264 million for SCE, and $34 million for SDG&E. This method produces an upper bound. Method 3 maintains the off-system sales volumes as in DA-out, which means that the incremental bundled load is met entirely through spot purchases. Using Method 3, the 2001-02 under-collection is $292 million for PG&E, $255 million for SCE, and $19 million for SDG&E. This method produces the lower bound. The range between Method 2 and 3 is only $19 million for PG&E, $9 million for SCE, and $15 million for SDG&E.
The fourth true-up method generates the 2001-02 DA-in cases by applying the 2003 ratio of DA-in and DA-out off-system sales volumes to 2001 and 2002 DA-out volumes. DWR believes this methodology is more appropriate than Method 1 because it uses 2001-02 DA-out figures in the calculus, where Method 1 only applied the 2003 purchase-sales percentage to DA-in net short volumes. Using Method 4, the 2001-02 under-collection is $304 million for PG&E, $260 million for SCE, and $23 million for SDG&E.
We are not persuaded by the up-dated runs produced by Navigant which purport to calculate the actual historical undercollection. The fact that the method used by Navigant produces an upper- and lower-bound range of only $19 million for PG&E, $9 million for SCE, and $15 million for SDG&E, suggests only that the new set of assumptions used for the last-minute calculation of 2001/2002 undercollections is at best internally consistent. Since we chose not to adopt actual 2003 DA revenue requirements or historical undercollections, Navigant's new runs will simply be used as another, though not definitive, set of calculations.
Further, parties had only a limited opportunity to evaluate these new calculations and no opportunity to litigate any differences. As the revised range of historical undercollections has not been adequately reviewed, examined, or evaluated10, we cannot determine whether they represent an improvement over previous undercollection calculations. At best, the revised numbers further highlight the wide range of possible outcomes and the extent to which "refinements" simply provide more unanswered questions.
4. Disposition of DWR Operating Reserves
TURN raises the question of whether a potential source of financing of the DA CRS undercollection may become available from DWR through the anticipated release of operating reserves. Reserves in the amount of $850 million were included in the DWR bond issuance in response to financial community concerns about DWR potentially being required to retain responsibility for procuring the utilities' net short requirements beyond January 1, 2003. As a result of the procurement function successfully being transferred from DWR to the utilities as of January 1, 2003, TURN expresses hope and expectation that DWR is in the process of securing approval from its lenders for the release of the $850 million of reserves. Under the Rate Agreement, the Commission, in consultation with DWR, is responsible for determining how the excess reserves will be applied.
TURN proposes that the $850 million in reserves, to the extent it becomes available, be applied to the DA CRS undercollection that will otherwise be financed by bundled customers, rather than as a reduction in the DWR bond balance. Under the TURN proposal, DA customers would assume exclusive liability for interest payments to DWR on the portion of the DWR bonds equivalent to the reserves applied to pay down the DA CRS undercollection. If the released reserves are not sufficient to fund the entire DA CRS undercollection, TURN proposes that any remaining undercollection be repaid first before the DWR bond debt. TURN also states its preference that DWR would issue additional debt to fund the entire DA CRS undercollection.
DWR disagrees with TURN's proposal to use of any reserves that become available to pay down the DA CRS undercollection. DWR argues that bundled customers would be adversely impacted by use of the reserves to reduce the DA CRS undercollections. DWR states that any reduction in reserves normally would be used by the Commission to reduce the revenue collections currently required from bundled customers.
The actual nature, extent, and timing of any such reserves that may become available is an issue to be addressed in the context of the DWR 2003 supplemental revenue requirement review in A.00-11-038. Also the specific impacts of such reserves on the modeling scenarios have not been determined as part of this proceeding, but would entail recasting the recorded undercollection as of the end of 2002. An offsetting prospective increase would be required to reflect an increase in the DWR Bond Charge obligation for DA customers and corresponding prospective reduction for bundled customers.
By paying down at least a significant portion of the DA undercollection, bundled customers would be relieved of having to finance this burden going forward, and would realize payback of any funds advanced much sooner. Because the actual determination and disposition of the reserve account is the subject of the DWR revenue requirement redetermination in A.00-11-038, we do not resolve the disposition of the reserves with respect to the undercollection in this order, but defer to the A.00-11-038 et al. be considered in that proceeding.
5. Analysis of Key Variables Underlying DA CRS Cap Evaluation
We discuss below our review of the key modeling variables underlying the Navigant high, low, and base case modeling runs, and the assumptions used to develop its 24 scenarios.
a) Natural Gas Prices
The price of natural gas is a significant variable in forecasting the DA CRS requirements over time. The gas price is a direct input into the market price of electricity and is inversely related to the level of DA CRS obligation. Increases in electricity market prices, in turn, reduce the degree of stranded costs associated with fixed-price DWR contracts and correspondingly, the allocation of such costs to the DA CRS.
Navigant has used, in its Base Case scenarios, annual average gas prices ranging from $3.81 to $4.13/MMBtu at the different California trading hubs. CLECA witness Barkovich testified that these prices are "far lower" than prices available in the market, that gas prices at the border have exceeded $5/MMBtu and that forward prices for the next year have been at the same level.11 The actual gas prices at the California border in March 2003 and recent futures gas prices for April and May 2003 were over $2/decatherm greater than the DWR high case.12 Beginning in March 2003, the DWR forecasts and the NYMEX futures prices begin to converge until they are comparable at a point in the middle of 2004. CMTA recommends combining the DWR low case scenario for 2003-04 with the base case for 2005-2020 to yield an improved gas price forecast. CMTA computes that such a "hybrid" scenario would result in a payback of the DA CRS obligation by 2009 for PG&E, 2006 for SCE, and 2004 for SDG&E.13
DWR witnesses McDonald and McMahon agreed, on cross examination, that the gas prices embedded in the Base Case are too low to reflect current conditions. McDonald acknowledged that gas price assumptions are critical to the forecast of CRS costs and that the prices in the Base Case likely overstate the level of the CRS for the next few months and thus the undercollection under a capped CRS level.14 Further, both McDonald and McMahon acknowledged that the DWR is considering the filing of a modified 2003 revenue requirement with the Commission and that the revised revenue requirement would include gas prices 17% to 18 % higher than those in the Base Case scenarios.15
This problem is addressed in the Low Case scenarios, in which the several parties participating in the Workshops agreed that Navigant should adjust the gas prices in the Base Case upward by 25%. While the gas prices in the Low Case are unlikely to be precisely correct, they better reflect current conditions in the market than do the gas price forecasts in the Base Case. Navigant and virtually every other party in the proceeding appears to agree. McDonald, for example, agreed that the DWR does not regard the Base Case as the case most likely to occur.16 We conclude that the gas price assumptions underlying the "low" case scenario thus reflects a more reasonable forecast of gas prices than that of either the base or high case scenarios, given current gas prices. The impacts of the low case resource assumptions at a 2.7 cents cap are represented in Scenarios 14 (at a 4% interest rate) and Scenario 13 (at a 9% interest rate). However, gas prices fluctuate rapidly, and while the low case values may appear at the moment to be more likely to occur, we must consider the possibility that gas prices will also be lower, and more consistent with the costs over the last few years.
b) New Generation Capacity Additions
Navigant's ProSym cases also include assumptions regarding the addition of new generation facilities. DWR states that as part of its annual revenue requirements process, it engaged in due diligence in forecasting new generation under construction in California, the Pacific Northwest, and the remainder of the Western Electricity Coordinating Council (WECC), as well as resources that are still in the planning and permitting stages. DWR states that its forecasts closely track the January 2003 CEC forecast in most years. In its modeling runs for this phase of the proceeding, DWR reduced its forecast of new generation from that underlying its initial forecasts in support of the evidentiary record underlying D.02-11-022. Even with this downward revision, the forecast does not reflect the delay in the expected on-line date for several plants. CMTA witness McGuire testified that over 3,500 MW of new generation has been delayed beyond the dates assumed in DWR's base case.17
The ProSym base case new generation assumptions are overly optimistic. Overestimates of new capacity causes an overstatement of DA CRS obligations, thus exaggerating the expected payback period. CLECA witness Barkovich testified that the Navigant estimates ignore numerous generating plant cancellations and the fact that most of the companies previously prepared to develop new plants are now in serious financial trouble.18 Barkovich believes that the amount of new generation is more likely to fall than rise and that there is a distinct possibility of an acceleration of retirements of older, more polluting plants. The Low Case adjusts the new generation entry assumptions down to 80% of those in the Base Case. We consider the low case to be a more realistic assumption for purposes of evaluating the payback period.
c) Levels of DA Load
Navigant's cases also include assumptions concerning DA load. DA load assumptions are required to calculate assumed DA CRS utilizing the DA-in/DA-out approach as adopted in D.02-11-022. For the DA-in calculation, DWR utilized DA load data provided by the utilities. For the DA-out case, DWR relied upon the December 15, 2002 DA load information submitted to the Commission by each utility. The DA-in/DA-out calculation compares the total portfolio costs based upon incremental DA load shifts between July 1, 2001 and September 20, 2001.
