Word Document PDF Document

PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

ENERGY DIVISION RESOLUTION E-3848

RESOLUTION

Resolution E-3848. Southern California Edison Company (SCE) request for approval as reasonable Amendment No. 2 to the Power Purchase Contract between Southern California Edison Company and Ormesa Geothermal (QFID No. 3010) and Contract Termination Agreement between Ormesa Geothermal II (QFID No. 3012) and Southern California Edison. Approved.

By Advice Letter 1726-E filed on August 1, 2003.

__________________________________________________________

SUMMARY

Southern California Edison Company (SCE) requests approval for Amendment No. 2 to the Power Purchase Contract between Southern California Edison Company and Ormesa Geothermal (QFID No. 3010) and Contract Termination Agreement between Ormesa Geothermal II (QFID No. 3012) and Southern California Edison as reasonable. Specifically, SCE's Restructuring Advice Letter Filing (RALF) would consolidate power purchase agreements (PPAs) for two viable adjacent geothermal Qualifying Facilities (QF) projects (the Ormesa Geothermal Project and the Ormesa Geothermal II Project), owned by the same developer, into a single restructured contract. This resolution approves SCE's request.

SCE requests that the Commission adopt a resolution at the earliest possible time, but, by no later than November 1, 2003, so that, after taking into account the 30-day period for applications for rehearing,1 a condition of finality may be achieved by the December 1, 2003 deadline agreed upon by SCE and Ormesa. SCE requests the following findings:

BACKGROUND

The Commission sought to encourage QF contract restructuring in its Preferred Policy Decision, D.95-12-063, as modified by D.96-01-009, by proposing an incentive mechanism to encourage the restructuring of QF contracts so that total transition costs might be reduced. Specifically, shareholders would be allowed to retain 10% of the net ratepayer benefits resulting from a renegotiation.

In D.96-12-088 (the Roadmap 2 Decision), the Commission stated its interest in "establishing a generic and possibly expedited process by which we can assess the reasonableness of [QF] contract restructuring in a manner which respects the principles outlined in our Preferred Policy Decision" (D.96-12-088, p.79).

In 1998, the Commission adopted the Restructuring Advice Letter Filing (RALF)2 process in D.98-12-066:

The Commission adopted the RALF process with modifications that were not included in Attachment B to D.98-12-066 but were instead set forth in the decision. The Commission included the following provisions in the adopted RALF process:

As described in SCE AL 1726-E, the Ormesa Geothermal and Ormesa Geothermal II Projects are geothermal QFs located in Imperial County, California. SCE's power purchases from Ormesa Geothermal and Ormesa Geothermal II are currently made in accordance with the terms and conditions of the Ormesa Geothermal and Ormesa II (QFID 3012) PPAs, which were entered into pursuant to the Public Utility Regulatory Policies Act of 1978 (PURPA), FERC's regulations implementing PURPA (18 C.F.R. § 292.101 et seq. (2002)), and decisions and orders of the Commission implementing PURPA in California. These PPAs account for approximately 65.3 MW of installed electric geothermal generating capacity. SCE states that the PPAs are based on Commission-approved standard offer forms and all provide for 30-year terms. The Ormesa Geothermal agreement was entered into on July 18, 1984 and the Ormesa Geothermal II agreement (QFID 3012) on June 13, 1984. These agreements will expire in 2017 and 2018, respectively. Energy deliveries by the Projects during 2002 collectively totaled approximately 374,085,000 KWh.

NOTICE

Notice of AL 1726-E was made by publication in the Commission's Daily Calendar. Southern California Edison states that a copy of the Advice Letter was mailed and distributed in accordance with Section III-G of General Order 96-A.

PROTESTS

Advice Letter AL 1726-E was filed on August 1, 2003. The protest period ended August 21, 2003. No protests were filed.

DISCUSSION

Energy Division has reviewed both the public and confidential versions of SCE AL 1727-E. SCE AL 1727-E included information required in Section 3 of RALF, and has complied with the other RALF filing requirements. These requirements are reproduced here as Attachment 1 to E-3848. Attachment 1 is modified from the original Attachment B to D.98-12-066 to reflect determinations made in D.98-12-066.

On July 14, 2003, ORA issued a letter in support of the contract restructuring, now proposed by SCE in AL 1726-E. The RALF procedure requires a statement of support or neutrality from ORA be attached to any restructuring Advice Letter filing.

SCE does not seek any shareholder incentive as a result of this contract restructuring.

With regard to historical performance, the projects have not experienced any operational issues such as probation or deration. From 1999 through 2002, overall production from the projects decreased slightly, but increased after ORMAT's3 reacquisition of the projects, and the subsequent capital improvement program. As a geothermal QF, Ormesa is not subject to efficiency monitoring standards.

Section 3f. of the RALF procedure requires disclosure of any significant, pending legal or regulatory disputes between the utility and the QFs. Upon such request, SCE informed the Energy Division that there are no disputes of any nature between Edison and the projects.

With regard to future viability, Ormesa plans to repower some of the units with newer machinery of the same technology, and requested that Edison concur that the equipment change-out constituted a repower and not a change of prime mover. After an engineering review of Ormesa's plans, Edison ultimately concurred that the equipment change constituted a repower and would not violate the contract. During the negotiations surrounding contract consolidation, Ormesa engaged in their capital improvement program, including the replacement of the project's cooling towers. Ormesa demonstrated to Edison's satisfaction through its plans and actions that Ormesa was determined to maintain the viability of the projects either separately or as consolidated.

