Public Utilities Commission of the State of California |
|
Timothy J. Sullivan, Executive Director |
|
|
|
Headquarters |
Southern California Office |
505 Van Ness Avenue |
320 West 4th Street, Suite 500 |
San Francisco, CA 94102 |
Los Angeles, CA 90013 |
(415) 703-2782 |
(213) 576-7000 |
|
|
Website: http://www.cpuc.ca.gov |
|
Calendar Archive: prior to year 2000 http://www.cpuc.ca.gov/daily_calendar_archive/ |
|
Daily Calendar
· Commission Meetings
· Notices
· Public Meetings and Workshops
· Notice of Draft Resolutions (PU Code § 311(g))
· New Filings
· Petitions for Modification and Applications for Rehearing
· Proposed Decisions/Alternates/Presiding Officer’s Decisions/Arbitrator’s Reports
· Advice Letter Filings
· Miscellaneous Transportation Items
· Miscellaneous Communications Matters
· Table of Submission Dates for the Preceding Two Weeks
· Changes to Hearing Calendar
· Hearings
· Notice of All-Party Meetings (PU Code §1701.3(c))
|
The Commission’s policy is to schedule hearings (meetings, workshops, etc.) in locations that are accessible to people with disabilities. |
|
The CPUC encourages all Californians to participate in its meetings,
hearings, workshops, and proceedings. We try to hold our public meetings
only in places that are wheelchair accessible and which can accommodate
specialized equipment and other services useful to people with disabilities.
Please see the notice of the meeting you wish to attend for more specifics. If you plan to attend and need specialized accommodations for a particular meeting that are not listed in the notice, request them from the Public Advisor’s Office at least three business days in advance of the meeting. Contact the Public Advisor’s Office by any one of the following: |
||
Email: public.advisor@cpuc.ca.gov |
FAX: 415-355-5404 (Attn.: Public Advisor) |
|
June 29, 2017 |
9:30 am |
San Francisco, CA 94102 |
The Continuation of the June 29, 2017 Business Meeting Closed Session to June 30, 2017 at 2 pm |
|
California Public Utilities Commission – Room 5305 505 Van Ness Ave San Francisco, CA 94102 Please use this link to view the published document
|
July 13, 2017 |
9:30 am |
San Francisco, CA |
August 10, 2017 |
9:30 am |
San Francisco, CA |
Ratesetting Deliberative Meeting dates are reserved as noted but will only be held if there are ratesetting matters to be considered.
July 10, 2017 |
10:00 am |
San Francisco, Room 5305 |
August 07, 2017 |
10:00 am |
San Francisco, Room 5305 |
August 21, 2017 |
10:00 am |
San Francisco, Room 5305 |
July
6, 2017 |
California Public Utilities Commission - Auditorium 505 Van Ness Avenue,(Corner of Van Ness Avenue and McAllister St.) San Francisco, California 94102
More Information will be available closer to the date of the event.
|
The California Public Utilities Commission (CPUC) will hold an Environmental Justice and Disadvantaged Communities En Banc hearing on July 6, 2017. In order to advance the CPUC’s energy policies and programs, the CPUC will host a discussion of challenges and potential solutions, including how to reduce the need for polluting energy resources in disadvantaged communities and how to increase investment of clean energy resources in these communities. The En Banc hearing will assemble a diverse panel of experts to consider these and related issues, including increased outreach to and coordination with community representatives. An agenda and remote attendance information will be made available before the En Banc. Although a quorum of Commissioners and/or their staff may be in attendance, no official CPUC action will be taken at this event.
To purchase Commission documents, there is a charge of 20 cents a printed page (postage prepaid) with a minimum purchase of $2.00.
The auditorium, hearing rooms, and training room at the headquarters of the California Public Utilities Commission, located at 505 Van Ness Avenue, San Francisco, California, are available for rent. Further information about requirements and fees can be obtained by contacting Scott Finger (415) 703-1641.
“The
below notices having been duly noticed in the Daily Calendar and along with the
requisite ruling, scoping memo or other order issued in the specific
proceedings satisfy the requirements of the Commission’s Rules of Practice and
Procedure Rule 8.1(c) such that no ex parte communication shall be considered
to occur should a decisionmaker or an advisor be present at the meeting or
workshop.”