DWR calculated DA load for 2002 using its own retail forecast and held that load constant for the Study Period. For its base case, DWR assumed no additional load shifting would occur into or out of DA. For the high and low cases, DWR assumed changes in the DA load level. Once the total dollar cost responsibility is generated by the DA-in/DA-out comparison, the resulting DA cost responsibility obligation is across all DA volumes that took bundled service as of February 1, 2001.
In the low ProSym case, Navigant assumed that 30% of DA load would depart simultaneously in July 2003, with subsequent DA CRS collections based on the reduced DA load. The model also subtracted a pro rata share (i.e., 30%) of the DA CRS undercollection from the balance at the time of departure. This approach effectively assumes a one-time "re-entry fee" for those DA customers returning to bundled service. The "Scenario 25" presented in the testimony of AReM witness McClary essentially isolates the difference attributable to the DA load assumptions between the base case and low case. AReM modified scenario essentially incorporates all of the low case assumptions for Scenario 13, except substituting the base case assumption for DA load. The substitution of the base case assumption for DA load results in an earlier payback period for all three utilities, as illustrated in Appendix 1 of Exhibit 181 (Prepared Testimony of McClary). Accordingly, use of Scenario 13 (rather than Scenario 25) for purposes of evaluating DA CRS payback periods provides a conservative estimate that provides added assurance that bundled customers' payback period will not be longer, and may be shorter than indicated by the DA load assumptions in Scenario 13.
d) Utility Retained Generation and CTC Costs
Under the total portfolio approach, the DA CRS reflects bundled customer indifference by taking into account the total portfolio of resources including both URG and DWR sources. Thus to make a complete assessment of the DA CRS cap level, it is necessary to model both DWR and URG resources. DWR's model assumptions regarding URG and CTC are based on data provided by each of the utilities. To break down the DA CRS revenue requirement into its ongoing CTC and DWR power charge components, D.02-11-022 mandates that DA customers' responsibility for ongoing CTC be determined, and that that amount subtracted from the DA revenue requirement. The remaining amount is DA customers' responsibility for the DWR revenue requirements. The separation is necessary because different cost allocation and tariff design apply to the ongoing CTC, DWR bond charge, and DA DWR power charge rate components. Since the ongoing CTC applies to bundled as well as DA customers, one must first determine the ongoing CTC revenue requirement. One can then determine direct access customers' share.
Separate testimony was sponsored by each of the utilities sponsoring and explaining the URG and CTC assumptions they supplied to DWR for purposes of DA CRS modeling.
SCE provided Navigant three forecasts: total URG Costs, URG Energy and CTC as a unit rate. The energy and cost forecasts were based on underlying forecasts of separate components for SCE-owned URG and purchased power from Qualifying Facility (QF) contracts. The CTC was forecasted using the benchmark price adopted in D.02-011-022 measured against URG costs. SCE provided sales data based on its most recent forecast prepared in May 2001 as part of its General Rate Case.
SCE URG output is assumed to be constant in all years at the 2003 level. The URG output and cost forecasts were consistent with SCE's filed Procurement Plan and with D.02-10-002. The output would reflect average generation levels, economic dispatch and average year hydro conditions. URG costs, except for the Incentive Cost Incentive Pricing (ICIP) mechanism, are escalated based on fuel specific cost factors.
The SCE QF forecast of energy and costs is tied to the underlying contracts and to the Navigant gas price forecast. This forecast also reflects fixed-price contracts that have been signed, and the gradual termination of contracts over time. SCE prepared an initial forecast through 2012, not anticipating that the projections would go well beyond this period. The forecasts after 2012 were held constant at the 2012 level
SCE's proposal incorporates the total portfolio method to calculate the uneconomic URG portion of the DA CRS, as adopted by D.02-11-022. Specifically, SCE calculates the above-market URG costs based on the total URG portfolio, as opposed to solely QF and Power Purchase Agreements ("PPA") costs, to comply with D.02-11-022, maintain consistency and to compartmentalize URG costs into a single calculation.19
PG&E agrees with SCE's interpretation of how to apply the total portfolio method.20 PG&E includes in the calculation all of its pre-December 20, 1995, or "old world" generation resources, including not only its power purchase agreements but also its retained generation facilities. By contrast, Section 36721 does not incorporate PG&E's retained generation facilities in the ongoing CTC costs it identifies. Because of the regulatory treatment adopted for these facilities, including PG&E's retained generation facilities in the calculation serves to lower the ongoing CTC revenue requirement.
Pursuant to D.02-11-022, the power component of PG&E's ongoing CTC revenue requirement is determined with reference to a benchmark of 4.3 cents per kWh adopted in D.02-11-022. The costs of PG&E's old world power costs above 4.3 cents per kWh are included in the ongoing CTC revenue requirement. Under D.02-11-022, PG&E's ongoing CTC revenue requirement also includes the net cost to meet PG&E's obligation to provide power to Western Area Power Administration (WAPA) under PG&E's WAPA contract. Pursuant to D.02-11-022's direction, the cost to provide power to WAPA is deemed to be the average cost of PG&E's portfolio, including the costs of DWR power. Finally, the ongoing CTC also includes a relatively minor amount for employee transition costs.
Thus, DA CRS revenue requirement is determined so that the average costs bundled customers pays for power, including power from URG and DWR contracts, is the same as it would have been had DA been suspended on July 1, 2001, and there had been no post-July 1, 2001, DA migration.
CMTA argues that adopted CTC values should reflect the most recent determination by the Commission that is based on a substantial review of URG costs. CMTA supports the use of the URG costs for 2002 adopted for each utility in D.02-04-016. CMTA opposes PG&E's proposed CTC revenue requirement of $777,661 which is based on PG&E Advice Letter No. 2233-E which significantly updated the URG revenue requirement levels adopted in D.02-04-016. For past periods, CMTA argues that recorded URG revenue requirements and volumes should be used to estimate CTC most accurately. CMTA also argues that PG&E's CTC calculations are still not sufficiently transparent and consistent with the other utilities.
TURN points out that the assumptions for PG&E do not include any costs that will be borne by customers as a result the resolution of PG&E's bankruptcy, and the repayment of some or all of PG&E's historic costs. Such costs were reflected for SCE in the form of the adopted Historic Procurement Charge (HPC). All the plans of reorganization that have been submitted to the court to resolve PG&E's bankruptcy will require PG&E's customers to reimburse PG&E for billions of dollars of costs incurred by PG&E in prior years, that are the responsibility of both bundled and direct access customers. By failing to include any costs to reflect the outcome of PG&E's bankruptcy, TURN points out that the analyses before us greatly understate the level of the DA undercollection for PG&E.
SDG&E's ongoing CTC was initially set pursuant to D.99-05-051, and made effective when SDG&E ended its AB 1890 rate freeze on July 1, 1999. SDG&E's ongoing CTC was subsequently redesigned pursuant to D.00-10-0948, effective January 1, 2001. In D.02-12-064, the Commission adopted a settlement whereby SDG&E's CTC component would continue until such time as the AB 265 balancing account has been reduced to zero and then at that time it would be revisited and adjusted in accordance with remaining tail costs.
Because SDG&E has no sunk costs remaining to be recovered pursuant to AB 1890, and because its ICIP mechanism ends this year, SDG&E believes that there no other URG costs to be addressed in the CTC component. SDG&E thus requests that its allocation and tariff design of ongoing CTC not be revisited in this DA CRS proceeding.
