Word Document PDF Document |
2006
TRIENNIAL ON-SITE SAFETY AUDIT
OF THE BAY AREA RAPID TRANSIT
RAIL TRANSIT SAFETY SECTION
RAIL TRANSIT AND CROSSINGS SAFETY BRANCH
CONSUMER PROTECTION AND SAFETY DIVISION
CALIFORNIA PUBLIC UTILITIES COMMISSION
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102
May 29, 2007
FINAL REPORT
Richard W. Clark, Director
Consumer Protection and Safety Division
BAY AREA RAPID TRANSIT DISTRICT'S
RAIL TRANSIT SAFETY PROGRAM
The California Public Utilities Commission's Rail Transit Safety Section staff, with the assistance of staff from the Railroad Operations Safety Branch, conducted this system safety program audit. Staff members directly responsible for conducting audit and inspection activities include:
Claudia Lam, Lead Auditor |
Anton Garabetian |
Joey Bigornia |
Georgetta Gregory |
Sherman Boyd |
Don Miller |
Brian Chavez |
Gary Rosenthal |
William Dockery |
Brian Yu |
Raed Dwairi |
|
TABLE OF CONTENTS
Page
1. EXECUTIVE SUMMARY.................................................................1
2. INTRODUCTION .......................................................................... 3
3. BACKGROUND ............................................................................5
A. BART Rail System Description
B. BART 2003 Triennial Audit
4. AUDIT PROCEDURE ....................................................................7
5. FINDINGS AND RECOMMENDATIONS ............................................8
APPENDICES
A. TSA Executive Summary................................................................16
B. BART 2006 Triennial Audit Index of Checklists ...................................19
C. BART 2006 Triennial Audit Recommendations List ...............................21
D. BART 2006 Triennial Audit .............. ...............................................23
1. EXECUTIVE SUMMARY
The California Public Utilities Commission's (Commission) Consumer Protection and Safety Division (CPSD), Rail Transit Safety Section staff (staff), with the assistance of staff from the Railroad Operations Safety Branch (staff), conducted an on-site safety audit of the Bay Area Rapid Transit District's (BART) safety program in August 2006.
The on-site audit was preceded by a pre-audit conference with BART personnel, including BART's General Manager, Chief Safety Officer, and Chief of Police, on August 14, 2006. Transportation Safety Administration (TSA) representatives were invited to attend the meeting and participate in the reviewing of BART's security plan.
The 2006 On-site Safety Audit was conducted in two phases. The first phase consisted of facilities and equipment inspections on August 1, 7, and 8, of 2006, completing audit checklists number one through four. During phase two of the audit, staff conducted the on-site safety audit from August 14 to August 21, 2006, completing the remaining twenty-nine (29) checklists. The remaining checklists focused on verifying the effective implementation of the safety and security program plan.
A post-audit conference with BART personnel and TSA representatives followed the On-site Safety Audit on September 6, 2006. Staff provided BART personnel with a synopsis of the preliminary audit findings and possible recommendations for corrective actions. TSA representatives utilized the Surface Transportation Action Review checklist to review and baseline the internal processes, procedures, and policies inherent in the BART system relating to BART system security. Appendix A provides the TSA Executive Summary.
The audit results indicate that BART has a comprehensive System Safety Program Plan (SSPP) and has effectively carried out that plan. Exceptions, however, were noted during the audit. These exceptions are described, where applicable, in the Findings/Comments Section of each checklist along with recommendations to correct identified exceptions. Of the 33 checklists, staff made 12 recommendations for corrective action. Recommendations for corrective action are directed in the areas of maintenance activities, safety audit programs, emergency response planning and training, transit vehicle maintenance, train equipment inspections and tests, signal maintenance training and certification, and operations safety compliance program.
The Introduction for this report is presented in Section 2. The background, in Section 3, contains a description of the BART rail system and the 2003 audit results. Section 4 describes the audit procedure. The audit findings and recommendations are depicted in Section 5. The BART 2006 Triennial Audit Safety Checklist Index and the Recommendations List are included, respectively, in Appendices B and C. The Safety Audit Checklists are presented in Appendix D.
2. INTRODUCTION
The Commission's General Order (GO) 164-C, Rules and Regulations Governing State Safety Oversight of Rail Fixed Guideway Systems, and the Federal Transit Administration's (FTA) Rule, Title 49 Code of Federal Regulations (CFR) Part 659, Rail Fixed Guideway Systems; State Safety Oversight, require the designated State Safety Oversight Agencies to perform a review of each rail transit agency's system safety program at a minimum of once every three years. The purpose of the triennial audit is to verify compliance with and evaluate the effectiveness of each rail transit agency's System Safety Program Plan (SSPP) and to assess the level of compliance with GO 164-C as well as other Commission safety requirements. BART was last audited in October 2003.
On July 21, 2006, staff mailed a letter to the BART General Manager (GM), advising him that the triennial audit would be scheduled for early August, 2006. The letter included 33 checklists that served as the basis for the audit. Four of the 33 checklists outlined inspection of track, signals, electric power systems, and vehicles. The remaining 29 checklists focused on the verification of the effective implementation of the safety and security program plan.
On August 14, 2006, staff conducted a pre-audit conference with BART's General Manager, Chief Safety Officer, and Chief of Police. TSA representatives attended the pre-audit conference to describe the methods and checklists they will be using to review BART's security program.
Staff conducted the on-site safety audit and records review from August 14, 2006 to August 21, 2006. At the conclusion of each audit activity, staff provided the BART representative with a summary of the preliminary findings and discussed any recommendations for corrective actions.
On September 6, 2006, staff conducted a post-audit exit meeting with BART's General Manager, Chief of Police, and Chief Safety Officer with TSA representatives in attendance. Attendees were given a synopsis of the findings from the 33 checklists and discussed the need for corrective actions where applicable. Staff also answered questions about the findings and explained that a preliminary draft audit report would be prepared for BART to review and comment.
3. BACKGROUND
A. SYSTEM DESCRIPTION
Original revenue operation year and track miles
BART began operation on September 11, 1972 with 28 miles of track in the Alameda County, servicing from Oakland to Fremont. The second segment opened on January 29, 1973 with 12 miles of track extending the service from Fremont to Richmond. The third segment opened on May 21, 1973 with 17 additional miles of track marking the opening of the Concord Line. On November 5, 1973, service began between Montgomery Street Station in downtown San Francisco and Daly City Station, adding another 7.5 miles of track to the system. Transbay service began on September 16, 1974, bringing the full 71.5 miles of track into service. On May 27, 1976, the Embarcadero Station officially opened for revenue service, bringing the total station count to 34. The Embarcadero Station added no additional track miles.
Extensions added by the years and added track miles
The extension to North Concord/Martinez Station opened on December 16, 1995, adding 2.25 miles of track north of the Station. On February 24, 1996, Colma Station opened for revenue service, adding 1.6 miles of track south of the Daly City Station. The Pittsburg/Bay Point Station was the next to be opened for revenue service on December 7, 1996, completing a 7.8-mile segment of the Pittsburg/Antioch Extension from the Concord Station. The Dublin/Pleasanton extension opening followed on May 10, 1997, adding 14 miles of track and two stations to the system. The San Francisco Airport extension opened on June 22, 2003 adding four stations and 8.7 miles of track. Currently, the system has approximately 119 miles of track.
On-going Extension Projects
Warm Springs Extension
The Warm Springs Extension Project will add 5.4 miles of track, extending BART's railway system from the Fremont Station to the Warm Springs Station in South Fremont. Staff has reviewed and approved the Safety and Security Certification Plan for this project.
Santa Clara Valley Transportation Authority/Silicon Valley Rapid Transit Project
The Santa Clara Valley Transportation Authority/Silicon Valley Rapid Transit Project (VTA/SVRT Project) is a 16.3-mile extension beginning at the Warm Springs BART Station in South Fremont, extending along the Union Pacific Railroad line to Milpitas and then continues on to 28th and Santa Clara Streets in San Jose. The extension will then proceed underground through Downtown San Jose to the Diridon Caltrain Station. The BART extension will then turn north under the Caltrain line and terminate at the Santa Clara Station. The project is in the preliminary engineering stage.