The primary ratepayer benefit that would result from the proposed contract restructuring is a one-time, lump sum payment by Ormesa, LLC to SCE. This payment could be received by SCE as soon as five days after Commission approval of SCE AL 1727-E. The payment amount is fixed and does not represent forecasted savings, nor is it tied to an energy index or other variable rate. Payment would be credited to SCE's 0103 Account for Purchased Power on behalf of QFID 3012, resulting in the same one-time, lump sum reduction amount eligible for inclusion in SCE's Energy Resource Recovery Account (ERRA).

Due to the relatively immediate ratepayer benefit that would accrue, the Commission should approve, as reasonable, Amendment No. 2 to the Power
Purchase Contract between Southern California Edison Company and Ormesa Geothermal (QFID No. 3010) and the Contract Termination Agreement between Ormesa Geothermal II (QFID No. 3012) and Southern California Edison. Accordingly, SCE should be allowed to recover all payments made pursuant to Amendment No. 2 and the Termination Agreement in SCE's retail rates, subject to review by the Commission with respect to the reasonableness of SCE's administration of the QFID 3010 PPA, as amended by Amendment
No. 2.

COMMENTS

PU Code section 311(g)(1) provides that this resolution must be served on all parties and subject to at least 30 days public review and comment prior to a vote of the Commission. However, since this is an uncontested matter in which the resolution grants the relief requested. Pursuant to PU Code 311(g)(2), the otherwise applicable 30-day period for public review and comment is being reduced.

FINDINGS

1. The Commission adopted the Restructuring Advice Letter Filing (RALF) process in D.98-12-066. On August 1, 2003, SCE filed Advice Letter 1726-E pursuant to the RALF process for approval to consolidate two QF contracts.

2. AL 1726-E was not protested.

3. On July 14, 2003, ORA issued a letter in support of the contract restructuring, now proposed by SCE in AL 1726-E.

4. SCE complied with RALF filing requirements.

5. SCE does not seek any shareholder incentive as a result of this contract restructuring.

6. The Ormesa QFs have not experienced any operational issues such as probation or deration, and project viability is expected to be enhanced through capital improvements.

7. There are no pending legal or regulatory disputes between SCE and the Ormesa QFs.

8. The primary ratepayer benefit that would result from the proposed contract restructuring is a one-time, lump sum payment by Ormesa, LLC to SCE. This payment would be credited to SCE's 0103 Account for Purchased Power on behalf of QFID 3012, resulting in the same one-time, lump sum reduction amount eligible for inclusion in SCE's Energy Resource Recovery Account (ERRA).

9. We should approve, as reasonable, Amendment No. 2 to the Power Purchase Contract between Southern California Edison Company and Ormesa Geothermal (QFID No. 3010) and the Contract Termination Agreement between Ormesa Geothermal II (QFID No. 3012) and Southern California Edison.

10. SCE should be allowed to recover all payments made pursuant to Amendment No. 2 and the Termination Agreement in SCE's retail rates, subject to review by the Commission with respect to the reasonableness
of SCE's administration of the QFID 3010 PPA, as amended by
Amendment No. 2.

THEREFORE IT IS ORDERED THAT:

1. Southern California Edison Company's request for approval of Amendment No. 2 to the Power Purchase Contract between Southern California Edison Company and Ormesa Geothermal (QFID No. 3010) and the Contract Termination Agreement between Ormesa Geothermal II (QFID No. 3012) and Southern California Edison, as requested in Advice Letter 1726-E, is granted.

2. SCE may recover all payments made pursuant to Amendment No. 2 and the Termination Agreement in SCE's retail rates, subject to review by the Commission with respect to the reasonableness of SCE's administration of the QFID 3010 PPA, as amended by Amendment No. 2.

This Resolution is effective today.

I certify that the foregoing resolution was duly introduced, passed and adopted at a conference of the Public Utilities Commission of the State of California held on October 16, 2003; the following Commissioners voting favorably thereon:

            _________________

Attachment 1 to Resolution E-3848

Formerly ATTACHMENT B to D.98-12-066

[Modified Here in Attachment 1 to Resolution E-3848
To Reflect Modifications Set Forth In D.98-12-066]

Revised Exhibit A

RESTRUCTURING ADVICE LETTER FILING ("RALF") PROCEDURE FOR REVIEW OF QF CONTRACT RESTRUCTURINGS

1. The utility will submit a restructuring advice letter to the Commission's Energy Division which will contain the essential information necessary to establish the reasonableness of the proposed voluntarily negotiated QF restructuring. Each such filing, and all protests, responses and replies concerning the filing, shall indicate a postal address and (where appropriate) a FAX number or e-mail address at which the advice letter filer, protestant or respondent, agrees to receive subsequent documents and notices relevant to the advice letter. Each such filing will be reported in the Daily Calendar.

2. Service of the restructuring advice letter shall be as follows:

On or before the date a restructuring advice letter is submitted for filing, and unless otherwise directed by Commission order, the utility shall serve the restructuring advice letter (1) on the Consumer Services Division and the Office of Ratepayer Advocates (service on these parties may be made by Internet); and (2) on the utility's restructuring advice letter service list and any other third parties as specified by the Energy Division, other Commission order, or statute.

