ALJ/RMD/avs Date of Issuance 6/4/2010

Decision 10-06-014 June 3, 2010

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

In the Matter of the Application of SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) for a Permit to Construct Electrical Facilities With Voltages Between 50kV and 200kV: Devers-Mirage 115 Kilovolt Subtransmission System Split Project.

Application 08-01-029

(Filed January 31, 2008)

DECISION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY
A PERMIT TO CONSTRUCT DEVERS-MIRAGE 115 KILOVOLT

SUBTRANSMISSION SYSTEM SPLIT PROJECT

TABLE OF CONTENTS

Title Page

DECISION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY A PERMIT TO CONSTRUCT DEVERS-MIRAGE 115 KILOVOLT SUBTRANSMISSION SYSTEM SPLIT PROJECT 22

Findings of Fact 2121

Conclusions of Law 2222

ORDER 2323

DECISION GRANTING SOUTHERN CALIFORNIA EDISON COMPANY
A PERMIT TO CONSTRUCT DEVERS-MIRAGE 115 KILOVOLT
SUBTRANSMISSION SYSTEM SPLIT PROJECT

1. Summary

This decision grants Southern California Edison Company a permit to construct the Devers-Mirage 115 Kilovolt Subtransmission System Split Project using the Proposed Project, as identified in the Environmental Impact Report.

As the Lead Agency for environmental review of the Proposed Project, we find that the Environmental Impact Report prepared for this project meets the requirements of the California Environmental Quality Act, Public Resources Code §§ 21000, et seq., and that there are overriding considerations that merit construction of the Proposed Project notwithstanding its significant and unavoidable environmental impacts on air quality.

The primary components of the Proposed Project include rearrangements and modifications of subtransmission line connections, construction of substation modifications in the Cities of Palm Springs, Rancho Mirage, Indian Wells, Cathedral City, Palm Desert, and unincorporated areas of Riverside County, including the Thousand Palms community, and minor modifications to existing telecommunications equipment at the Edom Hill Communications site and the Palm Springs Service Center. The Proposed Project includes two new 115 kilovolt (kV) subtransmission lines, seven 115 kV subtransmission/line reconfigurations, a 220 kV transmission line loop-in, substation modifications, and upgrades to telecommunications infrastructure. Implementation of the Proposed Project will split the existing Devers 115 Kilovolt Subtransmission System into two systems, the Devers 115 kV System and the Mirage 115 Kilovolt System.

This proceeding is closed.