B. 2003 TRIENNIAL AUDIT
Staff's previous audit of BART's System Safety Program was performed in October 2003. Twenty-two (22) recommendations for corrective action resulted from thirty-six checklists. The majority of the recommendations focused on preventive maintenance inspections and training/recertification programs.
The report on the 2003 Safety Audit of BART was granted by Commission Resolution ST-70, dated May 27, 2004. BART has developed and completed corrective actions to implement the recommendations prior to the 2006 audit.
Staff conducted the audit in accordance with the Rail Transit Safety Section Procedure RTSS-4, Procedure for Performing Triennial Safety Audits of Rail Transit Systems.
Staff developed thirty-three (33) checklists to cover various aspects of system safety responsibilities, using FTA guidelines, American Public Transportation Association (APTA) guidelines, and the staff's knowledge of the transit system. The 33 checklists are included as Appendix D.
Each checklist identified the APTA elements and characteristics audited, results of the audit, and recommendations for improvement, where applicable. The methods used to perform the audit include:
*0 Discussions with BART management
*1 Reviews of procedures and records
*2 Observations of operations and maintenance activities
*3 Interviews with rank and file employees
*4 Inspections and measurements of equipment and infrastructure
*5 Follow-up to the 2003 BART Triennial Audit
The audit checklists concentrated on requirements that affect the safety of train operations and are known or believed to be important in reducing safety hazards and preventing accidents.
5. FINDINGS AND RECOMMENDATIONS
The auditors and inspectors concluded that the BART rail transit system has a comprehensive System Safety Program Plan (SSPP) and that BART has been effective in implementing that plan.
Audit findings identified areas where changes should be made to further improve BART's system safety program. The audit results were derived from activities observed, documents reviewed, management discussions, and items inspected, confirming that BART is generally in compliance with its SSPP. The audit identified 12 recommendations from the 33 checklists outlined below:
1. Tack Inspection
No deficiency - No recommendation.
2. Vehicle Inspection
No deficiency - No recommendation.
3. Signal Inspection
No deficiency - No recommendation.
4. GO 95 Inspection
Deficiencies found:
· "Danger Electric Third Rail Keep Away" signs posted on the chain-link fencing were covered with graffiti.
· "Danger Electric Third Rail Keep Away" signs posted on the third rail cover boards throughout the underground stations were covered with thick layers of dust, making the signs not readily visible.
· "Danger Electric Third Rail Keep Away" signs posted on the third rail cover boards at the outdoor stations have found to be fading and peeling.
· "Danger Electric Third Rail Keep Away" signs posted on the chain-link fencing were covered with tree leaves.
· Traction Power Substation (TPSS) at the Ashby Substation had water leaking from the inside wall and accumulating on the floor.
· At various locations along the BART A-Line, trees and shrubbery have not been properly trimmed and or removed. More specifically:
- At certain locations near aerial structures, tree branches have found to be touching third rail cover boards.
- At certain locations, tree/shrubbery branches were growing over/through the fencing, partially blocking the maintenance walkways.
The specific areas noted were:
- Mile Post 3.1 on A2 track side
- Mile Post 12.2 on A2 track side
- Mile Post 19.8 on A2 track side
- Mile Post 23.4 on A2 track side
Recommendations:
1. BART should survey the entire system to ensure that signs are provided and maintained in accordance with GO 95, Section 79.5 requirements and replace/re-label the "Danger Electric Third Rail Keep Away" signs where needed.
2. BART should survey the entire system and trim/eradicate vegetation/tree growing near the right-of-way where necessary.
3. BART should investigate the water leakage in the TPSS and take corrective action in accordance with GO 128, Section 30 requirements. The corrective action should also prevent future occurrence of the same problem.
5. Third Rail Maintenance
No deficiency - No recommendation.
6. Reporting and Investigating Accidents and Investigation Procedures
No deficiency - No recommendation.
7. Review Operating Rules and Procedures Manual and Operating Bulletins
Deficiencies found:
· Management Procedure No. 34 requires an annual review of the BART Operating Rules and Procedures (OR&P) without establishing the criteria in which the document is required to be revised.
· Management Procedure No. 34 requires an annual review of the Operating Bulletins without establishing the criteria in which the bulletins are required to be revised.
· Management Procedure No. 34 refers to three BART Supplementary Operations Manuals but failed to identify them.
Recommendations:
4. BART should revise the appropriate control document to describe annual review process of the OR&P and the Operating Bulletins, including activities involved in the process and how the process (such as making findings, reaching conclusions, and recommending actions... etc.) is documented.
5. BART should list or provide a reference to all of the Supplementary Operations Manuals that apply to Management Procedure No. 34.
8. Review Employee Safety Program
No deficiency - No recommendation.
9. Internal Safety Audit Program
No deficiency - No recommendation.
10. Inter-departmental Safety Audit Program
Deficiencies found:
· Interdepartmental and interagency coordination was not included as a specific element of the BART internal safety audit program.
· Although the interdepartmental and interagency coordination process and requirements are discussed in the BART System Safety Program Plan, they are not defined in detail or specifically referenced. The System Safety Program Plan also failed to identify the BART Fire Life Safety Committee.
· BART identified and reviewed communications deficiencies with emergency responders and other participating agencies following emergency exercises and actual events. In cases where communications deficiencies were found to be the responsibility of emergency responders or other participating agencies, there was no clear evidence that BART tracked the corrective actions and verified the satisfactory resolution of the deficiencies.
Recommendations:
6. BART System Safety Program Plan should identify or reference all of the respective interdepartmental and interagency coordination programs, processes, and procedures, including the Fire Life Safety Committee (See Checklist No. 14).
7. BART should adopt and implement procedures to track and verify that all identified communications deficiencies affecting BART are tracked until the deficiencies are corrected (See Checklist No. 14).
11. Safety and Security Certification Plan (Warm Springs Extension)
No deficiency - No recommendation.
12. Hazardous Materials Management Program
No deficiency - No recommendation.
13. Data Acquisition Analysis
No deficiency - No recommendation.
14. Emergency Response Planning and Training
Deficiencies found:
· The Fire Life Safety Committee or its function was not described, specified, or referenced in BART's System Safety Program Plan.
· BART departments and other participants are invited to critique emergency drills and actual emergency events after the exercises or events are completed. Although deficiencies effecting BART are identified and reviewed by the participants, there is no record that corrective actions are established and tracked and the deficiencies corrected.
Recommendations:
6. BART System Safety Program Plan should identify or reference all of the respective interdepartmental and interagency coordination programs, processes, and procedures, including the Fire Life Safety Committee (See Checklist No. 10).
7. BART should adopt and implement procedures to track and verify that all identified communications deficiencies affecting BART are tracked until the deficiencies are corrected (See Checklist No. 10).
15. Drug and Alcohol Testing Program
No deficiency - No recommendation.
16. Security Program - BART Police and Security Audits
No deficiency - No recommendation.
17. Train Operator, Line Supervisor, and Central Control Supervisor Training and Recertification
No deficiency - No recommendation.
18. Hours of Service for Train Operators, Train Controllers, and Tower Fore Workers
No deficiency - No recommendation.
19. Calibration of Measuring and Testing Equipment
No deficiency - No recommendation.
20. Track Inspection and Turnout Inspection Records
No deficiency - No recommendation.
21. Exclusive Right-Of-Way Fence Inspection Records
Deficiencies found:
· Certain inspection records did not have the status of corrective actions taken.
· Certain inspection records were incomplete and corrective action completion could not be confirmed.
Recommendation:
8. BART should ensure that their fore workers and supervisors properly document the inspection, corrective actions, and completion status of the corrective actions to allow efficient and effective follow-up.
22. Transit Vehicle Maintenance
No deficiency - No recommendation.
23. Quality Assurance of Transit Vehicles
Deficiency found:
· For the cars selected at the Richmond Yard Shop (B cars: 1551, 1562, and 1567, C1 cars: 2557 and 2537, and C2 cars: 365 and 429), each had at least one missing Quality Assurance (QA) stamp on a Maintenance Discrepancy/Correction Sheet (D/C Form) in the Car History Book corresponding to the requirement of "To Be Released by QA Only."
Recommendation:
9. BART should review its applicable Quality Assurance (QA) procedures which pertain to the use of QA stamps to achieve consistency between Car History Books and archived files.