CMTA takes issue with SDG&E's calculation of CTC. CMTA argues that what is at issue here is whether SDG&E has any below-benchmark resources that can be used to offset to some degree its above-benchmark QF and purchased power resources. CMTA argues that SDG&E should be required to amend its CTC methodology to be consistent with that of PG&E and SCE by including below-benchmark resources in accordance with D.02-11-022.
Farm Bureau calls for a segregation of the CTC from DWR ongoing and bond costs. Farm Bureau concurs with DA parties that a review of CTC that the utilities carry forward is necessary. Farm Bureau also argues that segregation of CTC from the DWR costs is the only logical way that Draft Resolution E-3813 (for utilities' filed tariffs regarding DA CRS) can be implemented. The Draft Resolution would require charging continuous DA customers and DA customers charged under the CRS cap the same ongoing CTC until the full revenue requirement is recovered from DA customers. Farm Bureau argues that any other mechanism could possibly lead to limited or no recovery of CTC from continuous DA customers.
Farm Bureau opposes PG&E's request to utilize this proceeding to affirm a recalculation of its CTC. By making CTC charges consistent with other charges borne for utility costs to serve any load, Farm Bureau argues, a better balance will be struck between DA and bundled customers. Furthermore, the segregation of CTC will comport with the movement to bottoms-up billing.
As stated previously, this phase is not the designated place for adopting and finalizing CTC components for DA CRS purposes. The CTC values that have been presented in this phase are relevant for purposes of modeling the forecast DA CRS under the total portfolio approach which requires assumptions concerning CTC. Parties have raised various issues concerning the appropriate level of CTC for each of the utilities, particularly for PG&E. We need not resolve all of those CTC issues here. As noted by AReM, differing forecasts of CTC URG components do not appear to have a substantial impact on forecasting the impact of the cap. The finalization of the CTC element for each utility shall be addressed in its pending Energy Resource Recovery Amount (ERRA) proceeding. We also note that the CTC methodology used by SDG&E is not consistent with the total portfolio methodology in that it does not include URG resources that are below the CTC benchmark cost. The fact that SDG&E has ended its rate freeze does not relieve it from including all of its URG to achieve a total portfolio indifference value for its DA CRS. In finalizing the DA CRS total portfolio indifference calculation for SDG&E, we shall require that SDG&E conform to the total portfolio approach consistent with D.02-11-022.
e) Off-System Sales (OSS) Prices
DWR/Navigant's ProSym cases model two alternative assumptions as to the sales price of excess DWR power. The scenarios assume power will be sold at either 50% or 100% of the indicated hourly market prices from PROSYM. The assumed 50% sales price lowers the estimated revenue received for the sale of surplus power and thereby increases estimated CRS costs. DWR's estimate of the price received for such power is a key variable in determining CRS costs. Since the utilities are now responsible for dispatch of the DWR power, DWR's assumption would now impose this very low assumed price for sales of excess power to their activity in the year 2003 and beyond.
While the DWR's experience in 2001 and early in 2002 may have been consistent with a 50% assumption, changes in its sales practices in 2002 resulted in substantial improvement in the prices as of the time of the hearings last summer.22 Further, the Commission found in D.02-11-022 that a more reasonable assumption, based on evidence then before the Commission, would be closer to 100% than 50%.23
DWR states that the 50% assumption is based on its experience in 2001 and that it has asked the utilities to provide a new estimate based on their sales experience after January 1, 2003.24 McDonald testified that the 50% assumption is included in the CRS scenarios because it was used in the DWR 2003 revenue requirement, which was prepared in the spring and summer of 2002.25 PG&E witness Burns, while agreeing that DWR's 2003 revenue requirement is too high, testified that the 50% OSS assumption embedded in that revenue requirement is appropriate for use in calculating the CRS estimates here as a matter of consistency.26
SCE witness Collette testified that SCE's experience in the first two months of 2003 with sales of DWR power shows that it achieved prices equal to 96% of the average purchase price.27 As discussed in the hearings leading to D.02-11-022, the average purchase price will tend to be higher than the average sales price simply because of the load conditions under which each is most likely to occur. Thus, achieving sales prices equal to 96% of purchase prices is likely to reflect sales prices at levels in excess of PROSYM market clearing prices for the hours in which the sales were actually made. Collete testified that an 100% OSS assumption is the only reasonable assumption for purposes of long-term evaluation of the CRS.28
We find the 50% OSS assumption to be highly unlikely as a basis for estimating prospective CRS requirements for evaluating the duration of the CRS shortfall at various cap levels. The only party to support a 50% OSS assumption was PG&E. The only rationale offered by PG&E for the 50% assumption, however, was consistency with the DWR's 2002 revenue requirement determination. Yet PG&E witness Burns testified that there is no basis to assume a 50% assumption is more accurate than an OSS valued at 100% of MCP. PG&E conducted no analysis to compare the prices it obtained from OSS with the prices assumed by DWR's ProSym model.29 TURN recommended an OSS price range of "about 75% to 90 %" of MCP. Farm Bureau believes a midpoint compromise of 75% MCP assumption reasonably recognizes the uncertainty of predicting the actual level. ORA offered no position on this issue.
We conclude that those scenarios incorporating an assumption of OSS valued at 100% of MCP provide the most reliable model runs for purposes of evaluating the appropriate DA CRS cap. We are persuaded by the testimony of SCE witness Colette that a 100% OSS assumption is the most reasonable assumption for long term evaluation purposes.
However, no evidence has been submitted to demonstrate that the 100% assumption is certain to occur. No empirical evidence has been submitted to show that the actual amounts obtained by the utilities since they took over administration of DWR's contracts has actually been at the 100% of market price level. In addition, DWR has indicated that in its upcoming update to its 2003 revenue requirement, it will continue to use the 50% assumption. Thus, the actual revenue requirement that ratepayers must pay will be based on the 50% assumption, not the 100% assumption. So, for at least the year 2003, it is likely that the rates paid by bundled customers, the costs allocated to DA customers and the resulting DA CRS undercollection will reflect the 50% assumption.
6. Interest Rate Assumed as a Source of Financing
In order to remain indifferent with respect to DA migration, bundled customers must be compensated for the time value of money associated with funds advanced to cover DA CRS undercollections. In D.02-11-022, we directed that interest rate applicable to the DWR Bond Charge be applied on an interim basis for the financing the cap through July 1, 2003. We directed that further inquiry be conducted regarding longer term arrangements for the costs of financing of the DA caps.
For purposes of the scenarios modeled by Navigant, two alternative interest rate assumptions were used, one at 4% and a second at 9%, incorporating the range of interest rates requested by parties pursuant to the modeling workshop. The difference in interest rates causes a one-year difference in payback period. The longest payback period is projected for PG&E (between eight and nine years). The impacts of the low case resource assumptions at a 4 cents cap are represented in Scenarios 16 (at a 4% interest rate) and Scenario 15 (at a 9% interest rate). The difference in interest rates results in a one-year difference for SCE and no difference in payback period for PG&E or SDG&E.
However, the difference in interest rates causes a larger delay in the payback period in other scenarios. For example, in the base case scenarios 5 and 6, the payback period for PG&E is lengthened by 3 years from 11 to 14, due to the higher interest rate. The payback period for SCE is increased from 8 to 9 years.
a) Parties' Positions
A variety of proposals are offered as to the appropriate interest rate to be applied to compensate bundled customers for the carrying costs of funds advanced to cover DA CRS shortfalls.
ORA and TURN both proposed that the interest rate be indexed to the utility rate of return on rate base. ORA sponsors an after-tax approach while TURN favors a pre-tax approach. TURN believes the pre-tax utility rate of return, currently in the 12%-13% range, is analogous to the long-term nature of the bundled customers' "loan" to cover the DA CRS obligation. The utility rate of return provides a return on assets with a relatively long life.
ORA proposes the utility's rate of return (net of taxes) be used to compensate bundled customers for funding the DA CRS undercollection. So that direct access customers in the three utility service areas are treated the same, ORA proposes a simple average of the authorized returns of the three utilities be used.30 ORA proposes a 9.25% interest rate (equivalent to the average after-tax cost of capital for all three utilities) be applied where the adopted cap is 3 cents per kWh or less, and an interest rate of 8.25% apply if a 4 cents per kWh cap is adopted (as proposed for PG&E). The 100 basis point differential is intended to reflect the reduced risk of a shorter payback period.
