D0911009 Appendix 1
Word Document PDF Document

ALJ/KK2/lil Date of Issuance 11/25/2009

Decision 09-11-009 November 20, 2009

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Application of Pacific Gas and Electric Company for Approval of the 2009-2011 Low-Income Energy Efficiency and California Alternate Rates for Energy Programs and Budget (U39M).

Application 08-05-022

(Filed May 15, 2008)

And Related Matters.

Application 08-05-024

Application 08-05-025

Application 08-05-026

DECISION CORRECTING ERRORS IN
ATTACHMENT OF DECISION 08-11-031

1. Summary

This decision corrects four erroneous entries on Attachment F of Decision (D.) 08-11-031, in the Southern California Edison Company (SCE) Cost-Effectiveness Table (Attachment F). Attachment F incorrectly shows the replacement central air conditioner measure1 in four particular instances as passing the cost-effectiveness tests in climate zone 13 when, in fact, the measure failed the tests. These errors are misleading because these erroneous reportings suggest that the measure maybe approved in the Low-Income Energy Efficiency (LIEE) program as a cost-effective LIEE measure in those instances when, in fact, the measure is not approved because the measure failed the tests. Therefore, we correct Attachment F to reflect the correct cost-effectiveness analysis results, and we further take this opportunity to clarify the Commission's cost-effectiveness analysis in D.08-11-031 and to provide additional guidance to the parties on the subject.

1 The corrections in this decision do not relate to or affect the room air conditioner replacement or central air conditioner service measures for those household types which passed the cost-effectiveness tests and are presently permitted in SCE's climate zone 13 as separate and approved cost-effective LIEE measures.