24. Train Control Equipment Inspection and Tests
Deficiency found:
· Two Trouble Tickets associated with multiplexer (MUX) inspections were not closed out in a timely manner. Trouble Ticket TC-C76-BATT remained open since October 2004 and TC-W45-SM151 remained open since May 2004.
Recommendation:
10. BART should follow up on open Train Control Equipment Trouble Tickets by generating a report listing the tickets, reasons behind the open status of those tickets, and a plan to resolve the issues and close the open tickets in a timely manner.
25. Emergency Ventilation Fans and Associated Dampers
No deficiency - No recommendation.
26. Vital Relays
No deficiency - No recommendation.
27. Fire Alarms and Sprinkler Systems
No deficiency - No Recommendation.
28. Wet Stand Pipe, Sprinkler Systems, and Line Pumps
No deficiency - No recommendation.
29. Under-Car Deluge System
No deficiency - No recommendation.
30. Gap Breakers and Wayside Equipment
No deficiency - No recommendation.
31. Signal Maintenance Training and Certification
Deficiencies found:
· The record of a selected Train Control Maintenance Technician indicated that the employee failed the Vital Processor Interlocking (VPI) Hardware Recertification test on September 29, 2005 and did not attend the April 17, 2006 General Railway Signal (GRS) VPI Hardware Certification training course.
· No documentation was found to explain the employee's failure to attend the class or to indicate if a Restricted Status was placed on this employee to prevent him from performing maintenance work on any equipment requiring VPI Certification as required by BART Employee Certification Plan dated January 2005.
· The class roster of the April 17, 2006 GRS VPI Hardware Certification Class obtained from the Pathlore Learning Management System listed those who attended the class, their test scores, and those who cancelled their registration. However, the roster did not provide an explanation of their cancellation.
Recommendation:
11. BART should ensure that Train Control Technicians who failed their recertification test are not working on equipment requiring their success in being recertified. BART should have proper documentation explaining the technician's failure to be recertified.
32. Contractor Safety Coordination
No deficiency - No recommendation.
33. Review Operations Safety Compliance Program
Deficiency found:
· BART Transportation Department, BART Maintenance and Engineering Department, and BART Operations Liaisons have developed and adopted safety compliance programs, but have not implemented these programs.
Recommendation:
12. BART should implement the Operations Safety Compliance Program plans for the Transportation Department, BART Maintenance and Engineering Department, and BART Operations Liaisons.
APPENDIX A
TSA EXECUTIVE SUMMARY
APPENDIX B
BART 2006 TRIENNIAL SAFETY AUDIT INDEX OF CHECKLISTS
BART 2006 TRIENNIAL SAFETY AUDIT | |||
INDEX OF CHECKLISTS | |||
Checklist No. |
Characteristic |
Checklist No. |
Characteristic |
1 |
Track Inspection |
18 |
Hours of Service of Train Operators, Train Controllers, and Tower Fore Workers |
2 |
Vehicle Inspection |
19 |
Calibration of Measuring and Testing Equipment |
3 |
Signal Inspection |
20 |
Track Inspection and Turnout Inspection Records |
4 |
GO 95 Inspection |
21 |
Exclusive Right-Of-Way Fence Inspection Records |
5 |
Third Rail Maintenance |
22 |
Transit Vehicle Maintenance |
6 |
Reporting and Investigating Accidents and Investigation Procedures |
23 |
Quality Assurance of Transit Vehicles |
7 |
Review Operating Rules and Procedures Manual and Operating Bulletins |
24 |
Train Control Equipment Inspection and Tests |
8 |
Review Employee Safety Program |
25 |
Emergency Ventilation Fans and Associated Dampers |
9 |
Internal Safety Audit Program |
26 |
Vital Relays |
10 |
Inter-departmental Safety Audit Program |
27 |
Fire Alarms and Sprinkler Systems |
11 |
Safety and Security Certification Plan (Warm Springs Extension) |
28 |
1) Wet Stand Pipe, 2) Sprinkler Systems, and 3) Line Pumps |
12 |
Hazardous Materials Management Program |
29 |
Under-Car Deluge System |
13 |
Data Acquisition Analysis |
30 |
Gap Breakers and Wayside Equipment |
14 |
Emergency Response Planning and Training |
31 |
Signal Maintenance Training and Certification |
15 |
Drug and Alcohol Testing Program |
32 |
Contractor Safety Coordination |
16 |
Security Program - BART Police and Security Audits |
33 |
Review Operations Safety Compliance Program |
17 |
Train Operator, Line Supervisor, and Central Control Supervisor Training and Recertification |
|
|
APPENDIX C
BART 2006 TRIENNIAL AUDIT RECOMMENDATIONS LIST
| ||
BART 2006 TRIENNIAL SAFETY AUDIT RECOMMENDATIONS LIST | ||
No. |
Recommendation |
Checklist No. |
1 |
BART should survey the entire system to ensure that signs are provided and maintained in accordance with GO 95, Section 79.5 requirements and replace/re-label the "Danger Electric Third Rail Keep Away" signs where needed. |
4 |
2 |
BART should survey the entire system and trim/eradicate vegetation/tree growing near the right-of-way where necessary. |
4 |
3 |
BART should investigate the water leakage in the TPSS and take a corrective action in accordance with GO 128 section 30 requirements. The corrective action should also prevent future occurrence of the same problem. |
4 |
4 |
BART should revise the appropriate control document to describe annual review process of the OR&P and the Operating Bulletins, including activities involved in the process and how the process (such as making findings, reaching conclusions, and recommending actions... etc.) is documented. |
7 |
5 |
BART should list or provide a reference to all of the Supplementary Operations Manuals that apply to Management Procedure No. 34. |
7 |
6 |
BART System Safety Program Plan should identify or reference all of the respective interdepartmental and interagency coordination programs, processes, and procedures, including the Fire Life Safety Committee. |
10, 14 |
7 |
BART should adopt and implement procedures to track and verify that all identified communications deficiencies affecting BART are tracked until the deficiencies are corrected. |
10, 14 |
8 |
BART should ensure that their fore workers and supervisors properly document the inspection, corrective actions, and completion status of the corrective actions to allow efficient and effective follow-up. |
21 |
9 |
BART should review its applicable Quality Assurance (QA) procedures which pertain to the use of QA stamps to achieve consistency between Car History Books and archived files. |
23 |
10 |
BART should follow up on open Train Control Equipment Trouble Tickets by generating a report listing the tickets, reasons behind the open status of those tickets, and a plan to resolve the issues and close the open tickets in a timely manner. |
24 |
11 |
BART should ensure that Train Control Technicians who failed their recertification test are not working on equipment requiring their success in recertification. BART should have proper documentation explaining the technician's failure to be recertified. |
31 |
12 |
BART should implement the Operations Safety Compliance Program plans for the Transportation Department, BART Maintenance and Engineering Department, and BART Operations Liaisons. |
33 |
APPENDIX D
BART 2006 TRIENNIAL AUDIT CHECKLISTS (1 THROUGH 33)
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
1 |
Element |
Track Inspection | ||||
Date of Audit
|
8/8/2006 |
Department |
Maintenance and Engineering | ||||
Auditors / Inspectors |
Brian Chavez |
Persons Contacted |
Ken Cook | ||||
REFERENCE CRITERIA | |||||||
Track Standards Manual, June 1, 1995 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
FRA certified track inspector, from the Commission's Railroad Operations Safety Branch, will perform detailed visual and dimensional inspections/measurements of three sections of mainline track, four switches, four crossovers, and four turnouts to determine if the selected components are in compliance with the Code of Federal Regulation maintenance standards. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
The inspector performed switch inspections for compliance with Code of Federal Regulations Title 49, part F 213.235 and reviewed quarterly and annual procedures. The inspector also performed inspections of rail joints, including insulated joints. All switches inspected were lined both in the normal and reverse position by the dispatcher before the work group left the area to ensure they were working as intended. | |||||||
Comments: | |||||||
BART's track maintenance practices are effective. BART's maintenance manual and check-off list cover each procedure in a comprehensive manner. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
2 |
Element |
Vehicle Inspection | ||||
Date of Audit
|
8/9/2006 |
Department |
Rolling Stock and Shops | ||||
Auditors / Inspectors |
Don Miller |
Persons Contacted |
Rich Burr | ||||
REFERENCE CRITERIA | |||||||
