VII. Conclusion

As discussed above, we have adopted the following modifications to SCE and SDG&E's calculations of the decommissioning cost revenue requirements:


· A 10.5% pre-tax return on equities.


· A 6.0% pre-tax return on fixed assets.


· Escalation rates, except for LLRW burial costs, based on the most recent DRI forecasts in the record, using weighted averages, and no separate contingency factor.


· A 7.5% escalation rate for LLRW burial costs.


· LLRW burial costs of $200 per cubic foot.


· A contingency factor of 35% for Palo Verde.

Based on the above modifications to the decommissioning cost calculations, we adopt an annual revenue requirement for SONGS 2&3 for SCE of $21.160 million, respectively. We also adopt an annual revenue requirement for Palo Verde $11.688 million. This results in an overall annual revenue requirement for SCE of $32.848 million.

Based on the above modifications to the decommissioning cost calculations, we adopt an annual revenue requirement for SONGS 2&3 for SDG&E of $6.692 million.

In addition to the above revenue requirements, we find the SONGS 1 decommissioning work completed as of December 31, 2001 ($91 million) reasonable, find the utilities' estimate of SONGS 1 remaining decommissioning work ($531 million) reasonable, and authorize the utilities to use the tax benefits retained in the non-qualified trust fund for SONGS 1 to fund decommissioning work on that plant.

This decision should be effective immediately, so that the revenue requirements adopted herein can be put into effect as soon as possible.

Previous PageTop Of PageNext PageGo To First Page