The utility's restructuring advice letter service list shall include the postal and e-mail address, as appropriate, of persons on the list. The utility shall include on the requested list any person that requests such inclusion and may periodically confirm the desire of any currently listed person to remain on the list.

After the filing of a restructuring advice letter, and pending its disposition, the utility shall promptly provide a copy of the advice letter to anyone so requesting. Such provision shall be without charge to anyone who is a current customer for utility services from the utility, or to anyone receiving the advice letter by Internet.

3. The restructuring advice letter shall contain the following categories of information, including all relevant work papers and other relevant supporting documents:

a. Identification of the QF, location of the QF's generating facility, brief description of the generating facility size, type of technology and other pertinent or unique characteristics.

b. Ownership of the QF project and related companies, including affiliate relationships of the parties involved in the transaction, if any.

c. A detailed description of the historical operational performance of the project, including historical production and compliance with performance and efficiency monitoring standards.

d. A summary of the proposed contract restructuring.

e. A summary of the ratepayer benefits.

f. A description of any significant, pending legal or regulatory disputes between the Utility and the QF, and their resolution or status.

g. An assessment of the QF's projected economic and operational viability under the existing contract.

h. A detailed description of ratepayer benefits, shareholder incentive, and sensitivity analyses.

i. A copy of the QF's existing contract, including any amendments.

j. A copy of the executed or unexecuted restructured agreement for which approval is sought and copies of all related agreements between the QF and the Utility.

4. The publicly available version of the restructuring advice letter may be redacted to delete the following types of confidential information, which redaction would be approved in advance by the Commission in its orders authorizing the use of the advice letter process:

a. The schedule of any restructuring payments to be made to the QF, including the total amount thereof.

b. The Utility's non-public projection of replacement energy and capacity costs.

c. The Utility's projection of future production by and payments to the QF under the existing contract.

d. Non-public financial and operating data provided on a confidential basis by the QF to the Utility.

e. The Utility's assessment of the QF's financial and operating viability under the existing contract.

f. The Utility's analysis of ratepayer savings under expected, best case and worst case scenarios (except that the projected range of savings under each scenario shall not itself be deemed confidential).

g. Portions of restructuring agreements that are deemed to be confidential by the parties and which, if made public, would place the Utility and/or the QF at a competitive disadvantage.

h. Other information which constitutes a protectable trade secret of a party or which, if publicly disclosed, would place the Utility or the QF at a competitive disadvantage. [Deleted per D.98-12-066, p.18]

5. The restructuring advice letter shall only take effect upon Commission approval.

6. Any person may protest or respond to a restructuring advice letter as follows:

Within 20 days after the date that the advice letter is reported in the Daily Calendar, the protest or response shall be submitted to the Energy Division and served on the same day on the utility filing the restructuring advice letter. After filing a protest, and pending disposition of the restructuring advice letter, the protestant shall promptly provide a copy of the protest to anyone so requesting.

A restructuring advice letter may be protested on one or more of the following grounds:

a. The utility did not properly serve or give notice of the restructuring advice letter;

b. The relief requested in the restructuring advice letter would violate statute or Commission order;

c. The restructuring advice letter contains material errors, or does not follow the Commission's approved methodology, if any.

In addition, a restructuring advice letter may be protested on the grounds that the proposed restructuring is unjust, unreasonable, or discriminatory, provided, however, that a restructuring advice letter is not subject to protest on these grounds where such protest would require relitigating a prior order of the Commission.

The utility filing the restructuring advice letter shall reply to each protest and may reply to any response. Any such reply shall be submitted to the Energy Division not later than five business days after the last day to serve a protest or response, and shall be served on the same day on the person making the protest or response. If there are multiple protests or responses to a restructuring advice letter, the utility's reply may be to all such protests and responses.

The Energy Division may consider a late-filed protest or response. If the Energy Division considers a late-filed protest or response, it shall notify the utility filing the restructuring advice letter, and the utility shall have five business days from the date of issuance of the notice within which to reply to the late-filed protest or response.

7. The utility filing the restructuring advice letter may make minor revisions or corrections to the filing at any time before the effective date by filing and serving a supplement or substitute sheet. The utility shall withdraw the advice letter without prejudice in order to make major revisions. Supplements, substitute sheets, and withdrawals shall be filed and served in the same manner and on the same persons as was the original advice letter.

Minor revisions do not automatically extend the protest period. The Energy Division on its own motion or at the request of any person, may issue a notice extending the protest period. Any protest during the extended period shall be confined to the substance of the revision.

8. A supplement to a restructuring advice letter may be used to make minor revisions. The following revisions are examples of what commonly, but not necessarily, qualify as minor: a modification in response to a protest; a language clarification; or a later effective date. The supplement shall bear the same identifying number as the original advice letter but shall have a letter suffix "A" for the first supplement, "B" for the second supplement, etc.

9. Upon completion of the protest, response and reply period, the Energy Division will have 40 days within which to review the proposed restructuring to determine whether the information provided under paragraph 2 above and in response to any protest establishes that the proposed restructuring is reasonable under the Commission's standards and should be approved.