June 29, 2017 10 am – 5 pm
|
California Energy
Commission – Art Rosenfeld Room
To Listen By Phone Participant Call-in:(866) 469-3239 Participant meeting code: 926 921 951
TO Join Web Conference https://energy.webex.com/energy/onstage/g.php?MTID=e6f36058aa32bae5ffa2928326f466508 Meeting Code: 926 921 951
|
AGENDA
The California Energy Commission will jointly conduct a workshop with the California Public Utilities Commission (CPUC) and the California Independent Systems Operator (California ISO) to discuss the application of distributed energy resources (DER) on the California Grid. The workshop is part of the 2017 Integrated Energy Policy Report (IEPR) proceeding. A detailed schedule will be posted prior to the workshop at: http://www.energy.ca.gov/2017_energypolicy/
June 29, 2017 |
California Public Utilities Commission – Conference Room 3204 505 Van Ness Avenue,
(Corner of Van Ness Avenue and McAllister St.) |
AGENDA
The agenda of this workshop is as follows (1) Introductions, (2) Public Comment on Non-Agenda Items, (3) Review Agenda, (4) Review Prior Meeting Minutes, (5) Nomination of Jarrid Keller as Library Representative to CTF-AC, (6) Update on Applications Status, (7) Update on CTF Financial Status, (8) Discuss Annual Report due 10/1, (9) Discuss Budget Forecast for FY 2018 – 19, (10) Update on CTF OIR Status, (11) Update on Legislation Impacting CTF, (12) Set CTF-AC Meeting Schedule for Rest of Year, (13) Update on CTF Website Improvement Recommendations, and (14) Identify Items for Next Agenda. For questions about this meeting, please contact Lisa Paulo at LP1@cpuc.ca.gov or (415) 355-5495.
June 29, 2017 |
To Listen by Phone |
AGENDA
this is a monthly telephonic meeting where the co-leads for the Peer
Develop Panel (PDP) will provide to the assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of Fire Map 2 in
accordance with the schedule and procedures adopted by Decision 17-01-009. The
agenda for the meeting is for the PDP to provide: (1) A brief summary of
progress to date (first meeting) or since the previous meeting. (2) A succinct
description of the next deliverable(s) and/or milestone(s) the PDP is working
toward, and whether the PDP is on schedule. (3) Opportunity for questions
from the Assigned Commissioner, the Commissioner’s Advisor(s), assigned
Administrative Law Judges, and/or Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this telephonic meeting. Parties and the public may listen to the meeting using the listen-only toll-free number and passcode provided above. For questions regarding the monthly telephonic status meetings, please contact Martin Kurtovich at Martin.Kurtovich@cpuc.ca.gov or (415) 703-2623).
June 29, 2017 |
To Listen by Phone
|
AGENDA
this is a monthly telephonic meeting where the co-leads for the
Fire-Safety Technical Panel (FSTP) will provide to the assigned Commissioner,
the Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of proposed
fire-safety regulations in accordance with the schedule and procedures adopted
by Decision 17-01-009. The agenda for the meeting is for the FSTP to provide:
(1) A brief summary of progress to date (first meeting) or since the previous
meeting. (2) A succinct description of the next deliverable(s) and/or
milestone(s) the FSTP is working toward, and whether the FSTP is on schedule.
(3) Opportunity for questions from the Assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
July 10, 2017 |
To Join Web Conference
Click here: https://energy.webex.com; Meeting ID for WebEx and phone: 925 866 516
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group will allow participants to review, understand, and discuss the technical details of existing communication protocols. The recommendations of the working group will be considered and incorporated in CPUC’s Rulemaking 13-11-007 (and/or the SB 350 Transportation Electrification applications A.17-01-020, A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy Policy Report (IEPR) proceeding for future policy decisions. Anyone interested in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or 415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov or 415-703-2872).
July 10, 2017
and
3 pm to 5 pm
(two meetings will be held, please attend the one that is most convenient for your schedule)
TRADUCICÓN AL ESPAÑOL DISPONIBLE. |
San Joaquin Valley Air Pollution Control District 1990 E. Gettysburg, Ave. Fresno, CA 93726
Conference Phone Line: 1-877-715-0719 Participant Code:
721383 |
AGENDA
On July 10, 2017, the California Public Utilities Commission will host
two public meetings to provide information about its recently opened Rulemaking
to implement the Dairy Biomethane Pilots required by Senate Bill 1383. You may
access the rulemaking at: http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M191/K136/191136501.PDF.
The purpose of the rulemaking is to establish how dairy biomethane pilots will
be selected to demonstrate interconnection to the pipeline system, the
definition of pipeline infrastructure that will be eligible for cost recovery
from utility customers, the cost recovery framework, and data gathering
requirements. These pilot projects (which will process manure using anaerobic
digestion and produce useable methane gas) are part of the state’s efforts to
reduce emissions of short-lived climate pollutants, including reducing methane
emissions 40% by 2020.
