4. Net Costs/Benefits of Expediting DWR's Removal as Supplier of Power

4.1. Framework for Assessing Net Cost/Benefits

IOU - Estimated Costs/Savings Assuming DWR Contract Novation
Completed as of October 2011
($NPV Millions)

 
 

PG&E

SCE

SDG&E

Total

Novation Costs

 

    Debt Equivalency

$ 8.00

$ 0.90

$ 1.30

$ 10.20

    Utility Collateral 14

$

$

 

$ 0

    Letters of Credit

 

$

 

$ 0

    Working Capital

 

$ 0.10

 

$ 0.10

    Administrative Costs

$ 0.80

$ 0.08

$ 0.20

$ 1.08

Total costs

$ 8.80

$ 1.08

$ 1.50

$ 11.38

Novation Benefits

 

    Release of DWR Reserves

$ 24.00

$ 31.50

$ 7.00

$ 62.50

    Administrative Cost Savings

$ 5.00

$ 1.90

$

$ 6.90

Total Benefits

$ 29.00

$ 33.40

$ 7.00

$ 69.40

Net Benefits/Costs

$ 20.20

$ 31.32

$ 5.50

$ 58.02

4.2. Potential Categories of Savings

4.2.1. Early Release of Reserves

4.2.1.1. Parties' Positions

4.2.1.2. Discussion

4.2.2. Potential Cost Savings from Renegotiated Contracts

4.2.2.1. Parties' Positions

4.2.2.2. Discussion

4.2.3. Potential Benefits from Price-Responsive Load

4.2.3.1. Discussion

4.2.4. Claimed Portfolio Management Savings

4.2.4.1. Parties' Positions

4.2.4.2. Discussion

4.3. Potential Categories of Cost

4.3.1. Debt Equivalence Costs

4.3.1.1. Parties' Positions

4.3.1.2. Discussion

"debt equivalence is one of several considerations that rating agencies factor into their assessment of a utility's overall risk profile. The Commission considers the rating agencies' credit ratings in the cost of capital proceeding and thus considers debt equivalence when it determines the IOUs' cost of capital."20

"in no way presupposes any related cost recovery, or adjustments to capital structures in future cost of capital proceedings. We continue to direct the IOUs, especially SDG&E, to raise any individual concerns it has with the impact of a particular PPA on its debt to equity ratio in its Cost of Capital proceeding."21

4.3.2. Collateral Requirements

1. Current Collateral - SCE estimates that it would incur an annual cost of $1.25 million based on an assumed cost of 125 basis points for a Letter of Credit for every $100 million of Mark-to-Market (MTM) exposure.

2. Stress Case Collateral - SCE estimates that it would incur an annual cost of $250,000, assuming 25 basis points for credit capacity for every $100 million of potential MTM exposure.

4.3.2.1. Discussion

4.3.3. Incremental Administrative and General Costs

4.3.3.1. Parties' Position

($ in millions)

 

January 2010

July 2010

October 2011

July 2012

PG&E

$0.8

$0.8

$0.80

0

SCE

$0.7

$0.5

$0.08

0

SDG&E

$1.2

$1.2

$0.7

$0.1

4.3.3.2. Discussion

4.4. Cash Working Capital

Assumed Date for Taking Over Contracts

($ in millions)

 

January 2010

July 2010

October 2011

July 2012

SCE

$3.7

$2.4

$0.4

$0.09

SDG&E

$0.8

$0.6

$0.2

$0.05

4.4.1. Discussion

4.5. Transactional Costs

4.5.1. Parties' Positions

4.5.2. Discussion

12 PG&E Comments dated August 4, 2008, at 11.

13 Although the table prepared by Reliant shows $1.3 million and $0.3 million, respectively as the SCE estimate for utility collateral and letters of credit, respectively, the values shown in the table do not represent SCE's total estimate of collateral requirements. As discussed in Sec. 4.3.2, the values in the table reflect only SCE's estimated costs per year for every $100 million of mark-to-market exposure. SCE assumed no additional collateral or letter of credit costs under the scenario of successful novation of all DWR contracts. SCE, however, expressed doubts that successful novation of all contracts is feasible, particularly by January 1, 2010. If contract terms changed materially as a result of renegotiation, SCE believes that additional collateral would be required, but did not quantify a precise amount.

14 Consistent with the discussion in Sec. 4.3.2, we have not reflected a specific estimate in the table above for utility collateral or letters of credit based on the assumption that contracts are novated "as is" with no material changes in credit risk. This assumption is subject to the outcome of negotiations and any potential changes in perceived risk exposure associated with the IOUs assuming replacement contracts.

15 TURN, Opening Comments, August 4, 2008, p. 2. Consumer Federation of California, Opening Comments, August 4, 2008, p. 14.

16 In certain circumstances, a rating agency may treat some portion of power purchase agreement costs as payments on debt obligations rather than as operating costs (treating them as "debt equivalent"), and in turn make corresponding adjustments to the utility's credit metrics and financial ratios used as part of the rating agency's overall assessment of credit quality.

17 The risk factor is an element applied by S&P in assigning risk to an entity. S&P usually applies a risk factor ranging from 0% to 50% depending on the regulatory environment and counterparty risk.

18 D.07-12-052, Finding of Fact 75.

19 Id, Ordering Paragraph 36.

20 D.07-12-052 at 162. In D.08-11-008, the Commission modified D.07-12-052 finding that "it is appropriate in some cases for the IOUs to recognize the effects of [debt equivalence] in their bid evaluation processes." (D.08-11-088, p. 16.)

21 Id. at 165.

22 See Declaration of Jeffrey D. Merola, attached to the August 4, 2008, comments of Reliant at page 12, referencing the July 2, 2008 workshop transcript at page 383, relating to DWR representative's discussion of the potential conditions under which IOUs would need to post collateral.

Previous PageTop Of PageNext PageGo To First Page