ORA derives the 100 basis point differential based on a comparison of risk differentials reflected in the cost of capital using SCE as an example. The difference between SCE's weighted average cost of capital (9.75%) and its corporate bond rate (8.19%) is 156 basis points. (ORA Ex. 162, footnote 6; Edison Ex. 160, p. 11.) ORA notes the difference between SCE's weighted average cost of capital (9.75%) and its corporate bond rate (8.19%) is 156 basis points. (ORA Ex. 162, footnote 6; Edison Ex. 160, p. 11.) Corporate bonds are instruments are fully secured instruments, whereas the weighted average cost of capital represents a mix of instruments with only limited security. Rather than apply a full 156 basis point reduction to interest rate charged to core DA customers, ORA believes a two-thirds reduction (100 basis points) is appropriate since the risk remains unsecured regardless of how it is allocated.
ORA identifies three major components of risk: (a) loan duration, (b) source of borrower, and (c) lack of collateral security. ORA characterizes the DA CRS loan term as unusually long compared with the short-term nature of debt typically financed by commercial paper. The precise duration is also of unknown duration. Risk typically increases as a function of longer duration. ORA also proposes that the interest rate adopted reflect the duration of the CRS undercollection.
ORA notes that unlike most customer loans that are made to the utility, this loan is made to another class of customer. Thus ORA views the risk of repayment as being tied more to the creditworthiness of the DA customer than that of the utility. ORA proposes that the Commission should adopt an explicit policy requiring the remaining DA customers to bear the debt owed by DA customers who become insolvent or move out of state and thus are unable or unwilling to pay the debt themselves. ORA proposed an accounting system to ensure that DA customers pay their share of the debt.31 ORA's proposed accounting system is discussed in more detail below.
Moreover, unlike a voluntary loan between two private parties, ORA also distinguishes the nature of this loan as being involuntary. As the closest analogous situation, ORA draws upon the example of a Commission-approved energy conservation program where the initial capital investment in conservation technology is funded by nonparticipating utility customers. The investment is paid back in future years in the form of energy savings and avoided generation costs. ORA notes that most recently, parties have settled on using a discount rate of 8.15% to measure the present value of costs and benefits that reflect both participants and nonparticipants viewpoints.32
ORA argues that the risk of this loan is increased by virtue of lacking collateral in the form of secured assets such as would be true of a secured bond. ORA also expresses concern that the only security offered is through the Commission's ratemaking authority which could be subject to change before bundled customers are fully paid off.
Farm Bureau proposes an alternative approach using two different interest rates, separately applied to residential and business customers to reflect each group of customers' different costs of money. For its analysis, Farm Bureau used a 10-year average of the "Weighted Average Consumer Rate" (at 12%) for residential, and the "Average Long Term Corporate Bond Rate" (at 7.6%) for all other customers. The Weighted Average Consumer Rate is based upon an index produced by the Federal Reserve Bank of New York, and includes financing sources such as credit card debt. The corporate bond rate reflects the cost of money to companies with a wide range of credit worthiness levels.
The weighted average consumer rate provided by the Federal Reserve Bank of New York includes financing sources such as credit card debt, which is a source of financing that is more widely available to residential consumers. Farm Bureau believes that this latter rate would be a more appropriate for balances owed to residential customers. Farm Bureau also argues that the average long-term corporate bond rate is more reflective of the type of longer-term loans available to businesses.
Under the Farm Bureau's approach, different repayment balances would have to be maintained for residential and other customers so the differing interest rates could be applied to their respective undercollection balances.
SCE proposed the use of the interest rate associated with utility long-term debt. In its initial testimony, SCE proposed to apply its after-tax cost of long term debt as the interest rate on DA CRS undercollections. Based on its adopted cost of long-term debt of 8.19%,33 SCE proposed to apply an after-tax cost of debt of 4.87%. This rate is close to the 4.89% interest rate on DWR bonds, which was prescribed as the source of interim financing for the DA CRS undercollection in D.02-11-022. Subsequently, SCE revised its position to propose use of the 8.19% before-tax interest rate.
SDG&E and various other parties representing DA interests34 propose the use of the three-month commercial paper interest rate that is generally applied to finance utility balancing accounts. The general utility practice is to finance balancing accounts at a monthly rate equal to one-twelfth of the three-month commercial paper interest rate for the previous month, as reported in the Federal Reserve Statistical Release, G.13, or its successor. SDG&E argues that the DA CRS "risk" is no different from that associated with other utility balancing accounts. SDG&E cites as an example, the Assembly Bill (AB) 265 undercollection which rose to approximately $750 million. Yet, the Commission still only applied the three-month commercial paper rate.35
AReM provided a tabulation of the three-month commercial paper rates from March 1999 through February 2003, indicating an average of 4.07% during this period, with swings between 1.25% and 6.59% AReM proposes that the 4.07% average be assumed as the interest rate on undercollections on a going forward basis, and that the actual three-month commercial paper interest rates be applied to actual balances through December 2002. AReM considers this to be a conservative assumption since near term interest rates are likely to be below the 4.07% average.
CLECA argues that a 4% interest rate for purposes of financing the CRS undercollection appropriately reflects the nature and risk of the loan at issue. CLECA characterizes the CRS loan as having a relatively high degree of assurance of repayment, backed by the Commission's determination to assure full repayment. CLECA witness Barkovich testified that the only repayment uncertainty is the possibility that DA customers go out of business before the undercollection is paid off. CLECA opposes the use of the utility cost of capital as an interest rate measure because the utility is not doing the financing, but the customer is. CLECA contends that the customer's alternative lending opportunities are based on interest rates that banks pay to consumers.
CMTA proposes that for purposes of financing the initial CRS undercollection covering the period September 20, 2001 through December 31, 2002, the three-month commercial paper rate valued at 1.77% should apply. For subsequent financing from January 1, 2003 forward, CMTA proposes use of the DWR bond rate which it represents as 4.74%.
Corona characterizes the CRS advances by bundled customers as a "reallocation of costs" among customer groups rather than a "loan." As such, Corona argues that any interest rates applied in such situations traditionally are assessed interest at no more than the commercial paper rate, if any interest rate is applied at all. Corona argues that the interest rate proposed by TURN would be usurious and cause a windfall to bundled customers in violation of the Commission's goal of customer indifference.
b) Discussion
To preserve bundled customer indifference, the interest rate adopted for the DA CRS undercollections must compensate bundled customers for their time value of money. By funding DA CRS undercollections, bundled customers give up the use of funds that otherwise could be used to invest, pay off debt, or spend for current goods and services. The Commission has repeatedly been faced with decisions in which it must apply an interest rate to reflect ratepayers' time value of money. In essentially all of the historic instances where the Commission has addressed this issue, it has used the utilities' after-tax weighted cost of capital (WCOC) as the proxy for the ratepayers' time value of money. The Commission has used the WCOC in proceedings such as the recovery of Diablo Canyon costs (D. 88-12-083), in resource planning proceedings such as OIR-2 and the Biennial Resource Planning Update (BRPU), in setting interest rates for advanced ratepayer payments of utility transition costs (D. 97-09-074). Use of the WCOC would also be consistent with the assumptions used for ratepayer time value of money by the CEC in its resource planning and siting proceedings.
As a proxy for bundled customers' time value of money, various parties referenced the cost of money of the utility. There are limitations in the use of such a proxy. Utility financing involves only a single entity going to the capital markets for specific financing needs. Bundled customers, however, represent divergent classes and individuals within those classes with differing costs of money. For example, business customers typically may deduct their interest costs for income tax purposes, thereby lowering their after-tax cost of money. Residential customers, however, may be unable to claim a tax deduction for interest expense. Thus, aside from any other differences, the after-tax cost of money differs for various customers depending on whether deductibility of interest for income tax purposes. Unregulated businesses also face greater risks on the recovery of their costs than do regulated utilities. Thus, the return on equity component of the utility WCOC is likely to low to reflect the return sought by unregulated businesses on their investments.