At the public meetings, the California Public Utilities Commission staff will present a brief overview of the proposed framework for selecting pilots, the proposed definition of recoverable pipeline infrastructure, the cost recovery framework, and the data gathering requirements. The majority of the time will be set aside to hear from the public and potential stakeholders about the proposed implementation framework. We encourage you to review the Rulemaking and the Proposed Implementation Framework described in its Appendices in preparing your comments.
The public meetings will be convened by the Administrative Law Judge assigned to the Rulemaking who will describe how interested individuals and organizations can formally participate in the Rulemaking. The staff presentation and public comments will be recorded and available for review by the CPUC as part of the public input to the proceeding. Although a quorum of Commissioners and/or their staff may be in attendance, no official CPUC action will be taken at this event.
For questions about the public meetings, please contact Dorris Chow at dorris.chow@cpuc.ca.gov.
If you require special accommodations, please notify the Public Advisor's Office at toll free 1-866-849-8390 or mailto:public.advisor@cpuc.ca.gov,public.advisor@cpuc.ca.gov, at least 3 business days before the hearing.
July 10, 2017 |
PG&E Pacific Energy Center 851 Howard Street San Francisco, CA
To join by phone Conference call number: (646) 749-3122 Access Code: 979-040-069
To join online meeting: https://global.gotomeeting.com/join/979040069
|
AGENDA
The Energy Division, Energy Efficiency Branch of the California Public Utilities Commission staff will hold the Track 2 Working Group (T2WG) meeting on July 10, 2017 to address per Decision 16-08-019 Custom review process streamlining; Development and application of Industry Standard Practice determinations
Although a quorum of Commissioners and/or their staff may be in attendance or be on the telephone, no official CPUC action will be taken at this event. The agenda for this meeting is forthcoming and will be posted at the T2WG website at: http://t2wg.cadmusweb.com. For those unable to attend in person, a webinar and a call-in number are provided. However, parts of this meeting may be difficult to participate in by phone; please try to attend in person. If you wish to participate, but are unable to attend in-person or by telephone, please email t2wg@cadmusgroup.com to get on the T2WG email distribution list.
Public Workshop Notice: R.15-03-010 - Community Energy Option Assessment Workshops.
July 10, 2017
4pm -5pm
And
July 11, 2017
4pm -5pm |
West Goshen Elementary School 6505 Avenue 308 West Goshen, CA 93219 Community Tours
Ducor Union Elementary School 23761 Ave 56 Ducor, CA 93218 Community Tours
|
AGENDA
In 2014, Governor Edmund G. Brown, Jr. signed Assembly Bill (AB) 2672
into law, directing the California Public Utilities Commission to provide
options for affordable energy in communities in the San Joaquin Valley that may
lack access to natural gas. West Goshen and Ducor are on the list of
prioritized communities. Meetings are scheduled in West Goshen and Ducor to
engage in dialogue with residents and other stakeholders about what types of
affordable energy options might be best suited to the community. The agenda
includes presentations from Southern California Edison Company (SCE) and
Southern California Gas (SoCalGas), as well as from other stakeholders,
followed by open discussion with community members and bill assistance for
residents of the community from SCE staff. Discussion may be in English or
Spanish, with translation headsets available. Please contact Commission staff
lead Lola Odunlami if you have further questions, at Lola.Odunlami@cpuc.ca.gov or (415)
703-1893.
July 11, 2017 |
California Public
Utilities Commission - Auditorium To Listen By Phone Conference Call in: 1-866-811-6884 Participant code: 8742156
To Join Web Conference https://van.webex.com/van/j.php?MTID=m602ea5aa707c4555a471d1e6a7674944 Meeting number: 741 921 825; Password: !Energy1
|
AGENDA
California Public Utilities Commission staff will host a public
workshop to discuss the standard review transportation electrification
proposals included in the investor owned utilities’ (IOUs) applications filed
pursuant to requirements established in Senate Bill 350 to accelerate
widespread transportation electrification.
On January 20, 2017, Pacific Gas and Electric Company, San Diego Gas & Electric Company, and Southern California Edison Company submitted applications proposing programs designed to reduce dependence on petroleum, meet air quality standards, lower greenhouse gas emissions, achieve the goals set forth in the Charge Ahead California Initiative, and be in the interest of ratepayers, as required under D.16-11-005. The utilities’ applications can be found at www.cpuc.ca.gov/sb350te. The focus of this workshop will be the utilities’ proposals for standard review projects, which would install nearly $1 billion in infrastructure aimed at accelerating transportation electrification across the three IOUs’ service territories. A more detailed agenda for the workshop will be made available closer to the event. Though a quorum of commissioners may be present, no decisions will be made. For more information contact: Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or 415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov or 415-703-2872).