Book 42: Automatic Train Control Maintenance Procedures Book 50: C Car Maintenance Procedures Book 86: A2/B2 Car Maintenance Procedures | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
CPUC Inspectors will select and inspect at least two B cars, one A car, and one C car from the Richmond Shop to determine if BART is maintaining its vehicles properly and adequately. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
The inspectors selected and inspected BART vehicles number 2517C, 421C, 1243A, 1250A, 1692B, and 1769B at the Richmond Maintenance Facility. The scope of the inspection included: a) Visual inspection of the passenger cab, operator cab, door operation, safety appliances, truck / wheel components, traction motors, brake system, coupler assemblies and current collectors. b) Review of maintenance records of vehicle undergoing preventive maintenance inspection. c) Interview with and observation of maintenance personnel during preventive maintenance inspection/repairs. d) Review of recently released vehicle maintenance record for completeness and accuracy. e) Review of the maintenance standards used to perform vehicle maintenance. | |||||||
Comments: | |||||||
None. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
3 |
Element |
Signal Inspection | ||||
Date of Audit
|
8/8/2006 |
Department |
Maintenance and Engineering | ||||
Auditors / Inspectors |
Sherman Boyd |
Persons Contacted |
Don Allen | ||||
REFERENCE CRITERIA | |||||||
Operation Rules & Procedures
BART computer program - DataStream | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
FRA certified signal inspector, from the Commission's Rail Operations Safety Branch, will perform detailed inspections of selected mainline train control and signal systems and components. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
The inspector performed switch obstruction tests and reviewed monthly maintenance records to verify compliance with BART's' maintenance instruction manual on 315 E, 115 A, 213, and 413 F switches. The inspector also reviewed quarterly and annual procedures and visually inspected 12 insulated joints. All inspected switches were lined both in the normal and reverse position by the dispatcher before the work group left the area to ensure they were working as intended. | |||||||
Comments: | |||||||
BART's maintenance practices and trouble reporting procedures are well honed and effective. | |||||||
Recommendations: |
|||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR |
|||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
4 |
Element |
GO 95 Inspection | ||||
Date of Audit
|
8/1/2006 |
Department |
Maintenance and Engineering Way and Facilities Maintenance | ||||
Auditors / Inspectors |
Brian Yu |
Persons Contacted |
Randy Clark | ||||
REFERENCE CRITERIA |
|||||||
CPUC GO 95, Section 79.5 and Section 35
|
|||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION |
|||||||
The Inspector will inspect a minimum of three separate third rail segments to determine if they are in compliance with the General Orders. The Inspector will also inspect a minimum of three Substations to determine if they are in compliance with the General Orders. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
1. Traction Power Substation (TPSS) maintenance was in good standing. 4. "Danger Electric Third Rail Keep Away" signs posted on the third rail cover boards throughout the underground stations were covered with thick layers of dust, making the signs not readily visible. 5. "Danger Electric Third Rail Keep Away" signs posted on the third rail cover boards at the outdoor stations have found to be fading and peeling. 6. "Danger Electric Third Rail Keep Away" signs posted on the chain-link fencing were covered with accumulating on the floor. 8. At various locations along the BART A-Line, trees and shrubbery have not been properly trimmed/removed. More specifically: cover boards. - At certain locations, trees/shrubbery branches were growing over/through the fencing, partially blocking the maintenance walkways.
The specific areas noted were: - Mile Post 3.1 on A2 track side - Mile Post 12.2 on A2 track side - Mile Post 19.8 on A2 track side - Mile Post 23.4 on A2 track side | |||||||
Comments: |
|||||||
None. | |||||||
Recommendations: |
|||||||
1. BART should survey the entire system to ensure that signs are provided and maintained in accordance with GO 95, Section 79.5 requirements and replace/re-label the "Danger Electric Third Rail Keep Away" signs where needed. 2. BART should survey the entire system and trim/eradicate vegetation/tree growing near the right-of-way where necessary. 3. BART should investigate the water leakage in the TPSS and take corrective action in accordance with GO 128, Section 30 requirements. The corrective action should also prevent future occurrence of the same problem.
| |||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
5 |
Element |
Third Rail Maintenance | ||||
Date of Audit
|
8/16/2006 |
Department |
Maintenance and Engineering Power/Mechanical Maintenance | ||||
Auditors / Inspectors |
Brian Yu |
Persons Contacted |
Randy Clark, BART Power and Mechanical Maintenance | ||||
REFERENCE CRITERIA | |||||||
Book 31: Electrical Maintenance Procedures, Chapter 1, Section 17 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will select a minimum of four separate sections of third rail and review the relevant maintenance inspection records to determine if: | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
1. Staff reviewed BART Third Rail Maintenance Annual Inspection records for the 5. Completion status of the Work Orders generated from the scheduled maintenance | |||||||
Comments: | |||||||
BART could benefit from using a computerized work tracking system instead of the current manual tracking method. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
6 |
Element |
Reporting and Investigating Accidents and Investigation Procedures | ||||
Date of Audit
|
8/15/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Claudia Lam |
Persons Contacted |
Ken Cook | ||||
REFERENCE CRITERIA | |||||||
Management Procedure 48, March 6, 2001
| |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will randomly select at least five accidents involving an injury or fatality reportable to the CPUC during the past 24 months and determine if:
| |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
Filed copies of five accident reports for the past 24 months were reviewed to determine the completeness of the investigation requirements. | |||||||
The accidents selected were: a) Pittsburg/Bay Point Station, August 20, 2006, b) Fruitvale Station Platform, October 25, 2004, c) San Leandro Station, August 26, 2005, d) Fruitvale Station, December 25, 2005, and e) Union City Station, May 15, 2006.
October 25, 2004 at 6:28 p.m. and was reported by October 26,2004 at 7:00 a.m.. reported by December 27, 2005 at 7:05 a.m. | |||||||
Comments: | |||||||
BART Chief Safety Officer addressed the above findings immediately by sending a memorandum, dated September 27, 2006, to BART staff. The memorandum emphasized that BART must notify CPUC of all immediately reportable events in compliance with CPUC GO 164-C. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
7 |
Element |
Review Operating Rules and Procedures Manual and Operating Bulletins | ||||
Date of Audit
|
8/14/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Gary Rosenthal |
Persons Contacted |
Ken Cook | ||||
REFERENCE CRITERIA | |||||||
Management Procedure 34, November 1, 1998 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will review the Operating Rules and Procedures Manual and Operating Bulletins to determine if: months and the process has been tracked. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
1. Management Procedure No. 34 addresses the development and control of BART operating 5. Management Procedure No. 34 requires an annual review of the BART Operating Rules and revised. | |||||||
6. Management Procedure No. 34 requires an annual review of the Supplementary be revised. establishing the criteria in which the bulletins are required to be revised. 10. BART has adopted the practice of reviewing and reissuing the Operating Bulletins at the beginning of each calendar year.
12. In March 2007, BART submitted a report describing the annual OR&P review that took place in January 2007. Findings/recommendations are divided into Priority 1 and Priority 2. There is no information that describes the qualification for Priority 1 or 2. However, the report implied that there is a structure to the review and analysis process. | |||||||
Comments: | |||||||
Staff supports BART's practice of reviewing the OR&P annually and completing revisions in a timely manner. Staff also supports BART's practice of reviewing, revising, and reissuing Operating Bulletins annually. | |||||||
Recommendations: | |||||||
1. BART should revise the appropriate control document to describe annual process, and how the process (such as making findings, reaching conclusions, and recommending actions... etc.) is documented.