When such review has been completed, and within such 40-day period, the Energy Division will prepare and submit to the Commission for consideration at the Commission's next public meeting which is at least 10 days thereafter a proposed resolution either approving or rejecting the restructuring advice letter. (To facilitate this process, the utility may submit a proposed form of resolution as part of the advice letter package.) A proposed resolution approving the restructuring advice letter shall make at least the following finding:

The Commission may then adopt the proposed resolution or modify it in whole or in part. After the Commission has acted on the resolution, its action will be reported in the Daily Calendar and the resolution will be served on the utility filing the restructuring advice letter, the affected QF and on any person filing a protest or response to the restructuring advice letter.

10. Pursuant to Public Utilities Code Sections 1731 to 1736 and Rules 85 to 86.7 of the Commission's Rules of Practice and Procedure, the utility filing the restructuring advice letter, the affected QF, or any person filing a protest to the restructuring advice letter may apply for rehearing of a resolution approving or rejecting the restructuring advice letter pursuant to paragraph 9 above. The application for rehearing shall set forth specifically the grounds on which the applicant considers the resolution to be unlawful. Other than the affected QF, a person filing a response does not have standing to apply for rehearing.

The application for rehearing shall be submitted to the Commission's Docket Office, which will assign a docket number to the application, and with the Energy Division. If the applicant is the utility filing the restructuring advice letter, it shall serve all persons filing protests or responses to the restructuring advice letter. If the applicant is the affected QF or a person filing a protest, the applicant shall serve the utility and all other persons filing protests or responses to the restructuring advice letter.

11. If the Commission's final resolution does not approve the proposed restructuring in its entirety, then the terms of the agreement between the utility and the QF will determine whether or not the restructuring effort will terminate or whether the proposed restructuring will be resubmitted for consideration through a formal application process. Also, subject to its agreement with the QF, the utility will have the right to withdraw a restructuring advice letter without prejudice at any time prior to Commission action on the draft resolution prepared by the Energy Division, or to pursue a formal application process in lieu of the advice letter procedure.

12. Nothing in the restructuring advice letter filing procedure shall preclude the utility from electing not to use the advice letter process.

STATE OF CALIFORNIA GRAY DAVIS, Governor

PUBLIC UTILITIES COMMISSION

505 VAN NESS AVENUE

SAN FRANCISCO, CA 94102-3298

September 22, 2003 Commission Meeting Date: October 2, 2003 ID#2769

TO: PARTIES IN R.99-11-022 and SOUTHERN CALIFORNIA EDISON COMPANY ADVICE LETTER 1726-E, QUALIFYING FACILITY (QF) CONTRACT AMENDMENT BETWEEN THE UTILITY AND ORMESA PURSUANT TO THE RESTRUCTURING ADVICE LETTER FILING (RALF) PROCEDURE.

Enclosed is draft Resolution E-3848 of the Energy Division. It addresses Southern California Edison Company Advice Letter 1726-E for approval as reasonable Amendment No. 2 to the Power Purchase Contract between Southern California Edison Company and Ormesa Geothermal (QFID No. 3010) and Contract Termination Agreement between Ormesa Geothermal II (QFID No. 3012) and Southern California Edison.

The draft Resolution will be on the agenda at the October 2, 2003 Commission meeting. Since this is an uncontested matter in which the resolution grants the relief requested, pursuant to PU Code 311(g)(2), the otherwise applicable 30-day period for public review and comment is being reduced. The Commission may then vote on this draft Resolution or it may postpone a vote until later.

When the Commission votes on a draft Resolution, it may adopt all or part of it as written, amend, modify or set it aside and prepare a different Resolution. Only when the Commission acts does the Resolution become binding on the parties.

Parties may submit comments on the draft Resolution.

An original and two copies of the comments, with a certificate of service, should be submitted to:

Jerry Royer

Energy Division

California Public Utilities Commission

505 Van Ness Avenue

San Francisco, CA 94102

fax: 415-703-2200

A copy of the comments should also be submitted to:

Wade McCartney

Energy Division

California Public Utilities Commission

770 L Street, Suite 1050

Sacramento, CA 95814

email: wsm@cpuc.ca.gov

Any comments on the draft Resolution must be received by the Energy Division by close of business on Friday September 26, 2003. Those submitting comments must serve a copy of their comments on (1) the entire service list attached to the draft Resolution, including the R.99-11-022 service list, (2) all Commissioners, and (3) the Director of the Energy Division, on the same date that the comments are submitted to the Energy Division.

Comments shall be limited to five pages in length plus a subject index listing the recommended changes to the draft Resolution. Comments shall focus on factual, legal or technical errors in the proposed draft Resolution. Comments that merely reargue positions taken in the advice letter or protests will be accorded no weight and are not to be submitted. There will be no reply comments on the draft resolution.

Late submitted comments will not be considered.

Don Lafrenz

Energy Division

Enclosure

Service List - Parties in SCE AL 1726-E and R.99-11-022

    ROGER BERLINER

    MANATT, PHELPS & PHILLIPS, LLP

    County of Las Angeles

    1501 M STREET, N.W., SUITE 700

    WASHINGTON, DC 20005

 

    JONATHAN M. WEISGALL

    V.P. LEGISLATIVE & REGULATORY AFFAIRS

    CALENERGY COMPANY, INC.

    1200 NEW HAMPSHIRE AVE., NW, SUITE 300

    WASHINGTON, DC 20036

    JAMES ROSS

    RCS CONSULTING, INC.