July 24, 2017 8:30 am – 11:30am |
To Join Web Conference: Click here: https://energy.webex.com Meeting ID : 925 866 516
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group will allow participants to review, understand, and discuss the technical details of existing communication protocols. The recommendations of the working group will be considered and incorporated in CPUC’s Rulemaking 13-11-007 (and/or the SB 350 Transportation Electrification applications A.17-01-020, A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy Policy Report (IEPR) proceeding for future policy decisions. Anyone interested in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or 415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov or 415-703-2872).
July 27, 2017 |
To Listen by Phone |
AGENDA
this is a monthly telephonic meeting where the co-leads for the Peer
Develop Panel (PDP) will provide to the assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of Fire Map 2 in
accordance with the schedule and procedures adopted by Decision 17-01-009. The
agenda for the meeting is for the PDP to provide: (1) A brief summary of
progress to date (first meeting) or since the previous meeting. (2) A succinct
description of the next deliverable(s) and/or milestone(s) the PDP is working
toward, and whether the PDP is on schedule. (3) Opportunity for questions
from the Assigned Commissioner, the Commissioner’s Advisor(s), assigned
Administrative Law Judges, and/or Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
July 27, 2017 |
To Listen by Phone
|
AGENDA
this is a monthly telephonic meeting where the co-leads for the
Fire-Safety Technical Panel (FSTP) will provide to the assigned Commissioner,
the Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of proposed
fire-safety regulations in accordance with the schedule and procedures adopted
by Decision 17-01-009. The agenda for the meeting is for the FSTP to provide:
(1) A brief summary of progress to date (first meeting) or since the
previous meeting. (2) A succinct description of the next deliverable(s) and/or
milestone(s) the FSTP is working toward, and whether the FSTP is on schedule.
(3) Opportunity for questions from the Assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
August 7, 2017 |
San Francisco CA 94102
To
Join Web Conference: Meeting ID: 925 191 027
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group will allow participants to review, understand, and discuss the technical details of existing communication protocols. The recommendations of the working group will be considered and incorporated in CPUC’s Rulemaking 13-11-007 (and/or the SB 350 Transportation Electrification applications A.17-01-020, A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy Policy Report (IEPR) proceeding for future policy decisions. Anyone interested in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or 415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov or 415-703-2872).
August 21, 2017 |
To Join the Web Conference: Meeting ID : 925 866 516
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group will allow participants to review, understand, and discuss the technical details of existing communication protocols. The recommendations of the working group will be considered and incorporated in CPUC’s Rulemaking 13-11-007 (and/or the SB 350 Transportation Electrification applications A.17-01-020, A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy Policy Report (IEPR) proceeding for future policy decisions. Anyone interested in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or 415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov or 415-703-2872).
August 31, 2017 |
To Listen by Phone |
AGENDA
this is a monthly telephonic meeting where the co-leads for the Peer
Develop Panel (PDP) will provide to the assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of Fire Map 2 in
accordance with the schedule and procedures adopted by Decision 17-01-009. The
agenda for the meeting is for the PDP to provide: (1) A brief summary of
progress to date (first meeting) or since the previous meeting. (2) A succinct
description of the next deliverable(s) and/or milestone(s) the PDP is working
toward, and whether the PDP is on schedule. (3) Opportunity for questions
from the Assigned Commissioner, the Commissioner’s Advisor(s), assigned
Administrative Law Judges, and/or Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
Telephonic - Public Meeting Notice: R.15-05-006 - Status Report Regarding
Development of Proposed Fire-Safety Regulations
August 31, 2017 |
To Listen by Phone
|
AGENDA
this is a monthly telephonic meeting where the co-leads for the
Fire-Safety Technical Panel (FSTP) will provide to the assigned Commissioner,
the Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of proposed
fire-safety regulations in accordance with the schedule and procedures adopted
by Decision 17-01-009. The agenda for the meeting is for the FSTP to provide:
(1) A brief summary of progress to date (first meeting) or since the
previous meeting. (2) A succinct description of the next deliverable(s) and/or
milestone(s) the FSTP is working toward, and whether the FSTP is on schedule.
(3) Opportunity for questions from the Assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
Webinar - Public Meeting Notice: R.13-11-007 -
Vehicle-Grid Integration Communications Protocol Working Group Meeting Schedule
September 5, 2017 8:30 am – 11:30 am |
To Join Web
Conference: Meeting ID: 925 866
516 Details about location and remote access options for each meeting will be posted in advance at www.cpuc.ca.gov/vgi.
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group
will allow participants to review, understand, and discuss the technical
details of existing communication protocols. The recommendations of the working
group will be considered and incorporated in CPUC’s Rulemaking 13-11-007
(and/or the SB 350 Transportation Electrification applications A.17-01-020,
A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy
Policy Report (IEPR) proceeding for future policy decisions. Anyone interested
in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or
415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov
or 415-703-2872).
