V. Comments on Draft Decision

The draft decision of ALJ Simon in this matter was mailed to the parties in accordance with Pub. Util. Code § 311(g)(1) and Rule 77.7 of the Rules of Practice and Procedure. Comments were filed on ____________.

Findings of Fact

1. It is reasonable for utilities to make estimates of future procurement from specific types of renewable resources for planning purposes.

2. It is reasonable for utilities to plan for the possibility that not all planned renewable developments will deliver the planned-for energy, whether due to erosion of the baseline renewable resources, errors in load forecasting, transmission constraints, or unforeseen difficulties in project development.

3. It is reasonable for utilities to make estimates of future needs for transmission, delivery points, remarketing costs, and other delivery issues for renewable resources for planning purposes.

4. The planning estimates of the utilities for the year 2010 currently identify wind, geothermal, and solar thermal resources as significant sources of renewable energy procurement; these resources may be located in areas that are remote from the utility's load center.

5. The plans do not adequately address the consequences of the estimated reliance on resources that may be remote from the utilities' load center.

6. The long-term RPS plans of the utilities do not address all areas necessary for adequate RPS planning.

7. It is reasonable to require the utilities to supplement their plans, as needed, with respect to transmission planning, repowered wind resources, and alternative and contingency planning.

Conclusions of Law

1. Utilities should provide analysis and reasoned discussion in their RPS planning of the consequences of reliance for RPS procurement on resources remote from their load centers.

2. Utilities should address in their long-term RPS planning the availability of renewable resources and transmission planning (including delivery outside the utility's service territory, curtailablity, remarketing costs and benefits, and other alternatives to building new transmission).

3. Utilities should address in their long-term RPS planning the repowering of wind facilities currently under contract to the utility.

4. Utilities should include in their long-term RPS planning analysis that includes high, low, and base case scenarios.

5. Utilities should address in their long-term RPS planning potentially significant impediments to RPS compliance and include contingency planning addressing the identified impediments.

6. Utilities should explicitly address in their long-term RPS planning lessons learned from previous planning cycles.

7. In order to guard against shortfalls of planned renewable energy deliveries, utilities should provide in their RPS planning for procurement greater than the annual IPT required to reach the goal that 20% of their retail sales of energy be from eligible renewable resources by 2010.

8. Beginning in 2006, utilities' long-term planning for RPS compliance should be integrated with their general long-term procurement planning, in R.04-04-003 or its successor proceedings.

9. In integrating RPS planning with general procurement planning, utilities should specifically identify RPS planning components.

10. In order to begin more complete RPS planning, the utilities should, within 30 days of the mail date of this decision, supplement their current filings as follows:


a. PG&E must include:


b. SCE must include:


c. SDG&E must include:

11. In order for RPS planning to move forward expeditiously, this decision should be effective today.

INTERIM ORDER

IT IS ORDERED that:

1. Not later than 30 days from the mailing date of this decision, Pacific Gas & Electric Company (PG&E) must serve and file a supplement to its long-term procurement plan for the Renewables Portfolio Standard (RPS) program, including at least the following elements:

2. Not later than 30 days from the mailing date of this decision, Southern California Edison Company (SCE) must serve and file a supplement to its long-term RPS procurement, including at least the following elements:

3. Not later than 30 days from the mailing date of this decision, San Diego Gas & Electric Company (SDG&E) must serve and file a supplement to its long-term RPS procurement, including at least the following elements:

4. The utilities' future long-term plans for RPS compliance shall be conducted as part of general procurement planning in Rulemaking 04-04-003 or its successor proceedings.

5. The utilities' future long-term plans for RPS compliance shall include specific and identifiable RPS planning components in general procurement planning documents, and shall address at least the following topics:

This order is effective today.

Dated , at San Francisco, California.

Simon Notice of Availability

Previous PageTop Of PageGo To First Page