Pulsifer Ruling Incorporating Report And Letter Into The Record And Providing For Comments Thereon
Word Document PDF Document

Departing Load 2001-2005 CRS Obligations

(1) DWR Bond Charge. The actual amount of this charge for DA customers shall be computed and implemented through a separate decision in the Bond Charge Phase of A.00-11-038 et al. Implementation of the Bond Charge applicable to DA customers will become effective only after any legal challenges of the decision have been exhausted, as explained in the Bond Charge decision.

(2) DWR power charge covering DA customers' share of procurement costs between September 21, 2001 and December 31, 2002, representing DA customers' share of the uneconomic portion of DWR costs incurred after DA suspension but prior to the implementation date for the instant order.26

(3) DWR power charge applicable to prospective costs for calendar year 2003, representing DA customers' share of the uneconomic portion of prospective DWR costs. The principles and criteria underlying the determination of DA cost responsibility for this component shall be determined as prescribed in this order.

(4) A separate charge to cover the ongoing above-market portion of utility-related generation costs, as we explain in further detail below.27 (D.02-11-022, at p. 4.)

1 Merced Irrigation District and Modesto Irrigation District take no position regarding any portion of this Report that addresses calculation of the Competition Transition Charge (CTC) or anything related to calculation of CTC. On November 23, 2005, Merced Irrigation District and Modesto Irrigation District filed a Petition for Writ of Review of Commission Decision Nos. 05-01-031, 05-02-040, 5-10-046, and 05-10-047 in the California Court of Appeal, Fifth Appellate District (No. F049265) (Petition). Merced Irrigation District and Modesto Irrigation District cannot and will not make any statement or take any position with respect to this Report that might later be taken as contrary to any position taken or argument presented in that Petition. Merced Irrigation District and Modesto Irrigation District expressly disclaim any intent to take any such position in this Report, and hereby reserve all rights in that regard.

2 A December 23, 2004 Ruling of the Presiding Administrative Law Judge initiated the process to implement billing and collection relating to cost responsibility surcharges for MDL. Three issues were identified for resolution: (1) identifying customers and measuring usage for MDL CRS; (2) administration of the Commission authorized CRS exemptions; and (3) the need for and level of a MDL CRS cents per Kwh cap. The second of these issues is addressed in this report, while the third does not appear to remain an issue. The first issue, now that this report has resolved calculation issues, may be addressed in the pending advice letters that the IOUs have submitted (or will submit) regarding billing of DL customers.

3 For 2006 only, futures values from November 15th - December 15th were used.

4 See computational example in Appendix 1C.

5 The Total Portfolio Adjustment would not apply for year 2003 as, in accordance with Commission Decision 05-01-040, issued in this Rulemaking proceeding in January 2006, the CTC rate for 2003 has been set at $0.00.

6 See Part I of the Energy Division's April 18th, 2005 "Status Report To ALJ Pulsifer on MDL CRS Billing And Collection Bilateral Negotiations and First Meeting of DA/ MDL CRS Calculation Working Group":

7 See computational example in Appendix 1A. This example was prepared by DL parties. No other Working Group participants have disputed its accuracy.

8 If the decision in an IOU's General Rate Case or similar base revenue requirement proceeding changes that utility's generation revenue requirement by more than 2% in mid-year, the utility shall file an advice letter to update the DA CRS to reflect that change in generation base revenue requirement. This adjustment is necessary because generation base revenue requirements are not trued up to actual costs in the same manner as ERRA and DWR costs.

9 D.03-07-028, at 79, Ordering Paragraph 10 ("The MDL CRS shall be determined in accordance with the DA-in/out methodology on a total portfolio basis, as adopted for DA customers in D.02-11-022.").

10 See computational example in Appendix 1A. This example was prepared by DL parties. No other Working Group participants have disputed its accuracy.

11 See Footnote 1 (referencing the appeal of Modesto and Merced Irrigation Districts of the Commission's authorization of the use of the Statutory Method for the calculation of CTC)

12 These benchmarks represent the 30-day average, over the period from November 15, 2005 to December 15, 2005, of 12 month forward prices for 2006 at NP 15 and SP15, respectively, to which is added a "resource adequacy" amount of $4/MWH for PG&E and $8/MWH for SCE.

13 See computation example in Appendix 1B.

14 See computational example in Appendix 1C.

15 The Total Portfolio Adjustment would not apply for year 2003 as, in accordance with Commission Decision 05-01-040, issued in this Rulemaking proceeding in January 2006, the CTC rate for 2003 has been set at $0.00.

16 See D. 04-12-048

17 SDG&E prefers a gas futures-based benchmark and has not yet determined whether it will agree to a power futures-based benchmark.

18 Alternatives raised in the Working Group include use of a 60-day strip of forward prices or a selection of forward price indices from throughout the prior year.

19 Delivery six days a week (Monday through Saturday), 16 hours a day (7 am to 11 pm).

20 Note that the sample values provided in the text do not include the line loss adjustment.

21 Capacity/resource adequacy adders for 2006 have been negotiated as part of on-going workshop report discussions. Proposals have ranged from approximately $1.20/MWh-$9.60/MWh. The lower value of this range is based on PG&E's proposal to use the going-forward fixed cost needed to maintain a specific 300 MW steam unit on the PG&E system net of the energy benefit received from this unit. The higher value is based on CLECA, CMTA, and AReM's proposal to use the annual carrying cost of a combustion turbine.

22 Note that D.04-12-059 was clarified in D.05-07-038, which was issued after the January 2005 workshop.

23 EOY 2005 undercollection balances shown do not include bond charge undercollection balances.

24 EOY 2005 undercollection balances shown include bond charge undercollection balances.

25 In D.03-07-030, Finding of Fact #3, the Commission stated, "a reasonable criterion for purposes of preserving bundled customer indifference with respect to DA load migration is to ensure full payback of the DA CRS undercollection no later than the end of the DWR contract term expected to occur in 2011. In fact, the last DWR contract does not expire until 2015, but the vast majority of contracts expire by 2011.

26 The actual final amount of the DWR power charges shall be based on the specific forecast variables underlying the 2003 DWR revenue requirement that will be implemented in A.00-11-038 et al. proceedings.

27 In addition, DA customers in the SCE service territory currently pay a "Historic Procurement Charge" to SCE pursuant to D.02-07-032.

28 The total portfolio approach we adopt, involving the netting of high-cost URG against low-cost sources of power, is intended only for the express purpose of computing bundled ratepayer indifference during the period that DWR-related costs are being paid for through a DA CRS. Nothing in this order should be construed as creating any claim on low-cost URG by DA customers beyond the period covered by the DA CRS into perpetuity.

29 SCE also proposes to include the Independent System Operator (ISO) costs associated with the operation of this portfolio in this cost responsibility.

30 The parties have agreed to these benchmark prices for the sole purpose of setting the EOY 2005 DA CRS undercollection and they agree that these benchmark prices are not to be used as precedent in any other Commission proceeding.

31 Since the Edison TY 2006 GRC has yet to be decided by the Commission, Edison will file an advice letter to update the DA CRS calculation following the issuance of a final GRC Phase 1 decision if that decision results in a change in the generation revenue requirement of more than 2% from that reflected in the current calculation. A similar 2% update rule shall apply to future changes in the IOUs' generation base revenue requirements.

32 This negative 1.805 cent figure is expected to be affected by the update calculation referred to in FN 27 should the Commission adopt the ALJ's recommendation with respect to treatment of administrative A&G costs in Edison's TY 2006 GRC.

Top Of PageGo To First Page