Residential customers may also experience different costs of money among themselves depending whether they are a net borrower or net lender for their source of funds. For example, net borrowers that incrementally draw from an 18% line of revolving consumer credit have a very different marginal discount rate from customers that incrementally draw upon money market investment funds earning perhaps 1%-2%. The variety of differences among ratepayers makes it impossible to select one interest rate that is appropriate for everyone. As in the past, the best proxy to use to represent the time value of money to all ratepayers is the utilities' WCOC. The WCOC fall within the bounds of all the various interest rates that can be considered, from credit card interest rates, to private returns on equity, to money market rates. It also accurately reflects the opportunity costs foregone by ratepayers since the funds that will be collected from them could always be used to pay off utility rate base, and thus save ratepayers the cost of financing that rate base, which is by definition the WCOC.
The DA CRS undercollection represents a use of ratepayer capital with a duration of multiple years. For some ratepayers, this capital may come from the ratepayer taking on additional debt. For others, it may represent their equity, that would otherwise have been invested in the ratepayer's business, or other investments expected to earn a high rate of return. As such, the relevant standard for identifying the cost of money combines both return on debt and return on equity. The WCOC adopted for an investor-owned utility includes separate elements to compensate different types of investors. There is a both a long-term debt and a stockholder's equity component for which a cost of capital is determined based upon the risk and return characteristics of the each type of investment.
Utility stockholder's return is fundamentally the same as what ratepayers should expect here. The utility shareholders expect to recover only a fixed principal at a known interest rate. The shareholders recovery their actual costs of debt and a return on equity preset by the Commission over a preset period of time. This is entirely analogous to what we are providing ratepayers in the current circumstance, we will take ratepayer capital and return it to them over a multi-year period at a preset interest rate. The only differences are that we are not guaranteeing the ratepayers a fixed pay back period, and, unlike with utility return, there are no Federal laws which require the Commission to ensure that ratepayers are provided a fair opportunity to recover their capital and return.36 Whereas a utility would have legal recourse should a future Commission attempt to limit the utility's recovery of its capital, ratepayers would have little opportunity to challenge such a future Commission decision regarding the DA CRS, since it is merely a matter of Commission policy that bundled customers should be made indifferent to the DA CRS, not a matter of Federal law..
We thus conclude that the only reasonable benchmark for the interest rate on the DA CRS undercollection is the utilities' WCOC. We do not consider the three-month commercial paper rate to be applicable for financing DA CRS undercollections. Three-month commercial paper typically compensates for shorter-term debt, and is frequently applied to utility balancing accounts, because short term debt is how the utilities finance those accounts. Thus, the use of short -term debt interest rates is appropriate in circumstances where short term debt is used to finance undercollections, such as SDG&E's AB 265 account. Short-term debt is not how ratepayers will finance the capital that will be taken from them to pay the DA CRS undercollection. Although some balancing accounts have been set up to finance under or overcollections with a life extending beyond one year, balancing accounts are not typically been used to finance undercollections of the magnitude and length of time anticipated for the DA CRS.
Although certain parties point to the as examples of balancing accounts such as the TCBA and PROACT with multi-year lives that accrue interest at the three-month commercial paper rate, such accounts are not analogous to the DA CRS undercollection. The TCBA was trued up every year, and any undercollections (or overcollections) were offset in rates in the subsequent year. The repayment period for SCE's PROACT undercollection was limited to four years, and the actual repayment period is now expected to be only about two years. In addition, the PROACT settlement called for SCE to recover its actual interest costs, which could potentially have included longer term debt. Also, in the case of the TCBA, a short-term interest rate was applied with the expectation that the residually determined headroom revenues would fluctuate between positive and negative balances on a month-to-month basis. The DA CRS undercollection, however, is not expected to fluctuate between positive and negative balances on a short-term basis in this manner, but rather will be amortized over a period of years. We also note, that the utilities were allowed to earn interest at the WCOC rate for the uncollected portions of their transition costs, which were to be recovered over the four year transition period. Again, the Commission used the WCOC as the appropriate interest rate for multi-year recovery of capital during the transition period, and short term debt as the interest rate for the TCBA since the TCBA was not a multi-year undercollection financed with utility capital.
Two measures of long term debt were offered into the record. SCE offered its own utility long-term debt of 8.1%. No comparable figures were offered for PG&E or SDG&E. Farm Bureau offered a broader economy-wide measure of corporate long term of 7.1% for 2002 and 7.6% as a 10-year average based upon statistics from Moody's Investment Services Corp.
Certain parties (e.g., ORA and TURN) have argued that the default risk associated with DA CRS undercollections is particularly high, and should be compensated at a rate higher than corporate interest rates on long-term debt. We find no basis, however, to quantify any further interest rate premium related to the default risk associated with repayment of the DA CRS undercollection. For similar reasons, we decline to adopt the 12% interest figure proposed by Farm Bureau applicable to residential customers. This figure is much lower than the pre-tax utility equity investors earn.
ORA and TURN identify potential risks that repayment that the term of payoff will take longer than expected, or that individual DA customers will either go bankrupt or relocate outside of California, thereby defaulting on their repayment obligation. We have addressed these risks through the design of the DA CRS mechanism. To the extent that the forecasted payoff term varies from actual results, we have provided for periodic reevaluation of the cap so that adjustments can be made to assure timely repayment.
Moreover, we have designed the DA CRS methodology such that the repayment is a liability of the entire class of DA customers who took bundled service after February 1, 2001. Thus, even if individual DA customers possibly default on their share of the DA CRS repayment, their share shall be reallocated back into the total pool of DA CRS obligations in the periodic cap redeterminations. We are also adopting the accounting and tracking recommendations of ORA to ensure that DA cost responsibility is properly assigned to the respective customer group. Because the DA CRS cap and progress toward repayment shall be reviewed on an ongoing periodic basis, the per-kWh obligation assigned to the remaining pool of DA customers will be adjusted, as necessary, to absorb any increase in the undercollection attributable to defaulting DA customers.
Likewise, repayment of the DA undercollection will not be jeopardized to the extent that DA customers return permanently to DA bundled service since we have required that such customers shall still remain liable for paying their applicable share of the DA CRS undercollection. Moreover, DA customers returning to bundled service will continue to pay the applicable DWR Bond Charge and tail CTC as part of bundled charges.
Certain parties claim that bundled customers are at risk for DA CRS repayment as a result of the chance that a future body of commissioners may change existing commitments and reduce or cancel DA CRS repayment obligations. Yet, by law, the Commission may not arbitrarily or capriciously to change established rules and obligations in a Commission order. Changes in a Commission order require due process with opportunity for interested parties to be heard. We find no reasonable basis to speculate that a future Commission order might reverse or nullify the obligations that are now in place requiring timely reimbursement to bundled customers of DA CRS undercollections.
However, we have stated that there are policy reasons why it is important to retain DA service as a viable option. Thus, we ourselves have indicated that there may be reasons for a future Commission to limit the charges paid by DA customers. Since it is solely a matter of Commission policy that bundled customers should remain indifferent to the existence of DA service, it would likely be within the authority of a future Commission to limit the ability of bundled customers to recover the capital being provided to DA customers as a result of the cap on the DA CRS. By comparison, Federal law requires that the Commission provide the utilities with a reasonable opportunity to recover their capital and a return on their capital for reasonably incurred costs. Thus, the Commission would be precluded by law from not allowing a utility to recover their capital, providing utilities with much greater protection than bundled customers have.
We further conclude that the interest rate should not be applied on an after-tax basis to non-core customers and on a pre-tax basis to core customers, based upon the customer allocation groupings proposed by ORA. Because the non-core applies primarily to business customers, interest is generally tax deductible for them. Thus, DA customer will be able to deduct the costs of the interest they will pay on the DA CRS undercollection. Similarly, bundled business customers will pay taxes on the interest that they earn on the capital that is provided to DA customers. If the interest rate on the undercollction is set using an after tax interest rate, DA customers will be provided with a doubling of the deduction benefit, while bundled customers will essentially be taxed twice. Likewise, because core customers tend to be residential in nature, they typically cannot deduct interest, or their costs of electricity.
