"approved (Edison's) proposed flexible outage schedule ratemaking mechanism for SONGS 2 & 3 and a per-outage O&M estimate of $52.462 million (2000 dollars, 100% share). A component of that mechanism is (Edison's) proposal to forecast outage O&M costs in annual (post-test year) filings based upon the adopted outage cost estimate and a forecast of the number of outages expected to occur in the next year." (Mimeo, p. 276.)


"in any (post-test year) filing in which it includes costs for SONGS outages that it forecasts will occur in the following year, (Edison) shall include a proposal for refunding to ratepayers the costs of any outage that was forecast and included in rates but did not occur in that year."

110 D.02-10-062, mimeo p. 61, in Rulemaking 01-10-024.