3. Timetable; Submission Date
The timetable for the critical path issues in this proceeding and the projected submission dates are set forth in the following schedules. I recognize that the time allotted for intervenors to review and analyze the proposed procurement plans before they file their testimony is limited. To facilitate that review and analysis, and to potentially mitigate discovery issues, I will direct that a data clarification workshop be convened at which each utility will explain the input assumptions and outputs of its proposed long term procurement plan, and answer data clarification questions.
Schedule A - Long-Term Procurement Plans
Event
Date
Long-term plans and supporting testimony
07/09/04
Workshop on plan clarification
07/16/04
Intervenor testimony
08/04/04
Rebuttal testimony
08/18/04
Cross-examination estimates
08/23/04
Prehearing conference - motions, schedule witnesses, etc.
08/25/04
Hearings begin
08/30/04
Hearings end
09/10/04
Concurrent opening briefs/requests for final oral argument
09/27/04
Concurrent reply briefs/submission
10/08/04
Proposed decision
11/16/04
Comments
12/06/04
Reply comments
12/13/04
Final Commission order on long-term procurement plans
12/16/04
Schedule B - Resource Adequacy Issues
Event
Date
Workshop report
06/__/04
Comments on workshop report (due 21 days after report)
07/__/04
Replies to comments/submission (due 14 days after comments)
07/__/04
Draft decision
08/24/04
Final Commission order on resource adequacy issues
09/23/04
The timetable for resolution of procurement incentives, expiring QF contracts, management audits, and any RAR issues not resolved pursuant to Schedule B will be determined at a later date. As already noted in the OIR, the Commission intends to resolve all matters in this proceeding within 18 months of the date of this scoping memo, consistent with Pub. Util. Code § 1701.5.