7. Effects of the Cap on DA Economic Viability
As stated above, one of the goals underlying the level of DA CRS cap is to seek to preserve the economic viability of DA. In prior decisions, we have determined that it is in the public interest to maintain the economic viability of DA. For example, we stated in D.02-03-055:
"AReM and others contend that an earlier suspension will negatively affect California businesses, and thus, affect the California economy. With increased electricity costs resulting from an earlier suspension, California's economy may suffer if firms relocate or choose not to enter the state. ... . [S]uch increased costs also affect important state functions, such as the delivery of quality education. ... . Further, ORA states "direct access is a means of diversifying the California electric power market, and therefore helps to protect California against uncertainty." Moreover CMTA/CLECA notes that the growth of direct access load in summer 2001 contributed substantially to a $2.6 billion reduction in the level of the DWR revenue requirement estimate for the period through December 31, 2002. We agree...that there are significant risks associated with an earlier suspension date as well as benefits associated with retaining a viable direct access market."
a) Parties' Positions
Parties are in dispute concerning to what extent increases in the existing cap can be tolerated without making DA economically unviable. Although various parties representing DA interests complain as to the financial difficulties of absorbing even the existing 2.7 cents cap, no party argued that any reduction in the cap below 2.7 cents was required to maintain the overall viability of DA.
Parties raise a number of considerations in assessing the relationship between the level of any DA CRS cap and the continuing economic viability of DA. At one level, the question is whether the alternative to DA viability is a return to utility bundled service. At another level, the loss of DA viability may be expressed through businesses relocating outside the State of California, or simply business contraction (in the extreme, going out of business).
CLECA witness Barkovich testified that some companies are considering moving to neighboring states so that they can still service their California customers. For industrial customers that are significant users of electricity, especially in a recession, the cost of power is a critical issue. If power prices rise high enough, some businesses have alternatives to operation in California. Manufacturing customers competing with imports can import partially or fully manufactured products rather than produce them in California, and California manufacturing jobs will be lost.
DA parties argue that the Commission should take into consideration the impact of any increase in the CRS cap on the ability of direct access customers to remain competitive in their industries. CLECA witness Barkovich testified that an increase to 4 cents would, when added to generation procurement costs and transmission, distribution and other related utility costs, render the direct access service uneconomic relative to bundled service.37
The risk of losing DA load to bundled service is particularly pronounced in the case of SCE, which has applied for and anticipates substantial bundled service reductions in customer bills on or about July 1, 2003. ORA states that its support for an increase in the SCE cap to no more than 3 cents for SCE in view of this proposed reduction in A.03-01-019. ORA believes that an increase up to 3 cents for SCE now will prevent the problem of DA viability from becoming worse later on. ORA questions the contention that an increase in the cap from 2.7cents to 3 cents will cause DA customers to go out of business en masse. SCE likewise argues that DA appears to remain vigorous under the 2.7cents per kWh cap based on current DA load statistics and recent requests by DA customers to add load to DA accounts and to maintain DA status for relocated accounts.38
ORA's Exhibit 163, Attachment B, shows that at generation procurement prices above 5 cents, there is little room for any increase in the cap and that following the anticipated SCE reduction in customer bills, the cap room for TOU-8-Sub customers falls to less than 1 cent. This means that direct access will then be more costly than bundled service even at the current 2.7 cent cap. ORA's cross-examination of PG&E witness Rifas offers the prospect that PG&E's bundled service rates may also be falling in the not-too-distant future,39 thereby creating the same issue on PG&E's system.
SCE argues that a cap raised to 3 cents would not make DA uneconomic. SCE notes that while CLECA favors the 2.7 cents per kWh cap, it ultimately recommended "that the cap stay in the range of 2.5 to 3 cent per kWh."40 CLECA made this recommendation with knowledge of SCE's post-PROACT reduction recommended in A.03-01-019.41 Similarly, although CMTA's "primary recommendation is to maintain the 2.7 c/kWh cap," its witness conceded that "if the Commission decides that the cap should be increased, CMTA recommends that the cap not exceed 3.0 c/kWh."42
None of the parties representing DA interests provided concrete data regarding the current prices that they are paying for power to allow the Commission to "quantify the precise relationship between the level of a cap and the number of DA contracts that may become uneconomic," which was the stated aim of D. 02-11-022.43 Testimony presented as to the economic impacts of the DA CRS cap was anecdotal in nature, but did not provide broad or comprehensive statistics on the overall effect on the DA program. A more comprehensive empirical evaluation of the effects of various cap levels on DA economic viability is impeded by the lack of specific information on the energy prices DA customers currently pay their ESPs. DA customers remain unwilling to disclose contractual pricing information that could potentially be used by competitors.
Strategic Energy, for example, presented evidence on how the DA CRS will increase the energy costs of DA customers. As an example of the effects for a large retail customer, Target Corporation estimates that the 2.7 cents cap will translate into about $11 million per year, or $40,000 per store annually. Testimony was also presented on the effects of the DA CRS on the California's higher education system which is a DA customer.
In addition to business customers, DA is also utilized by public institutions, such as the UC/CSU system and municipalities such as Corona. For such institutions, the viability of DA affects not only employment levels but also arguably the quality of educational opportunities and quality of municipal services. UC/CSU alleged that increases in the DA CRS cap could cause colleges to cut back on services to students. UC/CSU states that an increase in the cap to 3 cents would require colleges to deny class access to 315 students. UC/CSU thus does not focus its analysis on the question of whether cap increases could render the DA option no longer viable as an economic option. Rather, their focus seems to imply increases in the cap would not cause UC/CSU campuses to discontinue DA, but would rather cause them to cut other university programs and services to offset cost increases in DA.
PG&E does not address how increasing the currently adopted 2.7 cent DA CRS cap to 4 cents per kWh would affect DA economic viability or whether it would force direct access customers to shut down or relocate their operations. PG&E believes that while raising customer charges is an important concern, it is important for bundled as well as DA customers. PG&E argues that even with a 4 cent cap, DA is competitive with bundled service, assuming DA power prices at about 5 cents per kWh. PG&E thus believes that a better basis for setting a cap is to limit the period of time during which DA customers lean on bundled customers, rather than lower direct access customers' charges now at the expense of a longer payback period for the loan from bundled to direct access customers.
TURN and Farm Bureau argue that raising the DA CRS cap to as high as 4 cents per kWh would not impair the economic viability of DA. TURN argues that there is no evidence that a low cap would be better for the state's economy than a high cap, or no cap at all on DA CRS. TURN argues that the cap does not eliminate overall system costs, but merely shifts those costs from DA customers to bundled customers. TURN argues that whatever adverse economic effects may result from the imposition of DWR costs on DA customers, the same potential risks face bundled customers to the extent they must shoulder those costs. Because the cap simply defers, but does not eliminate, the DA CRS payment obligation, TURN argues that a low cap does not promote any greater economic development than a high cap or no cap.
TURN also argues that the correct analytical approach to evaluating DA economic viability resulting from any cap should focus only on the avoidable costs facing DA customers if they return to bundled service. Because the DA customer cannot avoid the DWR bond charge, other past DWR shortfalls, the HPC, or CTC by returning to bundled service, TURN argues that these elements are not relevant for assessing the economic consequences of a DA CRS cap. TURN contends that the only relevant comparison for purposes of determining a cap is between (1) ESP charges plus DWR power charges versus (2) the bundled generation rate plus any allocated shortfall resulting from a DA CRS cap.
PG&E proposes raising its cap as high as 4 cents per kWh. ORA believes that PG&E can support a 4-cent cap, at least in the near term, without causing DA contracts to become uneconomic to a significant degree. PG&E is still under frozen bundled rates that include high surcharges. ORA argues that the reduction in the current DA credit resulting from a 4-cent cap would still leave DA contracts that are at current market rates less expensive than bundled rates. (ORA Ex. 163, Attach. B.) ORA thus advocates raising PG&E's CRS cap to 4 cents for a short while, with the aim of paying off the CRS undercollection faster. When PG&E's surcharges are terminated, ORA agrees that reducing PG&E's CRS to something closer to SCE's proposed 3 cent cap could be considered.