|
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
8 |
Element |
Review Employee Safety Program | ||||
Date of Audit
|
8/16/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Georgetta Gregory |
Persons Contacted |
David L. Sanborn, Manager, Employee/Patron Safety | ||||
REFERENCE CRITERIA | |||||||
System Safety Program Plan (SSPP), Chapter 19 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditors will interview operations management and at least two safety committee employee representatives and review the employee safety program records to determine if: | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
1. Programs and policies contained in the IIPP have been utilized to implement Employee/Patron Safety Programs. The IIPP supersedes Management Procedure No. 61. 3. The required documentation to verify all employee-identified safety hazards during the past 18 months and addressed by the Safety Committee was insufficient and difficult to cross reference. | |||||||
4. Safety Committee meetings have been held monthly over the past 18 months. A summary | |||||||
Comments: | |||||||
The program is well administered and organized given the limitations of staffing and automation with high level of individual accountability. BART could benefit by implementing a fully automated and integrated process for data collecting and tracking to ascertain that all reported hazards are captured and evaluated, corrective actions are planned and completed, and that each item is closed by a single documentation package | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
9 |
Element |
Internal Safety Audit Program | ||||
Date of Audit
|
8/17/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Gary Rosenthal |
Persons Contacted |
Ken Cook | ||||
REFERENCE CRITERIA | |||||||
Management Procedure 60, January 28, 1998
| |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will review BART documents/records to determine if: annually. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
1. BART annual internal safety audit reports for 2003, 2004, and 2005 include the internal safety audits schedules and performance. 2. Internal safety audit reports indicate that each of the APTA Safety program 3. Internal safety audits were performed according to the schedules submitted to |
4. Internal safety audit reports indicate that CPUC staff was frequently present to observe
6. The Emergency Response Planning, Coordination, and Training, the System 2003, 2004, and 2005. 12. In March 2007, BART submitted additional information demonstrating that, in at least one Instance, the auditor was not independent from the first line of supervision responsible for performing the activity being audited. | |||||||
Comments: | |||||||
Staff suggests that BART use the internal safety audit process to more actively and thoroughly monitor interdepartmental and interagency coordination programs, processes, and procedures. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
11 |
Element |
Safety and Security Certification Plan (Warm Springs Extension) | ||||
Date of Audit
|
8/16/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Raed Dwairi |
Persons Contacted |
Len Hardy, Chief Safety Officer | ||||
REFERENCE CRITERIA | |||||||
Safety and Security Certification Plan (SSCP) - Warm Springs Extension | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will interview management and review documentation to determine if the SSCP of the Warm Springs Extension: | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
1. BART has a Safety and Security Certification Plan for the Warm Springs Extension Project dated October 27, 2005.
and responsibilities in Sections 1.1, 1.5, and Chapter 3.0. 3. The SSCP addresses the controls used to maintain effective communications and liaison With staff throughout the life of the project by requiring the Safety Department to coordinate | |||||||
4. The SSCP identifies the process used to verify and document conformance with safety and address the identified recommendations. Certificates of Conformance are utilized for the verification of safety and security requirements. Safety Criteria Variances are reviewed and approved/disapproved by the Safety Department. Operational readiness is verified and a Notice of Intent to Operate is endorsed by the General Manager and issued to the CPUC. | |||||||
Comments: | |||||||
None. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | ||||||||||||
BAY AREA RAPID TRANSIT | ||||||||||||
Checklist No.
|
12 |
Element |
Hazardous Materials Management Program | |||||||||
Date of Audit
|
8/15/2006 |
Department |
System Safety | |||||||||
Auditors / Inspectors |
Anton Garabetian |
Persons Contacted |
David L. Sanborn, Manager, Environmental, Health, and Safety | |||||||||
REFERENCE CRITERIA | ||||||||||||
System Safety Program Plan (SSPP), Chapter 20 | ||||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | ||||||||||||
The auditors will interview BART department managers to determine if hazardous materials are being handled properly. The auditors will also review procedures and records to determine if: explained clearly. Safety Department. and cleanup of spill incidents. | ||||||||||||
ACTIVITIES/RESULTS/COMMENTS | ||||||||||||
Findings: |
||||||||||||
Staff interviewed BART Safety Department management in charge of the Hazardous Materials Management Program and the Hazard Communication Program. Staff also reviewed material safety data sheets (MSDS) and a list of employees that have been trained on the Hazardous Material Management Program. Staff inquired about the CIMAGE computer program used by the Safety Department. | ||||||||||||
1. BART does not procure insecticides or herbicides, but hire contractors to perform the necessary service. The procurement process for chemicals and solvent is very clear and all procurement requests are evaluated and approved by the Safety Department. MSDS System. also posted on the BART Intranet so that all departments have access to MSDS and the accompanying safety instructions for each chemical. and cleanup of spill incidents. BART location. | ||||||||||||
Comments: |
||||||||||||
Staff suggests that the Safety Department keeps a list of every chemical available in each department and be made available for emergency responders in case of a disaster. | ||||||||||||
Recommendations: | ||||||||||||
None. | ||||||||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
13 |
Element |
Data Acquisition Analysis | ||||
Date of Audit
|
8/16/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Claudia Lam |
Persons Contacted |
Ken Cook | ||||
REFERENCE CRITERIA | |||||||
APTA Guidelines Element 16 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditors will interview BART representative in charge of safety data acquisition and analysis. The auditors will also review the safety data acquisition and analysis program requirements, records, and reports to determine if: contributing to failures, accidents/incidents involving fatalities, accidents/incidents involving injuries, accidents/incidents resulting in property damage, and accident/incidents resulting in environmental damage. Management. for use in planning their safety-related activities. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
1. The System Safety Department produces three primary reports covering the following
2. Source of inputs:
3. Staff reviewed the following documents:
| |||||||
Comments: | |||||||
The program is well administered and organized given the limitations of staffing and automation with high level of individual accountability. | |||||||
Recommendations: | |||||||
None. | |||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
14 |
Element |
Emergency Response Planning and Training | ||||
Date of Audit
|
8/15/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Gary Rosenthal |
Persons Contacted |
John McPartland, Operations Safety | ||||
REFERENCE CRITERIA | |||||||
BART Emergency Plan, November 2002 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will interview the Safety Manager/Chief and review records and documentation for the past 18 months to determine if: agencies in the last three years. Agency Familiarization Program. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
1. BART conducts quarterly Fire Life Safety Committee meetings with fire departments in | |||||||
4. Records indicate that there were numerous tabletop exercises, emergency drills, departments in the various districts where BART operates. Other emergency responders also participate in the emergency drills. deficiencies effecting BART are identified and reviewed by the participants, there is no record that corrective actions are established and tracked and the deficiencies corrected. | |||||||
Comments: | |||||||
None. | |||||||
Recommendations: | |||||||
1. BART System Safety Program Plan should identify or reference all of the respective interdepartmental and interagency coordination programs, processes, and procedures, including the Fire Life Safety Committee (See Checklist No. 10). |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
15 |
Element |
Drug and Alcohol Testing Program | ||||
Date of Audit
|
8/15/2006 |
Department |
Administration Human Resources / Employee Services | ||||
Auditors / Inspectors |
Georgetta Gregory |
Persons Contacted |
Margaret Saget | ||||
REFERENCE CRITERIA | |||||||
BART Substance Abuse Program 2000 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditors will review records and documents to determine if:
2. The number of employees in safety sensitive positions were tested positive (or refused to take a test) during the past 3 years:
| |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
Staff interviewed BART personnel regarding the BART Substance Abuse Program, dated May 2006 and reviewed records of employee testing and statistics for the last three years. Staff also reviewed training documentation and the 2006 contractor substance abuse testing records to determine their compliance with current FTA guidelines. 3. There are approximately 1,500 safety sensitive BART employees and approximately 70 substance abuse tests performed each month. | |||||||
4. The results of the 3,679 substance tests during the past three years include 28 positive tests, which is less than one percent of employees tested. The positive results occurred in the following tests:
units. rosters include the starting and end times of the training. 10. BART uses a database to maintain substance abuse testing records on safety sensitive 11. Staff reviewed the Post-Accident Incident Log and determined that it provides adequate documentation. documentation and found it to be adequate in documenting non-compliances. are related to compliance with the Federal Transit Administration (FTA) spacing of testing throughout the month. One contractor was identified with insufficient staff to oversee the process, which was rectified by training additional personnel in drug program administration duties. Non-compliant contractors are terminated by BART. 14. BART records were generally well maintained and organized. completing the program. | |||||||
Comments: | |||||||
None. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
16 |
Element |
Security Program - BART Police and Security Audits | ||||
Date of Audit
|
8/16/2006 |
Department |
BART Police Department | ||||