    MIDSET COGENERATION COMPANY

    500 CHESTERFIELD CENTER, SUITE 320

    CHESTERFIELD, MO 63017

 

    DOUGLAS L. ANDERSON

    VICE PRESIDENT AND GENERAL COUNSEL

    CE GENERATION, LLC

    302 SOUTH 36TH STREET, SUITE 400

    OMAHA, NE 68131

    ANDREW N. CHAU

    TRACTEBEL POWER, INC.

    1177 WEST LOOP SOUTH, SUITE 900

    HOUSTON, TX 77027

 

    DAVID M. NORRIS

    ASSOCIATE GENERAL COUNSEL

    SIERRA PACIFIC POWER COMPANY

    6100 NEIL ROAD, PO BOX 10100

    RENO, NV 89520

    HOWARD CHOY

    ENERGY MANAGEMENT DIVISION MANAGER

    COUNTY OF LOS ANGELES

    INTERNAL SERVICES DEPARTMENT

    1100 NORTHEASTERN AVENUE

    LOS ANGELES, CA 90063

 

    KEVIN MC SPADDEN

    ATTORNEY AT LAW

    MILBANK, TWEED, HADLEY & MC CLOY

    601 S. FIGUEROA STREET, 30TH FLOOR

    LOS ANGELES, CA 90068

    DAN WOODS

    WHITE & CASE LLP

    Smurfit Stone Container Corporation,/Delta Power Co./Willamette Industries, Inc./E.F.Oxnard, Inc.

    633 WEST FIFTH STREET, SUITE 1900

    LOS ANGELES, CA 90071-2087

 

    TANDY MCMANNES

    KJC CONSULTING COMPANY

    KRAMER JUNCTION OPERATING COMPANY

    2938 CROWNVIEW DRIVE

    RANCHO PALOS VERDES, CA 90275

    SUSAN ROSSI

    ATTORNEY AT LAW

    CALIFORNIA POWER EXCHANGE CORPORATION

    70 SOUTH LAKE AVE 910

    PASADENA, CA 91101-4960

 

    ERIC J. ISKEN

    ATTORNEY AT LAW

    SOUTHERN CALIFORNIA EDISON COMPANY

    2244 WALNUT GROVE AVENUE

    ROSEMEAD, CA 91770

    JAMES B. WOODRUFF

    SOUTHERN CALIFORNIA EDISON COMPANY

    2244 WALNUT GROVE AVENUE, SUITE 342, GO1

    ROSEMEAD, CA 91770

 

    THEODORE ROBERTS

    ATTORNEY AT LAW

    SEMPRA ENERGY

    SAN DIEGO GAS AND ELECTRIC COMPANY

    101 ASH STREET, HQ 12B

    SAN DIEGO, CA 92101-3017

    EDWARD E. MADDOX

    BUSINESS DEVELOPMENT MANAGER

    SEAWEST WINDPOWER, INC.

    1455 FRAZEE ROAD, SUITE 900

    SAN DIEGO, CA 92108-4310

 

    NORMAN J. FURUTA

    ATTORNEY AT LAW

    DEPARTMENT OF THE NAVY

    2001 JUNIPERO SERRA BLVD., SUITE 600

    DALY CITY, CA 94014-3890

    DIANE I. FELLMAN

    ATTORNEY AT LAW

    LAW OFFICES OF DIANE I. FELLMAN

    234 VAN NESS AVENUE

    SAN FRANCISCO, CA 94102

 

    ROBERT FINKELSTEIN

    ATTORNEY AT LAW

    THE UTILITY REFORM NETOWRK (TURN)

    711 VAN NESS AVE., SUITE 350

    SAN FRANCISCO, CA 94102

    John M Chamberlain

    CALIF PUBLIC UTILITIES COMMISSION

    CPUC OFFICE OF RATEPAYER ADVOCATES

    LEGAL DIVISION

    505 VAN NESS AVENUE ROOM 4107

    SAN FRANCISCO, CA 94102

 

    EVELYN KAHL

    ATTORNEY AT LAW

    ALCANTAR & KAHL, LLP

    ENERGY PRODUCERS AND USERS COALITION (EPUC)

    120 MONTGOMERY STREET, SUITE 2200

    SAN FRANCISCO, CA 94104

    LINDA SHERIF

    ATTORNEY AT LAW

    ALCANTAR & KAHL LLP

    COGENERATION ASSOCIATION OF CALIFORNIA (CAC) and EPUC

    120 MONTGOMERY STREET, STE 2200

    SAN FRANCISCO, CA 94104

 

    ANN C. SELTING

    GRUENEICH RESOURCE ADVOCATES

    Sonoma County Water Agency

    582 MARKET STREET, SUITE 1020

    SAN FRANCISCO, CA 94104-5311

    DIAN M. GRUENEICH

    ATTORNEY AT LAW

    GRUENEICH RESOURCE ADVOCATES

    582 MARKET STREET, SUITE 1020

    SAN FRANCISCO, CA 94104-5311

 

    ALICE REID

    PACIFIC GAS AND ELECTRIC COMPANY

    77 BEALE STREET

    SAN FRANCISCO, CA 94105

    CHARLES R. MIDDLEKAUF

    PACIFIC GAS AND ELECTRIC COMPANY

    LAW DEPARTMENT

    77 BEALE STREET, B30A

    SAN FRANCISCO, CA 94105

 

    BRIAN CRAGG. ATTORNEY AT LAW

    GOODIN MACBRIDE SQUERI RITCHIE & DAY LLP

    CAITHNESS ENERGY/LUZ SOLAR PARTNERS LTD.,VIII&IX

    505 SANSOME STREET, SUITE 900

    SAN FRANCISCO, CA 94111

    JAMES D. SQUERI, ATTORNEY AT LAW

    GOODIN MACBRIDE SQUERI RITCHIE & DAY LLP

    MONSANTO CO.