While not disputing that a higher DA CRS cap might impact the businesses of current DA customers, SCE argues that bundled service customers face the same hardships caused by a sluggish economy as DA customers state they are experiencing. A lower DA CRS cap, lower interest rate and longer repayment period for DA customers translates into a longer period that bundled service customers must pay higher electric charges.
b) Discussion
The widely varying positions of parties concerning the impact of any DA CRS cap on the economic viability of DA highlight the lack of a properly developed record on this issue. The discussions on the economics of any cap continue to be anecdotal at best and we continue to be troubled by the notion that the assessment of the level of DA CRS cap needs to be considered in the context of maintaining DA economic absent any record. It's no surprise that parties representing DA customers would testify that any cap would render DA uneconomic. Some parties continue to argue that even a cap of 2.7 cents per kWh poses serious increases in electricity costs with some California companies even considering moving to neighboring states. Unfortunately, the record simply does not support such allegations nor have the parties presenting the cost impacts been forthcoming with information that would support those estimates. Indeed, it's not even clear whether some of the companies that presented cost estimates of the impact of a DA CRS cap are not continuous DA customers for whom the cap does not even apply44.
We agree with TURN that there is no evidence that a low cap would be any better for the State's economy than a high cap, or no cap at all. Further, we note that the elements covered under the cap include the same elements that that would apply under the DA or bundled service option. In assessing the economic viability of any cap on DA customers, it's worth pointing out that only the DWR going forward power charge is truly avoidable and the only component which impacts the viability of DA. Yet, the arguments against a cap continue to be based on a false impression of what charges can be avoided. We find that the record lacks any basis on which to assess whether the proposed caps of 4 and 3 cents per kWh for PG&E and SCE/SDG&E, respectively, will adversely impact DA customers. It is also important to note that the majority of California businesses are bundled customers, not DA customers. Thus, to the extent we limit the level of subsidies that bundled customers must provide to DA customers, we will be benefiting the majority of California businesses.
In addition, to the extent that we defer greater amounts to be recovered from DA customers in the future rather than now, we are creating the potential for the future demise of DA. Currently, DA providers must compete against bundled rates that include high DWR costs, transition costs and other costs that will likely decline over the next few years. By using a low cap now, we would increase the size of the future obligations of DA customers to repay bundled customers. Thus, future DA rates would be relatively high, and DA providers would need to then compete against bundled rates that are even lower than current bundled rates. By deferring DA costs now, we will need to increase DA costs later when DA providers are likely to be less able to compete. This could result in the end of the viability of DA as an option, albeit in a few years, which is the very thing we are attempting to avoid by setting a cap on current DA costs. We must balance the need for keeping DA costs low now, with the need for keeping DA costs low in the future as well. We find the best way to do that is to adopt the 4 cent/kwh cap on the current DA CRS, in an effort to minimize the amounts that will need to be collected from DA customers in the future.
8. Allocation of the DA CRS Undercollection to Bundled Customer Groups
In D.02-11-022, we adopted TURN's recommendation that any financing of the cap shall be retained with the same customer classes that benefit from the cap.45 On February 5, 2003, a Petition for Modification was filed by CLECA seeking clarification from the Commission of this provision to state that the loan is to be provided by bundled customers generally to DA customers generally, without specification by customer class. Parties have addressed the issue of how to implement this provision of D.02-11-022 relating to the allocation of the DA CRS financing of the cap as part of this proceeding.
a) Parties' Positions
CLECA questions whether the term "financing" as used in D.02-11-022 refers to the interest costs associated with any loan or to the entire loan. CLECA argues that the answer has very substantial ramifications for bundled customers in the Large Power class. If the DA CRS were implemented to spread the shortfall as broadly as possible across bundled sales, the effect on any particular customer is quite small. If it is implemented to concentrate the cost of the shortfall caused by the application of the cap to Large Power DA customers, on the bundled customers in that class, CLECA argues, the cost to some bundled customers would be significantly increased while others would bear essentially no part of the burden. CLECA contends that TURN's proposal to retain the shortfall within customer classes and/or rate groups on the basis of the percentage of direct access load in each class or rate group would unduly punish bundled industrial customers.
DA service was available to all utility customers in 2001 until its suspension effective on September 20.46 CLECA argues that there is no reason why bundled customers in a class or rate group that happens to have a significant amount of direct access load should bear a greater share of the CRS undercollection burden than bundled customers in other classes. Industrial bundled service customers are no more responsible for the decision of some customers to choose direct access than are bundled residential customers. CLECA notes that the subsidy created by several other programs, the benefits of which are only available to one customer class, are explicitly spread to all customers. The costs of these programs are explicitly spread to all bundled sales without regard to participation levels by customer class or rate group.
Further, unlike the CRS shortfall, these programs do not contemplate any repayment obligation by the beneficiaries, but are simply subsidies covered by other customers and sales. In contrast, the CRS undercollection is a loan from bundled customers to direct access customers. It is not a subsidy or payment, but will be repaid with interest.
CLECA witness Barkovich testified that the allocation of the shortfall on the basis of direct access sales by customer group would have a severely disproportionate impact on Edison's TOU-8-Sub customers.47 Using CLECA's recommended Scenario 14 results, the indicated maximum undercollection would result in an impact of roughly 0.3cents per kWh if spread to all bundled sales uniformly, but would cause a more significant 1.7cents per kWh impact on the bundled service customers in TOU-8-Sub if spread on the basis of the TURN proposal. The impact on these customers is nearly six times as great under the TURN approach. Further, if another scenario is adopted, or if the maximum undercollection exceeds that indicated in Scenario 14, the adverse result is magnified. Adoption of the Base Case Scenario 6 maximum undercollection of $505 million would result in a rate impact on these TOU-8-Sub bundled service customers of well in excess of 4 cents per kWh,48 nearly as much as some of them were paying for their full utility service in 2000 before the energy crisis hit California.
CLECA argues that there is no logical basis to impose this sort of penalty on the very large industrial customers who bore the brunt of the Commission's surcharge increases in January and June of 2001, and that such an allocation of the CRS shortfall would be bad public policy, and bad for the State's economy.
SDG&E agrees in principle with CLECA that DA CRS undercollections should be spread across all bundled customers, but proposes one modification to provide that the undercollection be allocated in proportion to customers' non-exempt bundled usage. SDG&E thus proposes to exclude residential usage up to 130% of baseline, medical baseline usage and CARE usage that are currently exempt from commodity charge increases beyond the 6.5 cents per kWh charge that existed on February 1, 2001, pursuant to AB 1X.
PG&E proposes that any future reduction in bundled customer bills associated with a DA DWR power charge shortfall that occurs while bundled customers are on frozen rates be allocated back to all bundled load equally.49 Under its current tariffs, PG&E argues that no subset of bundled customers has contributed more to covering the DA shortfall than has another. PG&E's shortfall will not cause any immediate change to bundled customers' electric bills, what PG&E bundled customers' pay for electricity will remain at their current, frozen levels.50 Just as is the case currently, PG&E's remittance obligation to DWR will be met through the combination of the revenues from bundled and direct access customers, with any remaining amount constituting headroom. PG&E argues that since no one subset of customers has contributed more to covering the shortfall than any other, it follows that when direct access customers begin to make up this shortfall, there is no basis for using this "make up" revenue from direct access customers to lower one subset of bundled customers' bills more than another.
Since any assignment would have nothing to do with costs paid for by bundled customers, PG&E argues, the assignment would in no way relate to any additional burden borne by various groups of bundled customers due to the DA DWR power charge shortfall. PG&E thus argues it would make no logical sense to use this artificial assignment as a basis for differing reductions later, because those reductions would confer a very real benefit.
In short, there is no reason at this point for the Commission to make any determination as to which of PG&E's bundled customers bear the burden of any DA DWR power charge, because under current frozen rates, which will not be changed to reflect the shortfall, there is no basis to conclude that any given subset of bundled customers bears more of the burden than do others.
ORA acknowledges that extreme impacts on customer charges would be caused by defining the term "class" too narrowly for purposes of implementing class allocation of the undercollection as required by D.02-11-022. At an informational hearing of the State legislature, it was shown that large industrial rates for bundled customers could increase as much as 4.3 cents per kWh in the near term.51 Such an increase would totally cancel any decrease customers will receive when the surcharges are eliminated in A.03-01-019. This impact would decrease as the CRS itself goes down, but it may persist for several years under some scenarios. This would render bundled customers uncompetitive with direct access customers in the same industry for some time. Given that the issue of business failures and customers moving out of state were concerns that underlie the need for the cap,52 such a result would be contrary to the intent of D.02-11-022.
