ENERGY DIVISION RESOLUTION E-3732

RESOLUTION

Resolution E-3732: Guidelines for Processing Advice Letters for Projects not Requiring Certificates of Public Convenience and Necessity or Permits to Construct During Energy Supply Emergencies Declared by the Governor of California

__________________________________________________________

SUMMARY

This Resolution establishes a procedure through which utilities subject to General Order (GO) 131-D may reduce the time between the filing of an informational advice letter concerning proposed energy transmission and distribution facilities for which a certificate of public convenience and necessity or permit to construct is not necessary and the date construction may begin, during energy supply emergencies declared by the Governor of California.