Upon completion of its further negotiations with Whispering Hills, SDG&E shall file and serve a motion, requesting leave to modify its application to reflect the results of the negotiations. To the extent that other parties wish to comment on those results, they may file and serve responses to SDG&E's Motion, consistent with Rule 45 of the Commission's Rules of Practice and Procedure (Rules). If SDG&E's Motion is granted, this Commission will then proceed to consider the sale of the property as proposed in the application.8 At the time that the Commission considers the sale of the land, the Commission will perform the CEQA review appropriate to that project, again in the role of responsible agency.
8 The Commission will also consider the procedural issues discussed in the ALJ Ruling of October 14, 2004.