Because of these problems, ORA proposes that only two major "classes" be defined, distinguished as core and non-core, for allocating the CRS undercollection. Similar to the firewall for CTC purposes in Assembly Bill (AB 1890), the core class would include all residential and small commercial customers under 20 Kilowatts ("kW") in load. ORA's definition would depart somewhat, however, from that of AB 1890 by including agricultural customers under 20 kW in the core class. Core would also include streetlighting customers. Because the penetration of direct access in the agricultural class in general is quite low for all three utilities, ORA proposes that the agricultural customers under 20 kW not be held responsible for the undercollections caused by the large industrial customers.53
No matter how classes are defined, bundled customers on tariffs with low direct access penetration that are grouped with customers on tariffs with high direct access penetration will complain of unfairness. While spreading the undercollection uniformly to all customers would minimize this inequity, doing so would moot the protection that D.02-11-022 was attempting to provide.
ORA argues that defining these two broad classes would not result in cost impacts to bundled non-core customers much different than if the undercollection had been allocated to all customers, at least for SCE. Using SCE's workpapers in A.03-01-019, ORA calculates that customer charges would increase by about 0.7 cents per kWh if the undercollection were allocated uniformly to all customers. If the undercollection were retained within separate core and non-core classes as defined by ORA, core rates would remain virtually unchanged and non-core rates would increase by approximately 1.0 cents per kWh.
ORA proposes a non-core class that would comprise customers with over 20 kW in load. The CRS undercollections from the core class would be allocated to the bundled core customers, and the undercollections from the non-core class would be allocated to the bundled non-core customers. (See ORA Ex. 162, pp.10-12.)
ORA characterizes its recommendation as a pragmatic approach preserving the intent of D.02-11-022 by affording protection from the effects of a CRS cap to customer classes with low rates of DA participation. ORA's proposal is intended to protect small customers and help moderate large increases that industrial customers could face if the CRS shortfall was allocated by customer class or industrial tariff schedule.
TURN and SCE support the core/non-core split for the purposes of allocating CRS undercollections. (TURN Ex. 169, pp. 14 - 15; SCE Ex. 160, pp. 15 ff.) ORA's proposal is a modification of the original proposal made by TURN adopted in D.02-11-022 that was designed to protect customer classes with a low rate of DA participation and to ensure that customer classes with low rates of participation in DA do not subsidize those classes with higher rates of participation
ORA broadened the definition of customer classes originally proposed by TURN,54 resulting in smaller increases for industrial customers than if the undercollection had been allocated to classes as currently defined while still protecting customers with low rates of DA participation. (SCE Ex. 160, Table #2.)
b) Discussion
We do not change the allocation of the DA CRS undercollection adopted in D. 02-11-022. Keeping the costs within each customer class is appropriate and consistent with the way the Commission and the Legislature have determined that transition costs, costs for energy efficiency programs and other costs should be allocated. Parties have not provided any evidence that demonstrates that keeping DA CRS undercollections within each customer class is unfair nor have they shown any reason why our prior decision should be modified.
Quite the contrary, the proposals to change our prior allocation are eminently unfair to broad classes of consumers. The ORA approach preserves somewhat the intent of D.02-11-022 concerning the assignment of the undercollection among different categories of bundled customers. The intent was to ensure that customer groups with low rates of participation in Direct Access (primarily residential and small commercial) do not subsidize customer groups with high levels of participation. ORA's approach modifies this approach, , requiring small customers to pay the DA undercollection associated with large agricultural DA customers. ORA's approach also makes an enormous change in the allocation of the undercollection of industrial DA customers.
Under D. 02-11-022, the industrial DA undercollection would be paid for by bundled industrial customers. ORA's proposal would instead have the industrial DA undercollection paid for in large part by commercial customers, including office buildings, schools, government buildings, restaurants and other groups. There is no evidence to justify making schools and the California government pay more now to reduce the costs of large industrial DA customers. Such an approach will only exacerbate the State's budget problems and likely result in even greater layoffs of teachers and other government employees and further reductions in State services than are currently being contemplated. Given the woeful state of the economy in California, it is also inequitable to saddle small businesses and commercial customers with the costs of keeping large industrial DA customers' electric rates low.
ORA's approach modifies the original TURN financing proposal by broadening the definition of customer class. ORA's approach was the most reasonable presented by any party in this proceeding, leading to the lowest shifting of costs among customer classes of any of the proposals presented to us. However, even ORA's approach is flawed and unfair to the residential customers who would be forced to subsidize large agricultural interests, and to commercial and government customers that would be forced to subsidize large industrial companies. Thus, no modification offers a pragmatic solution that balances the effects of the undercollection on both small and large customer groups. The allocation adopted in D. 02-11-022 shall remain unchanged.
8 The scenario modeling for SDG&E was initially done on a dual basis showing alternate results due to uncertainty as to whether 80 MW of United States Navy load was deemed to be exempt from the DWR components of the DA CRS. The Commission subsequently issued D.03-05-036 on May 9, 2003, affirming that the 80 MW of Navy load is indeed subject to the DWR charges. Accordingly, the treatment adopted in D.03-05-036 is incorporated into the modeling runs relied upon for purposes of analysis of the appropriate cap in this decision. 9 Competition Transition Cost (CTC) was identified in D.02-11-022 as the URG-related component of the DA CRS. 10 The revised calculations were submitted on May 13 with an update on May 15. Parties had only 4 days for comments with one conference call to discuss the revised numbers. 11 Barkovich, CLECA, Ex. 167, p. 10. 12 AReM/WPTF, Ex. 181, at 16. 13 CMTA, Ex. 172 at 5:8-3 14 RT pp. 2054-2055, (McDonald/DWR). 15 RT p. 2056 (McDonald/DWR); RT p. 2073 (McMahon/DWR). 16 RT p. 2058 (McDonald/DWR). 17 CMTA/McGuire, Ex. 172, pp. 7-8 (Table 1). 18 Barkovich, CLECA, Ex. 167, p. 10. 19 SCE/Collette, Ex.160, pp. 4-5. 20 PG&E/Rifas, Ex. 155, p. 1-5. 21 All statutory references are to the Public Utilities Code. 22 Ex. 167, p. 9. 23 D.02-11-022, p. 77 (slip op.). 24 DWR, Ex. 150, p. 7. 25 RT p. 2046 (McDonald/DWR). 26 RT pp. 2138-2140 (Burns/PG&E). 27 Collette, Edison, Ex. 160, p. 10. 28 RT p. 2228. 29 RT pp. 2136-2137 (PG&E/Burns). 30 Currently, the simple average authorized cost of capital is 9.25%. Pursuant to D.02-11-027, the authorized costs of capital of the three utilities are 9.24% (PG&E), 9.75% (SCE), and 8.77% (SDG&E). 31 See ORA Ex. 162, Attach. A. 32 ORA cites to the ALJ ruling of October 25, 2000 in A.99-09-049. 33 See D.02-11-074 34 SDG&E is affiliated with Sempra Energy Solutions, one of the largest direct access service providers in California. 35 RT p. 2300 (Hansen/SDG&E). 36 See Hope and Bluefield. 37 Barkovich, CLECA, Ex. 167, at pp. 13-17. The 4 cent figure was used by DWR in its scenario analysis. 38 SCE/Collette, Ex. 160, pp. 6-8. 39 RT pp. 2114-2117 (Rifas/PG&E); Exs. 157 and 158. 40 CLECA/Barkovich, Ex. 167, p. 26. 41 CLECA/Barkovich, Ex. 168, p. 6. 42 CMTA/McGuire, Ex. 173, p. 9. 43 D.02-11-022, p. 108 (slip op.); RT pp. 2370-2371 (CMTA/McGuire). 44 We note, for example, that UC/CSU has been a continuous DA customer. 45 D.02-11-022, p. 117 (slip op.). 46 Barkovich, CLECA, Ex. 167, p. 21. 47 Barkovich, CLECA, Ex. 167, p. 23. 48 This figure is simply 1.7¢ times the ratio of $211 million to $505 million. 49 Ex. 155, p. 1-4. 50 Ex. 155, p. 1-4. 51 This hearing was held in San Pedro, California on February 28, 2003 and chaired by Senator Debra Bowen. A bar chart containing the impacts of the CRS undercollection was presented and is available on the California State Senate website www.sen.ca.gov/ftp/SEN/COMMITTEE/STANDING/ENERGY/_home/