Public Meeting Notice: R. 13-11-007 - Vehicle-Grid
Integration Communications Protocol Working Group Meeting Schedule
September 18, 2017 |
Sacramento, CA 94814 Click here: https://energy.webex.com; Meeting ID: 926 148 357
Details about location and remote access options for each meeting will be posted in advance at www.cpuc.ca.gov/vgi
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group
will allow participants to review, understand, and discuss the technical
details of existing communication protocols. The recommendations of the working
group will be considered and incorporated in CPUC’s Rulemaking 13-11-007
(and/or the SB 350 Transportation Electrification applications A.17-01-020,
A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy
Policy Report (IEPR) proceeding for future policy decisions. Anyone interested
in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or
415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov
or 415-703-2872).
Telephonic - Public Meeting Notice: R.15-05-006 -
Status Report Regarding the Development of Fire-Threat Maps
September 28, 2017 |
To Listen by Phone |
AGENDA
this is a monthly telephonic meeting where the co-leads for the Peer
Develop Panel (PDP) will provide to the assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of Fire Map 2 in
accordance with the schedule and procedures adopted by Decision 17-01-009. The
agenda for the meeting is for the PDP to provide: (1) A brief summary of
progress to date (first meeting) or since the previous meeting. (2) A succinct
description of the next deliverable(s) and/or milestone(s) the PDP is working
toward, and whether the PDP is on schedule. (3) Opportunity for questions
from the Assigned Commissioner, the Commissioner’s Advisor(s), assigned
Administrative Law Judges, and/or Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this telephonic meeting. Parties and the public may listen to the meeting using the listen-only toll-free number and passcode provided above. For questions regarding the monthly telephonic status meetings, please contact Martin Kurtovich at Martin.Kurtovich@cpuc.ca.gov or (415) 703-2623).
Telephonic - Public Meeting Notice: R.15-05-006 -
Status Report Regarding Development of Proposed Fire-Safety Regulations
September 28, 2017 |
To Listen by Phone
|
AGENDA
this is a monthly telephonic meeting where the co-leads for the
Fire-Safety Technical Panel (FSTP) will provide to the assigned Commissioner,
the Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of proposed
fire-safety regulations in accordance with the schedule and procedures adopted
by Decision 17-01-009. The agenda for the meeting is for the FSTP to provide:
(1) A brief summary of progress to date (first meeting) or since the
previous meeting. (2) A succinct description of the next deliverable(s) and/or
milestone(s) the FSTP is working toward, and whether the FSTP is on schedule.
(3) Opportunity for questions from the Assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
Webinar - Public Meeting Notice: R.13-11-007 -
Vehicle-Grid Integration Communications Protocol Working Group Meeting Schedule
October 2, 2017 |
To Join Web Conference: Meeting ID: 925 866 516
Details about location and remote access options for each meeting will be posted in advance at www.cpuc.ca.gov/vgi
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group will allow participants to review, understand, and discuss the technical details of existing communication protocols. The recommendations of the working group will be considered and incorporated in CPUC’s Rulemaking 13-11-007 (and/or the SB 350 Transportation Electrification applications A.17-01-020, A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy Policy Report (IEPR) proceeding for future policy decisions. Anyone interested in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or 415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov or 415-703-2872).
October 16, 2017 |
San Francisco, CA
94102 Click here: https://energy.webex.com; Meeting ID: 928 215 208
|
AGENDA
The Vehicle-Grid Integration (VGI) Communication Protocol working
group, which is designed to inform the Commission’s rulemaking under
R.13-11-007 and related proceedings, will meet according to the above schedule.
Any changes to the schedule will be noticed on the Daily Calendar, including updates on locations for the all-day meetings. A current schedule will also be available at www.cpuc.ca.gov/vgi.
Background
The California Public Utilities Commission, California Energy Commission, and other State agencies convened this working group to assess how and whether the adoption of a communications protocol is necessary to enable Plug-In Electric Vehicle-Grid Integration (VGI) resources to more economically participate in electricity markets at scale.
Participants of the working group will identify and assess opportunities in which VGI can create value from multiple market participants’ perspectives, communication protocols needed to deliver that value, and concepts for how utilities, automakers, electric vehicle service providers, aggregators, and others can develop pathways to market for a VGI resource.
