Halligan Notice of Availability
Word Document PDF Document

ALJ/JMH/niz DRAFT Agenda ID # 5624

Decision DRAFT DECISION OF ALJ HALLIGAN (Mailed 4/25/2006)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Order Instituting Investigation to Facilitate Proactive Development of Transmission Infrastructure to Access Renewable Energy Resources for California

Investigation 05-09-005

(Filed September 8, 2005)

OPINION ON PROCEDURES TO IMPLEMENT THE COST RECOVERY PROVISIONS OF PUBLIC UTILITIES CODE SECTION 399.25

TABLE OF CONTENTS

OPINION ON PROCEDURES TO IMPLEMENT THE COST RECOVERY PROVISIONS OF PUBLIC UTILITIES CODE SECTION 399.25 11

I. Summary 22

II. Procedural History 44

III. Statutory Background 55

IV. Implementation of Section 399.25 99

V. Comments on Draft Decision 3131

VI. Assignment of Proceeding 3131

Findings of Fact 3131

Conclusions of Law 3232

INTERIM ORDER 3232

Attachment A - List of Acronyms and Abbreviations

I. Summary1

In this order, we evaluate and adopt specific policies and procedures to implement the cost recovery provisions of Pub. Util. Code § 399.25. Section 399.252 was enacted on September 12, 2002, as part of Senate Bill (SB) 1078,3 and is intended to facilitate California's use of renewable energy resources. Section 399.25 directs the Commission to deem necessary those transmission facilities identified in certificate applications if the proposed facilities are necessary to facilitate achievement of the State's renewable power goals. Section 399.25 also provides a "backstop" cost mechanism allowing the utilities to recover through retail rates any costs of the above facilities that are not approved by the Federal Energy Regulatory Commission (FERC) for recovery through transmission rates. Today's order clarifies how we intend to implement § 399.25 to provide the utilities and renewable resource developers with the cost recovery assurance to facilitate meeting the Renewable Portfolio Standard (RPS) goals. This decision adopts principles for implementing the requirements of § 399.25 that are in the public interest, because they will assist in our effort to ensure that California has the necessary transmission infrastructure in place in order to meet the RPS goals. The adopted principles are summarized below.

Requests for § 399.25 cost recovery for upgrades that do not meet the above criterion will be considered on a case-by-case basis in the applicable certificate proceeding.

In adopting these principles, this decision modifies certain findings previously adopted in D.03-07-033 to reflect our further consideration and subsequent events.

1 Attachment 1 explains each acronym or other abbreviation that appears in this decision.

2 All statutory references are to the Public Utilities Code unless otherwise stated.

3 (Stats. 2002, Ch. 516), adding Article 16 (California Renewables Portfolio Standard Program) to the Cal. Pub. Util. Code § 399.11, et seq. (2004) (SB 1078).

4 "Network" facilities are defined in FERC Order 2003 as "additions, modifications, and upgrades to the Transmission Provider's Transmission System required at or beyond the point at which the Interconnection Customer interconnects to the Transmission Provider's Transmission System to accommodate the interconnection of the Large Generating Facility to the Transmission Provider's Transmission System."

5 According to Order No. 2003 generation-tie facilities "include all facilities and equipment between the Generating Facility and the Point of Interconnection, including any modification, additions or upgrades that are necessary to physically and electrically interconnect the Generating Facility to the Transmission Provider's Transmission System. Interconnection facilities are sole use facilities and shall not include Distribution Upgrades, Stand Alone Network Upgrades or Network Upgrades."

6 Section 399.12 (a) of Article 16 defines an "Eligible renewable energy resource" as a facility that meets the definition of "in-state" renewable electricity generation facility in Section 25741 of the Public Resources Code.

Top Of PageNext PageGo To First Page