Auditors / Inspectors |
Georgetta Gregory |
Persons Contacted |
Captain Gary Gee | ||||
REFERENCE CRITERIA | |||||||
System Security Program Plan, January 1, 1998 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will Interview BART personnel and review record checks for the past three years to determine if: have been distributed to all department command staff. targets and areas of improvements. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
Staff interviewed BART personnel and reviewed the following documentations:
Livermore National Laboratory in November 2005 completion. 3. BART Police Crime Analysis: system. During this interim period, quarterly reports have been prepared and were reviewed by staff for Fiscal Year (FY) 2006. Reports are distributed via e-mail to supervisors. c. BART Police had 12,250 calls in the third quarter of FY 2006 with a 4.34 minutes response time. During the fourth quarter there were 11,961 calls with a 3.75 minutes response time. BART police goal is to respond within four minutes. e. Crimes per million trips, referred to as quality of life violations, have decreased since the 2006 and 55 in the fourth quarter. These crimes equate to 1.76 crimes per million FY 2006 exceeded the goal of eight, with ten being reported in the third quarter and fourth quarters consecutively. A total of 476 auto theft and burglary crimes were reported in the third quarter of FY 2006 and 523 were reported in the fourth quarter. audits identified potential terrorist targets and recommended corrective actions. | |||||||
Comments: |
|||||||
The Transportation Safety Administration (TSA) conducted a review of BART System Security Plan and threat and vulnerability assessment process simultaneously with staff during the completion of this checklist. Those findings are documented in a classified document and are not part of this report. Refer to TSA Executive Summary in Appendix A. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
17 |
Element |
Train Operator, Line Supervisor, and Central Control Supervisor Training and Recertification | ||||
Date of Audit
|
8/18/2006 |
Department |
Operations Training and Support Transportation | ||||
Auditors / Inspectors |
Gary Rosenthal |
Persons Contacted |
Ken Cook | ||||
REFERENCE CRITERIA | |||||||
BART Employee Certification Plan, 1986 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will randomly select at least six BART employees in each of the following classifications: 1. Train operator 2. Operation Control Center (OCC) Supervisor 3. Line Supervisor 4. Yard Supervisor The auditor will also review training and recertification records for the above employees for the past three years to determine if: | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: 1. The records of seven arbitrarily selected OCC Supervisors, including one OCC Manager, disclosed that they all had completed the initial training and certification program and the required recertification programs. | |||||||
2. The OCC Supervisor training program is comprehensive and requires certification as a Train Operator and as a Power Controller. 3. The OCC Supervisor training program is administered separately from the other operations training programs. BART personnel stated that there are informal efforts to ensure that the training programs are compatible. 4. The records of six randomly selected Train Operators disclosed that they all had completed program. | |||||||
Comments: | |||||||
Staff suggests that BART consider establishing a formal integration procedure to ensure the OCC Supervisor training program and other operations training programs are compatible. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | ||||||||||||
BAY AREA RAPID TRANSIT | ||||||||||||
Checklist No.
|
18 |
Element |
Hours of Service of Train Operators, Train Controllers, and Tower Fore Workers | |||||||||
Date of Audit
|
8/14/2006 |
Department |
Transportation | |||||||||
Auditors / Inspectors |
Anton Garabetian |
Persons Contacted |
Kathy Gilbert, Group Manager, Operations Support and Review Transportation | |||||||||
REFERENCE CRITERIA | ||||||||||||
Operations Control Center (OCC) Manual, Rev 14 2005 - 2009 | ||||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | ||||||||||||
The auditor will randomly select six employees from the following safety sensitive job classifications: | ||||||||||||
ACTIVITIES/RESULTS/COMMENTS | ||||||||||||
Findings: | ||||||||||||
Staff reviewed working hour records prepared during a three-month period in the past 18 months for six Train Operators and six Fore Workers. Staff also reviewed working hour records prepared during a one-month period in the past 18 months of one Operations Control Center (OCC) Manager, two Train Controllers, one Communications Specialist, and one Power and Support Controller as follows: 1. Working hour records of six Train Operators from July 18 to November 6, 2005 did not show any discrepancy. discrepancy. any discrepancy. any discrepancy. not show any discrepancy. show any discrepancy. | ||||||||||||
Comments: | ||||||||||||
None. | ||||||||||||
Recommendations | ||||||||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||||||||
BAY AREA RAPID TRANSIT | |||||||||||||
Checklist No.
|
19 |
Element |
Calibration of Measuring and Testing Equipment | ||||||||||
Date of Audit
|
8/10/2006 |
Department |
Rolling Stock and Shops | ||||||||||
Auditors / Inspectors |
Joey Bigornia |
Persons Contacted |
Charles Sewchok, | ||||||||||
REFERENCE CRITERIA | |||||||||||||
Book 15: Quality Assurance Manual, Chapter 17, Section 1, February 29, 1998 | |||||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||||||||
The auditor will select five different items on the list of equipments that require calibration and review their documentation and inspect the equipment to determine if: certified standards at the prescribed intervals. | |||||||||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||||||||
Findings: |
|||||||||||||
1. Staff interviewed the BART manager in charge of the calibration program for shop measuring
| |||||||||||||
c. Dial Calipers
3. Staff reviewed copies of the Calibration Data Sheets and Certificates to confirm equipments selected for review were calibrated within the required annual frequency. 4. BART's electronic equipment is calibrated by SE Laboratories annually.. listed above had a calibration sticker affixed showing the last date and the next scheduled date of calibration. No exceptions were noted. 6. Copies of the Calibration Data Sheets and Certificates for all equipment listed above were were noted. | |||||||||||||
Comments: | |||||||||||||
None. | |||||||||||||
Recommendations: | |||||||||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR |
||||||||||||
BAY AREA RAPID TRANSIT | ||||||||||||
Checklist No.
|
20 |
Element |
Track Inspection and Turnout Inspection Records | |||||||||
Date of Audit
|
8/8/2006 |
Department |
Maintenance and Engineering Way and Facilities Maintenance | |||||||||
Auditors / Inspectors |
Joey Bigornia |
Persons Contacted |
Tom Delaney, Section Manager | |||||||||
REFERENCE CRITERIA |
||||||||||||
Track Standards Manual, June 1, 1995 | ||||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | ||||||||||||
Track Inspection: The auditor will: to determine if:
timely manner. three years to determine if:
timely manner.
the running rails. timely manner. The auditor will also review BART track inspection reports for at least two separate periods during the last three years to determine if: manner. | ||||||||||||
ACTIVITIES/RESULTS/COMMENTS | ||||||||||||
Findings: |
||||||||||||
1. Staff interviewed the Section Manager in charge of the under-car deluge system inspection 2. Staff reviewed the following documents to determine if the tracks were inspected by hi-rail vehicle:
line (L1, L2), and R-line (R1, R2) were inspected by a geometry car:
testing:
6. The inspections by hi-rail vehicle were performed at the required frequency interval. Noted defects were closed out in a timely manner. explained that the geometry car was not available for performing the inspection since it was undergoing an engine rebuild. the inspection frequency interval. | ||||||||||||
Comments: | ||||||||||||
None. | ||||||||||||
Recommendations: | ||||||||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | ||||||||||||
BAY AREA RAPID TRANSIT | ||||||||||||
Checklist No.
|
21 |
Element |
Exclusive Right-Of-Way Fence Inspection Records | |||||||||
Date of Audit
|
8/14/2006 |
Department |
Maintenance and Engineering Way and Facilities Maintenance | |||||||||
Auditors / Inspectors |
Brian Yu |
Persons Contacted |
Mark Chan | |||||||||
REFERENCE CRITERIA | ||||||||||||
Fencing Inspection Procedure
| ||||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | ||||||||||||
The auditors will review the fence inspection reports prepared during the past 18 months to determine if: observation. | ||||||||||||
ACTIVITIES/RESULTS/COMMENTS | ||||||||||||
Findings: | ||||||||||||
1. Staff reviewed BART Right-of-Way Barrier Inspection Report Forms from January 2005 to August during and after the records review. 5. Certain inspection records were incomplete and corrective action completion could not be confirmed. 6. Although the inspection form has supervisor's signature requirement for reviewing the inspection
only after the repair work has been completed, some would list repair works needed without signatures, and some would list inspection findings and repair works without signatures. | ||||||||||||
Comments: |
||||||||||||
BART Maintenance and Engineering Department does not have a computerized system to track the status of repair works. BART could benefit from having a computerized work tracking system to follow up on the status of open work orders. | ||||||||||||
Recommendations: |
||||||||||||
BART should ensure that their fore workers and supervisors properly document the inspection, corrective actions, and completion status of the corrective actions to allow efficient and effective follow-up. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
22 |
Element |
Transit Vehicle Maintenance | ||||
Date of Audit
|
8/15/2006 |
Department |
Rolling Stock and Shops | ||||
Auditors / Inspectors |
Anton Garabetian |
Persons Contacted |
Mike Turner, Assistant Shop Superintendent | ||||
REFERENCE CRITERIA | |||||||
Book 50: C Car Maintenance Procedures, Volume 14
| |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will select three A cars, three B cars and three C cars from the Richmond shop to review the completed Preventive Maintenance (PM) records associated with each car selected to determine if: frame during the past three years. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
1. Staff reviewed the preventive maintenance inspection records at the Richmond Yard shop for:
| |||||||
2. Staff reviewed maintenance mileage record of the following cars between 2003 and 2006:
3. Preventive maintenance were performed within the required time frame in the past three years. 5. Noted discrepancies were corrected in a timely manner. 15, 2003, for the purpose of equalizing wheel flange wear. | |||||||
Comments: | |||||||
None. | |||||||
Recommendations: | |||||||
None. | |||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR |
||||||||||||||
BAY AREA RAPID TRANSIT |
||||||||||||||
Checklist No.
