4. PG&E's Existing System

In response to Appendix A of the ACR, PG&E provided testimony on system design, staffing, call center performance, deployment of resources, outage commissions, and reliability performance in general and during the December 2002 storms. PG&E's electric distribution system serves 4.7 million customers throughout Northern California, from Eureka in the north, to Bakersfield in the south, and extending from the Sierra Nevada Mountains in the east, to the Pacific Coast in the west. Approximately 50% of PG&E's customers reside in the San Francisco Bay Area. PG&E maintains 2.3 million poles, 93,000 miles of overhead circuits, 22,000 miles of underground circuits, 300,000 underground enclosures, and 2,500 distribution substation transformers. PG&E trims or removes approximately 1.8 million trees annually to ensure clearance between vegetation and overhead lines and maintain compliance with all rules and regulations.

Electricity consumed by PG&E's customers is delivered to PG&E's distribution system via high-voltage transmission lines. PG&E has almost 800 substations that connect PG&E's distribution system to the high-voltage transmission system. These substations are the central hubs of PG&E's distribution system. Each substation transforms the high-voltage electricity (e.g., 230 kilovolt (kV)) to a lower voltage electricity (e.g., 12 kV) for delivery to end-use customers. Primary and secondary distribution lines extend from each substation and deliver electricity overhead or underground. Local transformers that further lower the voltage level (e.g., 12 kV to 240 volts (V)) and switching equipment link the distribution lines in patterns that provide service drops to meters at customer premises.

PG&E's service territory is divided into 7 operating areas, 18 operating divisions, and 3,033 individual circuits. Service reliability and staffing varies by area and division due to circuit design, geography, customer density and other factors. Table 1, below, contains the 2002 Division and system values for the number of customers served, the number of circuits, the line miles of primary overhead and underground distribution circuitry, and the SAIDI and SAIFI performance indices.

TABLE 1

PG&E 2002 SERVICE RELIABILITY METRICS BY DIVISION


Division


Customers


Circuits


OH Miles

UG Miles

Total Miles

Excluding Major Events

SAIDI SAIFI

Including Major Events

SAIDI SAIFI

Central Coast

      290,610

    163

    5,839

    1,125

    6,965

206.6

    1.390

    605.2

2.273

DeAnza

      216,340

    121

    1,741

    828

    2,569

101.7

    0.838

    387.5

1.418

Diablo

      292,653

    128

    2,239

    2,093

    4,333

124.1

    1.372

    203.4

1.729

East Bay

      356,741

    206

    1,765

    875

    2,641

111.7

    0.980

    189.3

1.451

Fresno

      380,985

    285

    10,867

    2,064

    12,932

161.0

    1.323

    218.2

1.518

Kern

      216,083

    228

    7,035

    1,162

    8,197

151.3

    1.201

    184.9

1.335

Los Padres

      187,360

    76

    4,578

    876

    5,454

121.0

    1.177

    162.4

1.490

Mission

      361,329

    156

    1,823

    2,326

    4,150

65.5

    0.823

    99.0

1.084

North Bay

      245,682

    96

    2,805

    1,173

    3,979

138.2

    1.212

    747.5

2.521

North Coast

      362,934

    186

    10,455

    1,587

    12,043

223.1

    1.178

    1,098.1

2.330

North Valley

      199,093

    155

    10,055

    815

    10,871

231.2

    1.416

    977.6

2.458

Peninsula

      301,086

    201

    2,250

    1,062

    3,313

99.0

    0.978

    457.2

1.778

Sacramento

      192,811

    121

    4,899

    1,262

    6,161

165.2

    1.274

    280.0

1.711

San Francisco

      398,882

    254

    573

    620

    1,193

69.8

    0.624

    127.8

0.921

San Jose

      380,913

    155

    2,360

    2,156

    4,516

108.4

    0.931

    193.6

1.219

Sierra

      248,784

    149

    7,896

    1,346

    9,242

176.6

    1.200

    612.2

2.174

Stockton

      262,745

    191

    6,215

    1,427

    7,642

181.2

    1.314

    326.3

1.879

Yosemite

      225,733

    162

    10,958

    866

    11,824

137.5

    1.245

    215.1

1.497

System

      5,120,764

    3,033

    94,361

    23,671

    118,033

139.2

    1.112

    381.9

1.670

As of December 31, 2002, PG&E employed a total of 3245 electric field personnel, a reduction of 14% from the 3699 field personnel PG&E employed as of 1998. All electric field personnel are available for emergency response. PG&E does not have separate staff dedicated to "reliability," "maintenance," or emergency response functions. Rather, individuals in these job categories perform work in a variety of functions and may be installing facilities to connect new customers one day and restoring power during an outage the next day.

As discussed above, the metrics the Commission considers when examining PG&E's electric reliability include SAIFI, SAIDI, CAIDI, MAIFI, the number of circuits that consistently perform poorly, and the MR&ROs per line mile. During emergencies and severe storms, PG&E's performance is also measured against a service restoration performance metric.

In addition to these metrics, PG&E internally evaluates its performance using metrics related to employee safety, customer service, and call center performance. MR&RO, defined as the total number of unplanned sustained outages that could be influenced by inspection and maintenance activities, was developed to measure the effectiveness of PG&E's inspection and maintenance practices. PG&E's average performance from 1999 through 2001 for the MR&RO and the number of circuits with greater than 12 outages per year improved relative to 1996 through 1998 performance for MR&RO or 1997-1998 performance for the number of circuits with greater than 12 outages per year.

