Preliminary Schedule

Proceeding Milestone

Date

Ruling on Proposed Standardized Planning Assumptions

(shortly after OIR)

Comments due on Preliminary Scoping Memo

April 6, 2012

PHC

April 18, 2012

Comments / Reply and Party Alternative Proposals on Proposed Standardized Planning Assumptions

To be set forth in Ruling

Scoping Memo

April 2012

Renewable Integration Model results workshop

To be scheduled (Est. mid April)

Comments Replies on Renewable Integration Model results

To be determined

Testimony, Briefs, and Hearings (If Necessary)

Approximately July through September 2012

Proposed Decision

November 2012

Decision

December 2012

IOUs file Bundled Procurement Plans

Early 2013

Each of the issue areas outlined in the Preliminary Scoping Memo will likely require different types and degrees of public participation. Therefore, we delegate further definition of procedure and schedule for each issue area to the assigned Commissioner and ALJ as determined in the Scoping Memo or later ruling. We leave open the possibility that issue areas may be decided upon individually in interim decisions, if necessary. In addition, we authorize the assigned Commissioner and ALJ to organize issues within the proceeding, including moving issues between tracks. The assigned Commissioner or ALJ has the authority to make changes to the above schedule.

This proceeding will conform to the statutory case management deadline for ratesetting matters set forth in § 1701.5. In particular, it is our intention to resolve all relevant issues within 24 months of the date of the assigned Commissioner's Scoping Memo for each track. In using the authority granted in § 1701.5(b) to set a time longer than 18 months, we consider the number and complexity of the tasks and the need to coordinate with other proceedings.