2 Revised Phase 1 Schedule

The Scoping Memo adopted a procedural schedule for Phase 1 of this proceeding that accommodated both post-workshop comments and possible evidentiary hearings. The Scoping Memo also provided that, following a workshop on March 15, 2006, the ALJ would make a determination regarding the need for evidentiary hearings and additional workshops. By e-mail to the service list dated March 16, 2006, I announced (1) my determination that Phase 1 evidentiary hearings are not required, (2) that additional workshops would be held on March 27 (Tradable Capacity Product) and April 26 (Local Capacity Requirements Study), and (3) that an updated Phase 1 schedule with revised dates for comments would be issued. On March 29, 2006, Energy Division transmitted the revised schedule for the remaining Phase 1 procedural events by e-mail to the service list. That schedule, copied below, is revised to reflect the fact that this ruling providing direction and guidance on workshop comments is being issued on April 10, 2006; with this revision, the schedule is hereby confirmed.

Phase I Schedule - Remaining Events

Revised 4/10/06

Event

Date

Report(s) on tradable capacity product issues filed

April 3, 2006

Ruling providing direction/guidance on workshop comments

April 10, 2006

Workshop comments filed

April 18, 2006

CAISO files 2007 local capacity requirements (LCR) Study

April 21, 2006

Replies to workshop comments filed

April 25, 2006

CAISO workshop on completed LCR study (Folsom)

April 26, 2006

Comments on LCR study filed

April 28, 2006

Replies to comments on LCR study filed; submission of Phase 1

May 3, 2006

Draft decision

May 16, 2006

Comments on draft decision filed

June 5, 2006

Reply to comments on draft decision filed

June 12, 2006

Final Commission order on Phase 1 issues

June 15, 2006