    505 SANSOME STREET, SUITE 900

    SAN FRANCISCO, CA 94111

 

    JERRY R. BLOOM, ATTORNEY AT LAW

    WHITE & CASE LLP

    CALIFORNIA COGENERATION COUNCIL (CCC)

    THREE EMBARCADERO CENTER, SUITE 2210

    SAN FRANCISCO, CA 94111

    JOSEPH M. KARP, ATTORNEY AT LAW

    WHITE & CASE LLP

    Smurfit Stone COntainer Corporation, f.k.a.Jefferson Smurfit Corporation(U.S.)

    THREE EMBARCADERO CENTER, SUITE 2210

    SAN FRANCISCO, CA 94111

 

    LINDSEY HOW-DOWNING, ATTORNEY AT LAW

    DAVIS WRIGHT TREMAINE LLP

    CALPINE CORPORATION

    ONE EMBARCADERO CENTER, SUITE 600

    SAN FRANCISCO, CA 94111

    JEFFREY GRAY

    DAVIS WRIGHT TREMAINE

    Dynamis Incorporated

    ONE EMBARCADERO CENTER STE. 600

    SAN FRANCISCO, CA 94111-3611

 

    SARA STECK MYERS, ATTORNEY AT LAW

    ENRON WIND CORP., CENETER FOR ENERGY EFFICIENCY AND RENEWABLE TECHNOLOGIES (CEERT)

    122 - 28TH AVENUE

    SAN FRANCISCO, CA 94121

    SETH HILTON, ATTORNEY AT LAW

    MORRISON & FOERSTER LLP

    EL PASO MERCHANT ENERGY, L.P.

    101 YGNACIO VALLEY ROAD, SUITE 450

    WALNUT CREEK, CA 94596-7032

 

    NANCY RADER, EXECUTIVE DIRECTOR

    CALIFORNIA WIND ENERGY ASSOCIATION

    1198 KEITH AVENUE

    BERKELEY, CA 94708

    R. THOMAS BEACH

    PRINCIPAL CONSULTANT

    CROSSBORDER ENERGY

    WATSON COGENERATION COMPANY

    2560 NINTH STREET, SUITE 316

    BERKELEY, CA 94710

 

    PATRICK MCDONNELL

    AGLAND ENERGY

    TXU ENERGY SERVICES

    2000 NICASIO VALLEY

    NICASIO, CA 94946

    JIM CROSSEN

    AUTOMATED POWER EXCHANGE, INC.

    TECHMART

    5201 GREAT AMERICA PARKWAY, SUITE 552

    SANTA CLARA, CA 95054

 

    STEVE FELTE, GENERAL MANAGER

    TRI-DAM PROJECT & POWER AUTHORITY

    PO BOX 1158

    PINECREST, CA 95364-0158

    ROBERT BEACH

    SONOMA COUNTY WATER AGENCY

    739 MIRAMAR STREET

    WINDSOR, CA 95492

 

    JOHN J. PREVOST

    PACIFIC LUMBER COMPANY

    125 MAIN STREET

    SCOTIA, CA 95565

    DALE W. MAHON

    CENTRAL HYDROELECTRIC CORPORATION

    9951 GRANT LINE ROAD

    ELK GROVE, CA 95624-1411

 

    MATTHEW V. BRADY, SPECIAL COUNSEL

    MATTHEW V. BRADY & ASSOCIATES

    Central Hydroelectric Company

    2339 GOLD MEADOW WAY, SUITE 230

    GOLD RIVER, CA 95670

    DOUGLAS K. KERNER

    ATTORNEY AT LAW

    ELLISON, SCHNEIDER & HARRIS

    INDEPENDENT ENERGY PRODUCERS ASSOCIATION (IEP)

    2015 H STREET

    SACRAMENTO, CA 95814

 

    ROBERT ELLERY

    SIERRA PACIFIC INDUSTRIES

    19794 RIVERSIDE AVENUE

    ANDERSON, CA 96007

    MICHAEL ALCANTAR, ATTORNEY AT LAW

    ALCANTAR & KAHL LLP

    COGENERATION ASSOCIATION OF CALIFORNIA

    1300 SW FIFTH AVENUE, SUITE 1750

    PORTLAND, OR 97201

 

    DON SCHOENBECK

    RCS, INC

    COALINGA COGENERATION COMPANY

    900 WASHINGTON STREET, SUITE 780

    VANCOUVER, WA 98660

    C. FAIRLEY SPILLMAN

    AKIN, GUMP, STRAUSS, HAUER & FELD, LLP

    1333 NEW HAMPSHIRE AVENUE, NW

    WASHINGTON, DC 20036

 

    KAY DAVOODI

    NAVY RATE INTERVENTION OFFICE

    WASHINGTON NAVY YARD

    1314 HARWOOD STREET SE

    WASHINGTON NAVY YARD, DC 20374-5018

    MAURICE BRUBAKER

    BRUBAKER & ASSOCIATES

    PO BOX 412000

    ST. LOUIS, MO 63141

 