The working group
will allow participants to review, understand, and discuss the technical
details of existing communication protocols. The recommendations of the working
group will be considered and incorporated in CPUC’s Rulemaking 13-11-007
(and/or the SB 350 Transportation Electrification applications A.17-01-020,
A.17-01-021 and A.17-01-022) and the Energy Commission’s Integrated Energy
Policy Report (IEPR) proceeding for future policy decisions. Anyone interested
in participating in the VGI Working Group should contact Amy Mesrobian (amy.mesrobian@cpuc.ca.gov or
415-703-3175) or Carrie Sisto (cs8@cpuc.ca.gov
or 415-703-2872).
Telephonic - Public Meeting Notice: R.15-05-006 -
Status Report Regarding the Development of Fire-Threat Maps
October 26, 2017 |
To Listen by Phone |
AGENDA
this is a monthly telephonic meeting where the co-leads for the Peer
Develop Panel (PDP) will provide to the assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of Fire Map 2 in
accordance with the schedule and procedures adopted by Decision 17-01-009. The
agenda for the meeting is for the PDP to provide: (1) A brief summary of
progress to date (first meeting) or since the previous meeting. (2) A succinct
description of the next deliverable(s) and/or milestone(s) the PDP is working
toward, and whether the PDP is on schedule. (3) Opportunity for questions
from the Assigned Commissioner, the Commissioner’s Advisor(s), assigned
Administrative Law Judges, and/or Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
Telephonic - Public Meeting Notice: R.15-05-006 -
Status Report Regarding Development of Proposed Fire-Safety Regulations.
October 26, 2017 |
To Listen by Phone
|
AGENDA
this is a monthly telephonic meeting where the co-leads for the
Fire-Safety Technical Panel (FSTP) will provide to the assigned Commissioner,
the Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of proposed
fire-safety regulations in accordance with the schedule and procedures adopted
by Decision 17-01-009. The agenda for the meeting is for the FSTP to provide:
(1) A brief summary of progress to date (first meeting) or since the
previous meeting. (2) A succinct description of the next deliverable(s) and/or
milestone(s) the FSTP is working toward, and whether the FSTP is on schedule.
(3) Opportunity for questions from the Assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
Telephonic - Public Meeting Notice: R.15-05-006 -
Status Report Regarding the Development of Fire-Threat Maps.
November 30, 2017 |
To Listen by Phone |
AGENDA
this is a monthly telephonic meeting where the co-leads for the Peer
Develop Panel (PDP) will provide to the assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of Fire Map 2 in
accordance with the schedule and procedures adopted by Decision 17-01-009. The
agenda for the meeting is for the PDP to provide: (1) A brief summary of
progress to date (first meeting) or since the previous meeting. (2) A succinct
description of the next deliverable(s) and/or milestone(s) the PDP is working
toward, and whether the PDP is on schedule. (3) Opportunity for questions
from the Assigned Commissioner, the Commissioner’s Advisor(s), assigned
Administrative Law Judges, and/or Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
Telephonic - Public Meeting Notice: R.15-05-006 -
Status Report Regarding Development of Proposed Fire-Safety Regulations.
November 30, 2017 |
To Listen by Phone
|
AGENDA
this is a monthly telephonic meeting where the co-leads for the
Fire-Safety Technical Panel (FSTP) will provide to the assigned Commissioner,
the Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of proposed
fire-safety regulations in accordance with the schedule and procedures adopted
by Decision 17-01-009. The agenda for the meeting is for the FSTP to provide:
(1) A brief summary of progress to date (first meeting) or since the
previous meeting. (2) A succinct description of the next deliverable(s) and/or
milestone(s) the FSTP is working toward, and whether the FSTP is on schedule.
(3) Opportunity for questions from the Assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
Telephonic - Public Meeting Notice: R.15-05-006 -
Status Report Regarding the Development of Fire-Threat Maps
December 28, 2017 |
To Listen by Phone |
AGENDA
this is a monthly telephonic meeting where the co-leads for the Peer
Develop Panel (PDP) will provide to the assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of Fire Map 2 in
accordance with the schedule and procedures adopted by Decision 17-01-009. The
agenda for the meeting is for the PDP to provide: (1) A brief summary of
progress to date (first meeting) or since the previous meeting. (2) A succinct
description of the next deliverable(s) and/or milestone(s) the PDP is working
toward, and whether the PDP is on schedule. (3) Opportunity for questions
from the Assigned Commissioner, the Commissioner’s Advisor(s), assigned
Administrative Law Judges, and/or Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
December 28, 2017 |
To Listen by Phone
|
AGENDA
this is a monthly telephonic meeting where the co-leads for the
Fire-Safety Technical Panel (FSTP) will provide to the assigned Commissioner,
the Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff a status report regarding the development of proposed
fire-safety regulations in accordance with the schedule and procedures adopted
by Decision 17-01-009. The agenda for the meeting is for the FSTP to provide:
(1) A brief summary of progress to date (first meeting) or since the
previous meeting. (2) A succinct description of the next deliverable(s) and/or
milestone(s) the FSTP is working toward, and whether the FSTP is on schedule.
