The adopted, revised Phase 1 schedule provides that post-workshop comments on issues other than the CAISO's LCR study are due April 18, 2006. Replies to those comments are due April 25, 2006. Advisory Staff has prepared a report on the Phase 1 workshops which includes guidance and direction to parties regarding the post-workshop comments. The workshop report is attached to this ruling. Commenting parties should use the outline of the Staff workshop report in preparing their comments.
IT IS RULED that:
1. California Department of Water Resources State Water Project, Edison Mission Energy, J. Aron & Company, Good Company Associates on behalf of TAS, Energy Users Forum, and the California Electricity Oversight Board are parties to this proceeding.
2. Aglet Consumer Alliance has met the eligibility requirements of § 1804, including the significant financial hardship requirement, and is eligible to file a claim for an award of compensation in this proceeding.
3. The Utility Reform Network has met the eligibility requirements of § 1804, including the significant financial hardship requirement, and is eligible to file a claim for an award of compensation in this proceeding.
4. The revised Phase 1 schedule set forth herein is adopted.
5. Post-workshop comments and replies, and comments and replies on the CAISO's LCR study, may be filed in accordance with the foregoing discussion and schedule.
Dated April 10, 2006, at San Francisco, California.
/s/ MARK S. WETZELL | ||
Mark S. Wetzell Administrative Law Judge |
CERTIFICATE OF SERVICE
I certify that I have by mail this day served the Notice of Availability of the attached Administrative Law Judge's Ruling Regarding Motions to Intervene, Notices of Intent to Claim Intervenor Compensation, Revised Phase 1 Schedule, Advisory Staff Workshop Report, and Post-Workshop Comments on all parties of record in this proceeding or their attorneys of record.
Dated April 10, 2006, at San Francisco, California.
/s/ ERLINDA PULMANO |
Erlinda Pulmano |
NOTICE
Parties should notify the Process Office, Public Utilities Commission, 505 Van Ness Avenue, Room 2000, San Francisco, CA 94102, of any change of address to insure that they continue to receive documents. You must indicate the proceeding number on the service list on which your name appears.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
The Commission's policy is to schedule hearings (meetings, workshops, etc.) in locations that are accessible to people with disabilities. To verify that a particular location is accessible, call: Calendar Clerk (415) 703-1203.
If specialized accommodations for the disabled are needed, e.g., sign language interpreters, those making the arrangements must call the Public Advisor at (415) 703-2074,