    JANET DOYLE

    KRAMER JUNCTION COMPANY

    1636 AJAX LANE

    EVERGREEN, CO 80439

    CLIFF ROCHLIN

    SOUTHERN CALIFORNIA GAS COMPANY

    SEMPRA ENERGY

    555 W. FIFTH STREET, ML 22A1

    LOS ANGELES, CA 90013

 

    ED J. WHELESS

    DIVISION ENGINEER

    COUNTY SANITATION DIST. OF L.A. COUNTY

    SOLID WASTER MANAGEMENT DEPT

    PO BOX 4998

    WHITTIER, CA 90607-4998

    JOHN COSTANZO

    KRAMER JUNCTION COMPANY

    1778 FISK COURT

    THOUSAND OAKS, CA 91362

 

    DANIEL W. DOUGLASS

    ATTORNEY AT LAW

    LAW OFFICES OF DANIEL W. DOUGLASS

    6303 OWENSMOUTH AVENUE, TENTH FLOOR

    WOODLAND HILLS, CA 91367-2262

    JACK MCNAMARA

    GEO-ENERGY PARTNERS-1983 LTD.

    PO BOX 531

    AGOURA HILLS, CA 91376

 

    CASE ADMINISTRATION

    SOUTHERN CALIFORNIA EDISON COMPANY

    2244 WALNUT GROVE AVENUE, R00M 370

    ROSEMEAD, CA 91770

    JOHN W. LESLIE

    ATTORNEY AT LAW

    LUCE, FORWARD, HAMILTON & SCRIPPS, LLP

    Coral Energy Resourced, LLC/Engage Energy US,L.P.

    600 WEST BROADWAY, SUITE 2600

    SAN DIEGO, CA 92101

 

    ANDY FRIEDL

    CP KELCO

    2025 E. HARBOR DRIVE

    SAN DIEGO, CA 92113

    CHRIS SMITH

    CORAL ENERGY RESOURCES, LLC

    4320 LA JOLLA VILLAGE DRIVE

    SAN DIEGO, CA 92122

 

    ROBERT TURNER

    COASTAL MERCHANT ENERGY LP

    PO BOX 17097

    SAN DIEGO, CA 92177

    MITSUBISHI POWER SYSTEMS, INC.

    100 BAYVIEW CIRCLE, SUITE 4000

    NEWPORT BEACH, CA 92660

 

    ERIC WILLS, PRESIDENT

    SUNRAY ENERGY, INC.

    20668 PASEO DE LA CUMBRE

    YORBA LINDA, CA 92687

    JAMES L. MCARTHUR

    DAI OILDALE, INC

    3300 MANOR DRIVE

    BAKERSFIELD, CA 93308

 

    EDWARD G. CAZALET, CHAIRMAN

    AUTOMATED POWER EXCHANGE

    5201 GREAT AMERICA PARKWAY

    SANTA CLARA, CA 94054

    JUDY PECK

    SEMPRA ENERGY UTILITIES

    601 VAN NESS AVENUE, SUITE 2060

    SAN FRANCISCO, CA 94102

 

    KEENAN O'BRIEN

    PACIFIC GAS AND ELECTRIC COMPANY

    245 MARKET ST., MAIL CODE: N12E

    SAN FRANCISCO, CA 94102

    WILLIAM BLATTNER

    ADMINSTRATOR STATE REG. RELATIONS

    SEMPRA ENERGY

    601 VAN NESS AVENUE, SUITE 2060

    SAN FRANCISCO, CA 94102

 

    JACK MCGOWAN

    GRUENEICH RESOURCE ADVOCATES

    582 MARKET STREET, SUITE 1020

    SAN FRANCISCO, CA 94104

    JOHN PAPPAS

    UTILITY ELECTRIC PORTFOLIO MANAGEMENT

    PACIFIC GAS AND ELECTRIC COMPANY

    77 BEALE STREET, N12E

    SAN FRANCISCO, CA 94105

 

    ROBERT T. BOYD

    ENRON WIND CORP.

    444 SOUTH FLOWER STREET, SUITE 4545

    LOS ANGELES, CA 94105

    TONY WAKIM

    KENNEDY/JENKS CONSULTANTS

    622 FOLSOM STREET

    SAN FRANCISCO, CA 94107

 

    ARTHUR V. O'DONNELL

    CALIFORNIA ENERGY MARKETS

    9 ROSCOE STREET

    SAN FRANCISCO, CA 94110-5921

    MARGERY NEIS

    FTI CONSULTING

    353 SACRAMENTO STREET

    SAN FRANCISCO, CA 94111

 

    EDWARD W. O'NEILL, ATTORNEY AT LAW

    DAVIS WRIGHT TREMAINE LLP

    ONE EMBARCADERO CENTER, SUITE 600

    SAN FRANCISCO, CA 94111-3611

    SHIRLEY L. WONG

    PACIFIC GAS AND ELECTRIC COMPANY

    PO BOX 770000, RM. 987 - B9A

    SAN FRANCISCO, CA 94177

 

    ALEXANDRE MAKLER, ATTORNEY AT LAW

    CALPINE CORPORATION

    PO BOX 11749

    PLEASANTON, CA 94588-1749

    ROBERT SZYMANSKI

    POWERWORKS, INC.