(3) Opportunity for questions from the Assigned Commissioner, the
Commissioner’s Advisor(s), assigned Administrative Law Judges, and/or
Commission staff.
As stated above, Commission decisionmakers and Advisors may participate in this
telephonic meeting. Parties and the public may listen to the meeting using the
listen-only toll-free number and passcode provided above. For questions
regarding the monthly telephonic status meetings, please contact Martin
Kurtovich at Martin.Kurtovich@cpuc.ca.gov
or (415) 703-2623).
The ALJ
Division has prepared Resolution ALJ-345 for the June 29, 2017,
Commission Meeting. (Adopting Intervenor Compensation Rates for 2017 and
Addressing Related Matters) Any comments should be directed to ALJ Farrar via
e-mail: edf@cpuc.ca.gov or phone
1-415-703-1599.
The web link is: http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=187482279
The Energy Division has prepared Draft Resolution E-4851 for the June 29, 2017, Commission Meeting. This Resolution grants Southern California Edison Company’s request for Commission approval of a new renewable power purchase agreement with Maverick Solar, LLC. Any questions and/or comments should be directed to Brian Korpics at Brian.Korpics@cpuc.ca.gov and Cheryl Lee at cheryl.lee@cpuc.ca.gov.
The web link is: http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=187474938
The Energy Division has prepared Draft Resolution G-3529 for the June 29, 2017 Commission Meeting. This Resolution addresses Southern California Gas Company’s request for expedited approval of the gas storage Proposed Injection Plan and Injection Enhancement Memorandum between the Utility System Operator and the Gas Acquisition Department for Services to Maintain Summer Reliability. All questions or comments should be addressed to Belinda Gatti at belinda.gatti@cpuc.ca.gov and Franz Cheng at franz.cheng@cpuc.ca.gov.
The web link is: http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=190187614
The Communication Division has prepared Draft Resolution T-17570 conditionally approves the Wireless Identification Registration application of Lycamobile USA, Inc. subject to the fine for operating without authority and authorizes the Director of the Communications Division to issue final approval letter and Wireless Identification Registration identification number for the June 29, 2017, Commission meeting. The Communications Division e-mailed the Notice of Availability letter for this resolution to parties in accordance with PU Code Section 311 (g)(1). Instruction and timelines on filing of opening and reply comments as well as the service list for this resolution are included in the Notice of Availability. Any questions or comments should be directed to Danny Tse: email danny.tse@cpuc.ca.gov
The web link is: http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M188/K985/188985969.doc
NOTICE OF RESOLUTION
Resolution TL-19125 sustains the cease and desist orders issued by the Consumer Protection and Enforcement Division (CPED) on Adesa California, LLC d/b/a Brasher’s Sacramento and Brasher’s San Jose Auto Auctions (Adesa), and affirms Commission jurisdiction over charter-party carriers that conduct transportation services incidental to another business, pursuant to Public Utilities Code § 5384.
On May 30, 2017, the draft
resolution was mailed to the service list, pursuant to California Public
Utilities Code
§ 311(g) and Rule 14.5 of the Commission’s Rules of Practice and Procedure.
Comments shall be served no later than June 19, 2017 and reply comments shall
be served no later than June 26, 2017.
Resolution TL-19125 will be on the agenda at the June 29, 2017 Commission meeting. The Commission may then vote on this draft resolution, or it may postpone a vote.
When the Commission acts on the draft resolution, it may adopt all or part of it as written, amend or modify it, or set it aside and prepare its own order. Only when the Commission acts does the resolution become binding on the parties.
Finally, an original and two copies of the comments, with a certificate of service should be submitted to:
Lisa Marie
Clark, Staff Counsel
Legal Division
California Public Utilities Commission
505 Van Ness Avenue, Room 5040
San Francisco, CA 94102-3298
Telephone: 415-2069
E-mail: lms@cpuc.ca.gov
The ALJ Division has prepared Draft Resolution ALJ-344. The resolution would amend the Rules of Practice and Procedure (Title 20, Division 1, of the California Code of Regulations) to implement statutory amendments pursuant to Senate Bill 215, reflect changes in the Commission’s administration, streamline certain procedures, and provide greater clarity. Notice of this draft has been sent to subscribers to the Rules-Update list for notification of proposed changes to the Rules of Practice and Procedure. (See https://ia.cpuc.ca.gov/rulesupdate/.) Pursuant to Government Code §§ 11346.4 and 11351, and California Code of Regulations, Title 1, §§ 1-120, notice of these proposed amendments was published in the California Regulatory Notice Register on May 19, 2017. This publication starts the 45-day notice and comment period, which closes at 5:00 p.m. on July 3, 2017. This 45-day notice and comment period satisfies the notice and comment requirements of Public Utility Code § 311. Any person may submit written comments concerning the proposed rule amendments to ALJ Hallie Yacknin by email to hallie.yacknin@cpuc.ca.gov or by post at California Public Utilities Commission, 505 Van Ness Ave., San Francisco, CA 94102.
