II. Procedural Background and The Stipulation

A. Procedural Background

By rulings on September 22, 1999, October 5, 1999, and November 12, 1999, the ALJ ordered the parties to submit additional testimony regarding issues identified in the Scoping Memo and necessary to determine whether the costs sought for recovery were reasonable under § 454.9. SoCalGas provided some additional testimony on November 15, 1999.4 SoCalGas also provided substantial information to the Commission's Energy Division in response to data requests. On November 12, 1999, the ALJ set tentative hearing dates on the settlement for January 6 and 7, 2000.

After reviewing the additional information presented, the ALJ determined that an evidentiary hearing remained necessary to establish a complete record and to effectively evaluate the stipulation to determine whether it is in the public interest. By ruling dated December 17, 1999, the ALJ directed (a) SoCalGas and ORA to produce witnesses and supporting documentation to explain and support the stipulation, and (b) SoCalGas to produce witnesses and supporting documentation to support its application. SoCalGas was asked to put into the record responses and documents submitted to the Energy Division in response to data requests. We affirm the ALJ's rulings.

The Commission held evidentiary hearings on January 6 and January 7, 2000. The parties submitted opening briefs on February 4, 2000 and reply briefs on February 18, 2000. The record was reopened on May 15, 2000 to receive additional late-filed exhibits and the case was submitted on May 30, 2000. As such, we have a record upon which to evaluate the stipulation and SoCalGas' application.

B. The Declared Disaster

a. The commission shall authorize public utilities to establish catastrophic event memorandum accounts and to record in those accounts the costs of the following:

b. The costs, including capital costs, recorded in the accounts set forth in subdivision (a) shall be recoverable in rates following a request by the affected utility, a commission finding of their reasonableness, and approval by the commission. The commission shall hold expedited proceedings in response to utility applications to recover costs associated with catastrophic events.

C. SoCalGas' and ORA's Stipulation

D. Standard of Review

The Commission will not approve stipulations or settlements, whether contested or uncontested, unless the stipulation or settlement is reasonable in light of the whole record, consistent with law, and in the public interest.

[T]he standard of review [under Rule 51.1(e)] is somewhat more stringent. Here, we consider whether the settlement taken as a whole is in the public interest. In so doing, we consider individual elements of the settlement in order to determine whether the settlement generally balances the various interests at stake as well as to assure that each element is consistent with our policy objectives and the law." (D.96-01-011, 64 CPUC2d, 241, 267, citing D.94-04-088.)

Parties to the settlement may chafe at what they perceive as intrusion on bargained-for deals and may believe that this Commission should simply take their word that the settlements serve the interest of the public in addition to the interests of the settling parties. However, settlements brought to this Commission for review are not simply the resolution of private disputes, such as those that may be taken to a civil court. The public interest and interests of ratepayers must also be taken into account, and the Commission's duty is to protect those interests. (Id., at p. 360.)

E. Positions of the Parties

F. Review In Light of the Whole Record

While costs incurred for repairs may well be significant, they may not necessarily all be properly recoverable from ratepayers. Recovery may be limited by consideration of the extent to which losses are covered by insurance, the level of loss already built into existing rates, and possibly other factors relevant to the particular utility and event. Before authorizing recovery from customers of any costs, the Commission will examine how they relate to the overall costs currently authorized for these types of repairs. . . . As with any rate increase request, the Commission staff will review the basis for the increase request and make a recommendation to the commission as to the amount in the account to be recovered in rates.

Where a rate case is litigated or a settlement is contested, the utility must provide a more detailed showing for all of its requested revenue requirement, in order to sustain its burden of proof. Where a settlement is adopted by all parties and is consistent with relevant law and Commission policy, the utility must provide a more detailed showing to enable the Commission to be confident both the settlement can be well understood in the context of the company's initial request and that the Commission and its staff will have sufficient information with which to monitor the utility's activities and costs." (supra, at p. 27.)11

1 All references are to the Pub. Util. Code unless otherwise stated. 2 SoCalGas states that $1,903,104 reflects incremental operating and maintenance (O&M) costs, which it proposes to recover over a one year period, and that $4,542,695 reflects capital costs, which it proposes to amortize. 3 In a late-filed exhibit, SoCalGas shows the proposed recovery of total carrying costs associated with capital investments of $14,657,751 exclusive of franchise fees and uncollectibles. (Exh. 24.) However, SoCalGas points out that the cost recovery schedule will most likely vary greatly because it expects its rates to change in its next base margin proceeding. 4 SoCalGas was allowed to incorporate in its testimony the factual matters set forth in the October 14, 1999 Joint Motion. 5 The Governor declared a state of emergency for various counties on February 9, 24, and 26, 1998. 6 In its application, SoCalGas represents that the Governor declared the counties of Santa Barbara, San Luis Obispo, and Ventura to be in a state of emergency on February 9, 1998, the county of Fresno on February 11, 1998, the city and county of Los Angeles on February 18, 1998, the county of Orange on February 24, 1998, and the counties of Kern, Riverside, San Bernardino, Tulare, and Ventura (stet) on February 26, 1998. SoCalGas did not, however, offer into the record evidence to support this statement. In its responses to data requests, SoCalGas also states that the Governor declared 43 counties to be in a state of emergency starting February 2, 1998 and that the President declared 27 counties disaster areas from storms starting February 2, 1998. (Exh. 10, DR 2; DR 3.) These are undisputed and readily verifiable facts. We take official notice pursuant to Rule 73 of the Commission's Rules of Practice and Procedure that the President declared 27 counties, including Ventura, San Luis Obispo, and Santa Barbara counties, where SoCalGas incurred damage, disaster areas, effective February 2, 1998, and that the Governor declared 43 counties to be in a state of emergency, including Ventura, San Luis Obispo, Santa Barbara, Los Angeles, Orange, San Bernardino, and Riverside counties, where SoCalGas incurred damage, effective February 2, 1998. 7 However, we note that the reduction in the revenue requirement SoCalGas proposes through 2002 is 8.9%. (From $5,171,478 to $4,713,616.) 8 Title 20, California Code of Regulations, Section 6.2. All references to Rules unless otherwise specified refer to the Commission's Rules of Practice and Procedure. 9 We stated that we would approve an all-party settlement if it: (1) commands the unanimous sponsorship of all active parties to the instant proceeding; (2) the sponsoring parties are fairly reflective of the affected interests; (3) no term of the settlement contravenes statutory provisions or prior Commission decisions; and (4) the settlement conveys to the Commission sufficient information to permit us to discharge our future regulatory obligations with respect to the parties and their interests. (Id. at p. 9.) Satisfying these criteria, in effect, creates a rebuttable presumption of the reasonableness of the settlement although we still need to determine that the settlement is consistent with the law and in the public interest. 10 ORA adopts the positions set forth in SoCalGas' brief with one minor exception discussed infra. 11 Further, concluding that a company's traditional method of offering the most minimal support for rate requests is "not acceptable," the Commission specifically warned parties that it would reject rate case settlements "no matter how reasonable they might otherwise appear, where they are not supported by a comprehensive initial showing. (Id.)

Previous PageTop Of PageGo To First PageNext Page