Conclusion of Law

The application should be granted as set forth in the following order.

ORDER

IT IS ORDERED that:

1. Alameda Corridor Transportation Authority (ACTA) is authorized to construct three ACTA tracks and two storage tracks underneath the proposed Del Amo Boulevard Grade Separation Structure, identified as crossing 114-12.40-A, in Los Angeles County, as set forth in Appendix A, and as more fully described and indicated by text and plans attached to the application.

2. Construction and maintenance of the crossings shall be in accordance with the provisions of General Order (GO) 72-B.

3. Clearances shall be in accordance with GO 26-D. Walkways shall conform to GO 118. Walkways adjacent to any trackage subject to rail operations shall be maintained free of obstructions and shall be promptly restored to their original condition in the event of damage during construction.

4. Construction and maintenance costs shall be borne in accordance with an agreement entered into between parties. A copy of the agreement shall be filed by ACTA with the Commission's Rail Safety and Carriers Division prior to commencing construction.

5. Within 30 days after completion of the work under this order, ACTA shall notify the Commission in writing that the authorized work was completed.

6. This authorization shall expire if not exercised within three years unless time is extended or if the above conditions are not complied with. Authorization may be revoked or modified if public convenience, necessity, or safety so require.

7. The application is granted as set forth above.

8. Application 00-12-036 is closed.

LORETTA M. LYNCH

President

HENRY M. DUQUE

RICHARD A. BILAS

CARL W. WOOD

GEOFFREY F. BROWN