    781 THOMAS LANE

    WALNUT CREEK, CA 94596

 

    STEVE HUHMAN

    SOUTHERN COMPANY ENERGY MARKETING

    1350 TREAT BLVD. SUITE 500

    WALNUT CREEK, CA 94597

    VIDA BENAVIDES

    EXECUTIVE DIRECTOR

    C/O NAATA

    4096 PIEDMONT AVE, 312

    OAKLAND, CA 94611

 

    ROBERT B. WEISENMILLER, PH.D.

    MRW & ASSOCIATES, INC.

    VARIOUS INTERVENORS

    1999 HARRISON STREET, SUITE 1440

    OAKLAND, CA 94612-3517

    REED V. SCHMIDT

    BARTLE WELLS ASSOCIATES

    1889 ALCATRAZ AVENUE

    BERKELEY, CA 94703

 

    RICHARD MC CANN

    M.CUBED

    2655 PORTAGE BAY, SUITE 3

    DAVIS, CA 95616

    SCOTT BLAISING

    ATTORNEY AT LAW

    BRAUN & ASSOCIATES, P.C.

    8980 MOONEY ROAD

    ELK GROVE, CA 95624

 

    TONY WETZEL

    THERMO ECOTEK CORPORATION

    631 HANCOCK DRIVE

    FOLSOM, CA 95630

    ANDREW BROWN

    ELLISON & SCHNEIDER, LLP

    2015 H STREET

    SACRAMENTO, CA 95814

 

    EDWARD J. TIEDEMANN, ATTORNEY AT LAW

    KRONICK, MOSKOVITZ, TIEDEMANN & GIRARD

    PLACER COUNTY WATER AGENCY

    400 CAPITOL MALL, 27TH FLOOR

    SACRAMENTO, CA 95814

    STEVE PONDER

    FPL ENERGY, INC., LLC

    980 NINTH STREET, 16TH FLOOR

    SACRAMENTO, CA 95814

 

    DAVID R. BRANCHCOMB

    HENWOOD ENERGY SERVICES

    INDEPENDENT ENERGY PRODUCERS ASSOCIATION (IEP)

    SUITE 300 NORTH

    2710 GATEWAY OAKS DRIVE

    SACRAMENTO, CA 95833

    DOUGLAS E. DAVIE

    PRINCIPAL CONSULTANT

    HENWOOD ENERGY SERVICES, INC.

    2379 GATEWAY OAKS DRIVE, SUITE 100

    SACRAMENTO, CA 95833

 

    Maria E. Stevens

    CALIF PUBLIC UTILITIES COMMISSION

    EXECUTIVE DIVISION

    320 WEST 4TH STREET SUITE 500

    LOS ANGELES, CA 90013

    Amy C Yip-Kikugawa

    CALIF PUBLIC UTILITIES COMMISSION

    LEGAL DIVISION

    505 VAN NESS AVENUE ROOM 5135

    SAN FRANCISCO, CA 94102

 

    Bruce DeBerry

    CALIF PUBLIC UTILITIES COMMISSION

    DIVISION OF ADMINISTRATIVE LAW JUDGES

    505 VAN NESS AVENUE ROOM 5043

    SAN FRANCISCO, CA 94102

    Darwin Farrar

    CALIF PUBLIC UTILITIES COMMISSION

    LEGAL DIVISION

    505 VAN NESS AVENUE ROOM 4107

    SAN FRANCISCO, CA 94102

 

    Edwin Quan

    CALIF PUBLIC UTILITIES COMMISSION

    CPUC - ENERGY DIVISION

    INFORMATION & MANAGEMENT SERVICES DIVISION

    505 VAN NESS AVENUE ROOM 3016

    SAN FRANCISCO, CA 94102

    Gregory A. Wilson

    CALIF PUBLIC UTILITIES COMMISSION

    CPUC - ENERGY DIVISION

    ELECTRIC INDUSTRY & FINANCE

    505 VAN NESS AVENUE AREA 4-A

    SAN FRANCISCO, CA 94102

 

    Pearlie Sabino

    CALIF PUBLIC UTILITIES COMMISSION

    OFFICE OF RATEPAYER ADVOCATES (ORA)

    ELECTRICITY RESOURCES AND PRICING BRANCH

    505 VAN NESS AVENUE ROOM 4209

    SAN FRANCISCO, CA 94102

    BILL JULIAN

    ATTORNEY AT LAW

    UTILITIES & COMMERCE

    STATE CAPITOL, ROOM 2117

    SACRAMENTO, CA 95814

 

    Wade McCartney

    CALIF PUBLIC UTILITIES COMMISSION

    NATURAL GAS, ENERGY EFFICIENCY AND RESOURCE ADVISORY

    770 L STREET, SUITE 1050

    SACRAMENTO, CA 95814

    JAMES HOFFSIS

    CALIFORNIA ENERGY COMMISSION

    1516 NINTH STREET MS-45

    SACRAMENTO, CA 95814-5504

   

   
     
     
     
     
     
     
     

1 Filing of a timely application for rehearing is a jurisdictional requirement for further review of Commission decision in the courts. Pub. Util. Code Section 1731(b).

2 Restructuring Advice Letter Filing ("RALF") Procedure For Review of QF Contract Restructurings.

3 ORMAT Group, an energy company based in Sparks, Nevada, purchased Ormesa Geothermal I & II in April 2002. The company owns and operates about 30 energy projects (geothermal, waste heat recovery, and solar), a total portfolio of about 200 MW. See www.ormat.com

Top Of Page