Prior to 2002, PG&E tracked Occupational Safety and Health Administration (OSHA)-recordable events to measure employee safety performance. However, PG&E is re-evaluating whether the OSHA recordables metric remains appropriate since OSHA changed its reporting rules and definitions effective January 1, 2002. PG&E's OSHA recordables performance from 1999-2001 improved relative to PG&E's performance from 1996-1998. For 2002, PG&E used three measures of lost work days: (1) lost work days per case; (2) lost work days; and (3) lost work days per employee.

PG&E also tracks customer service quality through customer surveys and by measuring the effectiveness of outage management functions, such as providing information about an outage and providing accurate information on how long an outage will last.

PG&E has a network of three call centers that provide customer service through a combination of service representatives and Voice Response Unit (VRU) systems at all times. The VRU automated self-service functions include a general service/information menu for account balances, payment arrangements, and appliance service appointments. There is also a VRU menu for outages, which includes options to hear outage status messages, to report outages, and to request a callback. The call centers have over 900 inbound telephone lines for customers, with a capacity of handling over 500,000 calls per hour. In a normal week, the call center representatives and automated response systems handle about 260,000 calls.

PG&E uses a computerized OIS to identify, track, and communicate information for electric outages. PG&E uses its OIS in two key ways: (1) to assist in deploying resources to address outages, and (2) to provide outage information to customers via the call center. PG&E's OIS links field information (e.g., outage location, causes, response assignments, and estimates of restoration) to PG&E's Customer Information System (CIS), which is used in the call centers to communicate with customers. The OIS receives outage information from several sources, including customer calls, automatic system devices located on PG&E's facilities, field personnel, and Enhanced Outage Notification devices located in customer homes. The OIS addresses outages affecting multiple customers, such as during storm events. For single customer outages, trouble reports are managed through the Field Automation System.

When an outage report is entered into the OIS system, the system notifies the appropriate dispatcher. The dispatcher then sends a troubleman to the outage location and initiates an outage record in OIS, with an estimated time of arrival. Once this information is recorded in the OIS it becomes accessible to customers through the call center.

When an outage call is received, the call center systems check the OIS for outage record and status information. If there is no record of an outage, the customer is advised of this and can report the outage. If there is a record of an outage, the call centers provide the customer with the available outage status information including the estimated time of restoration (ETOR).

PG&E tracks the ETORs provided to the call centers for each of its outages so that it can compare the ETOR times in its OIS with the actual time the power was restored. PG&E does not record the ETOR information provided to customers when they call and therefore cannot compare the ETORs received by the customers to the actual time of restoration. PG&E states that the comparison of the first ETOR to actual restoration time provides a measure of how well PG&E's field and dispatch personnel estimate the time it takes to restore service, and comparing the last ETOR to actual restoration time measures how well the ETOR improves over time as better information becomes available.

PG&E's OIS database contains information concerning outages recorded since January 1, 2000. Comparable data from PG&E's prior outage database, CTAS, was not archived, and is not available. For the past three years, from 2000 through 2002, PG&E's ETOR was, on average, within two hours of the actual time of restoration. During non-major event conditions, including storms, PG&E either provided an ETOR, or restored service within four hours to 85 percent of all outages. In other words, customers who called PG&E to find out the ETOR of their service were provided an ETOR that, on average, was within four hours of the actual restoration time.

There were three major events in PG&E's service territory from 2000 through 2002. During these major events, PG&E either provided an ETOR, or restored service within four hours to an average of 73 percent of the outages. The difference between actual restoration time and the first ETOR during the December 2002 storms averaged 11.52 hours, while the differences between the actual restoration time and first ETOR during the November 2002 storms and the November 2001 storm were 6.25 hours and 5.14 hours, respectively.

During storm events, an emergency plan is used to supplement normal call center operations in responding to the storm. The emergency plans cover extending hours, adding service representatives and conducting daily conference calls during storms to review and assess operations performance. In addition, during storm events, one or more of PG&E's Operations Emergency Centers is activated to expedite the deployment of restoration resources and assist in outage communications.

As shown in Table 2 below, PG&E's SAIFI has been improving, from a high of 1.709 in 1996 to a low of 1.112 in 2002.9 PG&E's SAIFI from 1999-2002 was better than the average performance from 1996-1998.

TABLE 2

Year

SAIFI

Major Events Excluded

SAIFI

Major Events Included

    1996

    1.709

    2.462

    1997

    1.639

    1.700

    1998

    1.659

    2.130

    1999

    1.477

    1.481

    2000

    1.410

    1.413

    2001

    1.439

    1.559

    2002

    1.112

    1.670

    1996-1998 Average

    1.67

    2.10

    1999-2002 Average

    1.36

    1.53

Similarly, Table 3 shows that while PG&E's SAIDI performance has fluctuated from year to year, PG&E's average SAIDI performance from 1999-2002 has improved slightly relative to PG&E's average SAIDI performance from 1996-1998.10

TABLE 3


Year

SAIDI

Major Events Excluded

SAIDI

Major Events Included

1996

178.1

347.0

1997

161.8

171.3

1998

180.0

317.0

1999

156.7

157.2

2000

167.9

168.4

2001

211.8

249.1

2002

139.2

381.9

1996-1998 Average

173.3

278.43

1999-2002 Average

168.9

239.03

9 Exhibit 13, Table 2-4, p.2-16 10 Exhibit 13, Table 2-5, p.2-17.

Previous PageTop Of PageNext PageGo To First Page