The table below shows initial estimates of annual program costs. These will be further refined once the utility issues a request for proposal and receives bids from contractors for exact costs.
Item and assumptions |
Estimated Cost |
Administrator Costs |
|
Contract administration, marketing, and regulatory reporting, and program evaluation (admin and marketing limited to a maximum of 5% of budget) |
$1,188,000 |
Installation, service, and operation costs |
|
Includes hardware, software, installation costs, communications, and customer incentives |
$4,752,000 |
Total Annual Program Budget |
$5,940,000 |
All customers participating in the program should receive the equipment and installation free of charge from the utility. In addition, the customer should receive a one-time incentive payment at the end of each year of program participation. The program administrator shall set a program incentive, which may include an annual program incentive, override penalties, and/or on-peak interruption bonuses.