|
23 |
Element |
Quality Assurance of Transit Vehicles |
|||||||||||
Date of Audit
|
8/14/2006 |
Department |
Rolling Stock and Shops |
|||||||||||
Auditors / Inspectors |
Raed Dwairi |
Persons Contacted |
Charles Sewchok, Quality Assurance Manager |
|||||||||||
REFERENCE CRITERIA |
||||||||||||||
Book 15: Quality Assurance Manual |
||||||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION |
||||||||||||||
The auditors will randomly select three B cars and four C car from the Richmond Yard shop and review their quality assurance records for six months in the past year to determine if:
year has been tracked to completion. |
||||||||||||||
ACTIVITIES/RESULTS/COMMENTS |
||||||||||||||
Findings: |
||||||||||||||
1. For the cars selected at the Richmond Yard Shop (B cars: 1551, 1562, and 1567, 2. For selected cars 365, 413, 429, 2529, 2544 and 2558, the 600-hr inspection records obtained through the Maintenance and Reliability Information System (MARIS) for the past three years (August 1, 2003 to August 13, 2006,) indicated that the Quality Assurance process was followed as required. None of the selected cars exceeded the 50-hour window beyond the 600-hour mark. |
||||||||||||||
3. The above records include the inspection results, both regular and unscheduled, for all cars make up about 1% of the transit vehicles maintained by the Richmond Yard. |
||||||||||||||
Comments: |
||||||||||||||
None. |
||||||||||||||
Recommendations: |
||||||||||||||
BART should review its applicable Quality Assurance (QA) procedures which pertain to the use of QA stamps to achieve consistency between Car History Books and archived files. |
||||||||||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
24 |
Element |
Train Control Equipment Inspection and Tests | ||||
Date of Audit
|
8/15/2006 |
Department |
Maintenance and Engineering: | ||||
Auditors / Inspectors |
Raed Dwairi |
Persons Contacted |
Edward Pomposo, Section Manager, Systems Maintenance | ||||
REFERENCE CRITERIA | |||||||
BART computer program - DataStream Joint Switch and Turnout and Inspection Checklist
| |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
1. The auditor will randomly select three stations and review their inspection records of the station Multiplexer (MUX) to determine if: Track and Train Control Departments Joint - Switch, Turnout, and Interlocking Inspection Form" to determine if: | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
For the randomly selected Coliseum (A30), Montgomery (M20), and El Cerrito Del years 2004, 2005, and 2006 were performed as required. Annual inspection dates obtained · A30: April 16, 2004, October 16, 2005, and April 16, 2006 | |||||||
2. Two Trouble Tickets associated with Multiplexer (MUX) inspections were not closed out in a W45-SM151 remained open since May 2004.
Joint Switch, Turnout, and Interlocking Inspection Forms were performed during the years 2004, 2005, and 2006. Documentation was properly prepared and signed by the Track and Train Control representatives. | |||||||
Comments: | |||||||
None. |
|||||||
Recommendations: | |||||||
BART should follow up on open Train Control Equipment Trouble Tickets by generating a report listing the tickets, reasons behind the open status of those tickets, and a plan to resolve the issues and close the open tickets in a timely manner. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
25 |
Element |
Emergency Ventilation Fans and Associated Dampers | ||||
Date of Audit
|
8/16/2006 |
Department |
Maintenance and Engineering Power/Mechanical Maintenance | ||||
Auditors / Inspectors |
Raed Dwairi |
Persons Contacted |
Dean Giebelhausen, Section Manager, Power Mechanical | ||||
REFERENCE CRITERIA | |||||||
Book 4: Mechanical Maintenance Procedures, Volume 1, Chapters 1,2,3, and 4 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will randomly select four ventilation fans and associated dampers and review the | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
1. The selected 2004, 2005, and 2006 preventive maintenance records for the Emergency in a timely manner. The Mechanical portion of the inspections were as follows: | |||||||
The electrical portion of the inspections were as follows: incomplete. | |||||||
Comments: | |||||||
While no exceptions were noted and the program has continue to show improvements since previous CPUC Audits, the program could be further improved by implementing a Quality Assurance component similar to the one utilized by transit vehicle maintenance. | |||||||
Recommendations: | |||||||
None. | |||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
26 |
Element |
Vital Relays | ||||
Date of Audit
|
8/15/2006 |
Department |
Maintenance and Engineering Power/Mechanical Maintenance | ||||
Auditors / Inspectors |
Raed Dwairi |
Persons Contacted |
Dan Stevenson, Section Manager, Systems Maintenance | ||||
REFERENCE CRITERIA | |||||||
BART computer program - DataStream | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will review the records of vital relay inspections in the last three years to determine if: criteria. The auditor will also conduct a field inspection of two relays to determine if the measured pick- up and drop-away voltages are within acceptable limits specified in the reference criteria. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: | |||||||
1. Vital relays were inspected as required for 2003, 2004, 2005, and 2006. Inspections have been properly documented in DataStream. Relay PM schedules and assignments for 2005 and 2006 indicated that all inspections were on schedule. | |||||||
Comments: | |||||||
None. |
|||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||||||
BAY AREA RAPID TRANSIT | |||||||||||
Checklist No.
|
27 |
Element |
Fire Alarms and Sprinkler Systems | ||||||||
Date of Audit
|
8/15/2006 |
Department |
Maintenance and Engineering Power/Mechanical Maintenance | ||||||||
Auditors / Inspectors |
Brian Yu |
Persons Contacted |
John McPartland | ||||||||
REFERENCE CRITERIA | |||||||||||
Book 31, Volume 5, Chapter 8, CCR Title 19 | |||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||||||
The auditor will randomly select one aerial station, one at-grade station, and one subway station. The auditor will also review the corresponding fire alarm and fire sprinkler system inspection, testing, and maintenance records to determine if: inspections were properly documented and noted discrepancies were corrected in a timely manner. specified in the referenced procedure. The inspections, testing, or maintenance were properly documented and noted discrepancies were corrected in a timely manner. | |||||||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||||||
Findings: | |||||||||||
1. Staff selected the following locations to conduct the records review:
2. Staff reviewed Annual and Semi-annual Fire Alarm Preventive Maintenance inspection records for the selected locations. records review.
and repairs with no supervisory verification needed. to track the status of open work orders. | |||||||||||
Comments: | |||||||||||
BART could benefit by implementing a computerized work tracking system to efficiently track the status of open work orders | |||||||||||
Recommendations: | |||||||||||
None. | |||||||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | ||||||||||||
BAY AREA RAPID TRANSIT | ||||||||||||
Checklist No.
|
28 |
Element |
1) Wet Stand Pipe, 2) Sprinkler Systems, and 3) Line Pumps | |||||||||
Date of Audit
|
8/15/2006 |
Department |
Maintenance and Engineering Power/Mechanical Maintenance | |||||||||
Auditors / Inspectors |
Brian Yu |
Persons Contacted |
Mark Chan | |||||||||
REFERENCE CRITERIA | ||||||||||||
Book 4: Mechanical Maintenance Procedures, Volume 3, Chapter 1, CCR Title 19 | ||||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | ||||||||||||
The auditor will review the wet pipe sprinkler systems testing records and the line pumps maintenance inspection records to determine if: discrepancies were corrected in a timely manner. properly documented and noted discrepancies were corrected in a timely manner. | ||||||||||||
ACTIVITIES/RESULTS/COMMENTS | ||||||||||||
Findings: | ||||||||||||
1. Staff reviewed Stand Pipe Inspection records for the following locations:
2. Staff reviewed Sump Pump Inspection records for the following locations:
| ||||||||||||
3. Staff interviewed the BART Section Manager during and after the inspection records review. documented. | ||||||||||||
Comments: |
||||||||||||
None. |
||||||||||||
Recommendations: | ||||||||||||
None. | ||||||||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
29 |
Element |
Under-Car Deluge System | ||||
Date of Audit
|
8/9/2006 |
Department |
Maintenance and Engineering Power/Mechanical Maintenance | ||||
Auditors / Inspectors |
Joey Bigornia |
Persons Contacted |
Randy Clark, Superintendent | ||||
REFERENCE CRITERIA | |||||||
Book 31, Chapter 2, Section 5 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will randomly select four underground stations and review the corresponding under-car deluge system maintenance inspection records to determine if: timely manner. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
1. Staff interviewed the Section Manager in charge of the under-car deluge system inspection 2. Staff also reviewed the dated documents of the following stations to determine if the corresponding under-car deluge systems were inspected on a quarterly basis: | |||||||
3. Staff reviewed the dated documents of the following stations to determine if the corresponding under-car deluge systems were inspected every five years as required by Title 19: 4. Staff reviewed the quarterly and five-year inspection records for the M20, M30, W20, W30, Y10, R30, C70, and A10 under-car deluge which indicated that the inspections were performed at the required frequency intervals. Manager, and closed out from the inspection records in a timely manner. | |||||||
Comments: | |||||||
None. | |||||||
Recommendations: | |||||||
None. | |||||||
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | ||||||||||
BAY AREA RAPID TRANSIT | ||||||||||
Checklist No.
|
30 |
Element |
Gap Breakers and Wayside Equipment | |||||||
Date of Audit
|
8/9/2006 |
Department |
Maintenance and Engineering Power/Mechanical Maintenance | |||||||
Auditors / Inspectors |
Joey Bigornia |
Persons Contacted |
Randy Clark, Superintendent | |||||||
REFERENCE CRITERIA | ||||||||||
Book 31, Chapter 1, Section 1 | ||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | ||||||||||
The auditor will randomly select four Gap Breaker Stations and review the corresponding maintenance inspection records to determine if: | ||||||||||
ACTIVITIES/RESULTS/COMMENTS | ||||||||||
Findings: | ||||||||||
1. Staff reviewed the following documents of the following gap breakers to determine if they have been inspected monthly:
been inspected semi-annually:
| ||||||||||
3. Staff reviewed the following documents of the following gap breakers to determine if they have been inspected annually:
| ||||||||||
Comments: | ||||||||||
None. | ||||||||||
Recommendations: | ||||||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||||||
BAY AREA RAPID TRANSIT | |||||||||||
Checklist No.
|
31 |
Element |
Signal Maintenance Training and Certification | ||||||||
Date of Audit
|
8/17/2006 |
Department |
Operations Training and Development Maintenance | ||||||||
Auditors / Inspectors |
Raed Dwairi |
Persons Contacted |
Deslar (Des) Patten, Employee Development Specialist | ||||||||
REFERENCE CRITERIA | |||||||||||
BART Employee Certification, January 2005 | |||||||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||||||
The auditor will interview the signal maintenance training representatives and review the training and certification record of two randomly selected employees, from each Train Control Technician Training Maintenance classification, to determine if: | |||||||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||||||
Findings: | |||||||||||
1. The record of a selected Train Control Maintenance Technician indicated that the employee failed the Vital Processor Interlocking (VPI) Hardware Recertification test on September 29, 2005 and did not attend the April 17, 2006 General Railway Signal (GRS) VPI Hardware Certification training course. 2. No documentation was found to explain the employee's failure to attend the | |||||||||||
3. Training, certification, and refresher training records are complete and in compliance with employees who are past due, never certified, failed certification test, due for certification in three months, six months, and in more than six months. Another matrix shows certification classes needed as of August 10, 2006 to easily identify training needs and schedule classes accordingly. and those who cancelled their registration. However, the roster did not provide an explanation of their cancellation. | |||||||||||
Comments: | |||||||||||
None. | |||||||||||
Recommendations: | |||||||||||
BART should ensure that Train Control Technicians who failed their recertification test are not working on equipment requiring their success in being recertified. BART should have proper documentation explaining the technician's failure to be recertified. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
32 |
Element |
Contractor Safety Coordination | ||||
Date of Audit
|
8/14/2006 |
Department |
System Safety Operations Liaisons Transit System | ||||
Auditors / Inspectors |
Anton Garabetian |
Persons Contacted |
Len Hardy, Chief Safety Officer | ||||
REFERENCE CRITERIA | |||||||
Operating Bulletins | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditor will interview the BART representative responsible for the Contractors Safety Program and review applicable documentation to determine if: responsible to comply with BART's safety rules and procedures. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
Staff interviewed BART Chief Safety Officer and Safety Manager to confirm BART's implementation of Contractor Safety Program (CSP). The staff also reviewed two contract documents for the following projects to confirm the inclusion of CSP in new construction or capital projects: 1. The Operations Rules and Procedures Manual, which includes sections on contractor | |||||||
2. BART Facilities Standards, Standard Specifications, and Operating System Interface, which | |||||||
Comments: | |||||||
None. | |||||||
Recommendations: | |||||||
None. |
2006 CPUC SYSTEM SAFETY AUDIT CHECKLIST FOR | |||||||
BAY AREA RAPID TRANSIT | |||||||
Checklist No.
|
33 |
Element |
Review Operations Safety Compliance Program | ||||
Date of Audit
|
8/21/2006 |
Department |
System Safety | ||||
Auditors / Inspectors |
Gary Rosenthal |
Persons Contacted |
Ken Cook, Len Hardy, Tamar Allen, Richard Leonard, Ron Cook, Richard Rounke, and Rudy Crespo | ||||
REFERENCE CRITERIA | |||||||
Management Procedure 84 | |||||||
ELEMENT/CHARACTERISTICS AND METHOD OF VERIFICATION | |||||||
The auditors will review Operations Safety Compliance Program to determine if: 3. Employees are evaluated based on their performance on unannounced safety compliance exercises to determine their compliance with the standard of safety rules, procedures, and/or practices. | |||||||
ACTIVITIES/RESULTS/COMMENTS | |||||||
Findings: |
|||||||
1. The requirements of the Operations Safety Compliance Program Procedure 84.0, effective as of September 1, 2003, are included in the Transportation and System Service Department Operations Safety Compliance Plan, the Maintenance and Engineering Department Operations Safety Compliance Plan, the Operations Safety Compliance Program RS&S Plan, and the Operations Safety Compliance Program Operations Liaisons. 2. Each of the above procedures has a "Safety Aspects Covered" section, a "Safety Aspects to be covered" section, or a "Safety Aspects to be covered by the Plan" section. There was no clear evidence that every bulleted item in these sections have been addressed by the checklists. There also appear to be lacking a plan to address all of the procedural requirements. 3. The Operations Safety Compliance Program established by BART Management Procedure Number 84, effective as of September 1, 2003, is not addressed or referenced in the SSPP. 4. BART Rolling Stock and Shops has developed, adopted, and implemented its operations safety compliance program. | |||||||
5. BART Transportation Department, BART Maintenance and Engineering Department, and BART Operations Liaisons have developed and adopted safety compliance programs, but have not implemented these programs. 6. Al four of the program plans base evaluations of employee performance on unannounced safety compliance observations to confirm their compliance with safety rules, procedures, and practices. BART requires controllers to periodically listen to taped BART operations radio communication to verify compliance with operating and communications rules and procedures. | |||||||
Comments: | |||||||
1. Automation of the checklists would allow for collection of metric data and to better ensure would verify that the procedure is being performed and could also be used to identify deficiencies in operating and communication rules compliance. | |||||||
Recommendations: |
|||||||
BART should implement the Operations Safety Compliance Program plans for the Transportation Department, BART Maintenance and Engineering Department, and BART Operations Liaisons. |