The web link is http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=185486822.
The Energy Division has prepared Draft Resolution E-4859 for the July 13, 2017 Commission Meeting. This Draft Resolution approves Pacific Gas and Electric Company’s request to retain fee title to approximately 112 acres of land in Shasta County commonly known as Kilarc Reservoir. Notice of this Draft Resolution has been sent to parties in the service list. Any questions or comments should be directed to Michael Rosauer at Michael.Rosauer@cpuc.ca.gov and Mary Jo Borak at maryjo.borak@cpuc.ca.gov.
The web link is: http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M189/K786/189786422.PDF
Resolution ESRB-7 ratifies Commission Executive Director Timothy J. Sullivan’s May 31, 2017 health and safety directive granting the Southern California Edison Company (SCE) a temporary deviation from the climbing space requirements in General Order 95, Rule 54.7, due to emergency conditions in the City of Compton, California.
On June 16, 2017, the draft resolution was mailed to the attached service list, pursuant to California Public Utilities Code § 311(g) and Rule 14.5 of the Commission’s Rules of Practice and Procedure. Comments must be filed by July 3, 2017, and reply comments must be filed by July 10, 2017.
Resolution ESRB-7 will be on the agenda at the July 13, 2017 Commission meeting. The Commission may then vote on this draft resolution, or it may postpone a vote.
When the Commission acts on the draft resolution, it may adopt all or part of it as written, amend or modify it, or set it aside and prepare its own order. Only when the Commission acts does the resolution become binding on the parties.
Finally, an original and two copies of the comments, with a certificate of service should be submitted to:
Fred
Harris, Staff Counsel
Legal Division
California Public Utilities Commission
505 Van Ness Avenue, Room 5040
San Francisco, CA 94102-3298
Telephone: 415-703-1557
E-mail: fnh@cpuc.ca.gov; ah4@cpuc.ca.gov
The Safety and Enforcement Division has prepared Draft Resolution ST-204 for the July 13, 2017, Commission meeting. This resolution grants approval of the final report, titled “2016 Triennial Safety Review of the J. Paul Getty Center Tram (Getty)” dated April 19, 2017. The report compiles the results of the Commission Staff’s review of Getty’s fixed guideway (Tram) safety programs. Background information, review procedures, safety review checklists, findings, and recommendations are included in the report. Any questions or comments should be directed to Daniel Kwok: daniel.kwok@cpuc.ca.gov
The web links are:
Cover Letter, Certificate of Service, Service list:
http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=190197398
Comment Resolution ST-204:
http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=190198433
Resolution ST-204 Attachment A, 2016 Getty Tram Triennial Safety Review Report:
The Communications Division has prepared Draft Resolution T-17572 which will be on the Commission’s July 13, 2017, meeting agenda. Resolution T-17572 approves the Fiscal Year 2017-18 budgets for California’s six telecommunications public purpose programs that the California Public Utilities Commission administers.The Communications Division e-mailed the Notice of Availability letter for this resolution to parties in accordance with P.U. Code Section 311(g)(1). Instructions and timelines for filing comments as well as the service list for this resolution are included in the Notice of Availability. Any questions or comments should be directed to Eric Van Wambeke; email: evw@cpuc.ca.gov
The web link is: http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M190/K074/190074909.doc
The Energy Division has prepared Draft Resolution E-4853 for the August 10, 2017 Commission Meeting. This Resolution addresses San Diego Gas & Electric Company’s request for approval to offer Line Item Billing Service for a Home Protection Plan Service, on a non-tariffed basis. All questions or comments should be addressed to Scarlett Liang-Uejio at scarlett.liang-uejio@cpuc.ca.gov and Jonathan Tom at jonathan.tom@cpuc.ca.gov .
The web link is: http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=191247200
The Energy Division has prepared Draft Resolution G-3525 for the August 10, 2017 Commission Meeting. This Draft Resolution approves the costs of the procurement activities undertaken to maintain Southern System reliability during the period from September 1, 2015 through August 31, 2016. Notice of this Draft Resolution has been sent to parties in the service lists. Any questions or comments should be directed to Jamie Ormond at Jamie.ormond@cpuc.ca.gov and Franz Cheng at franz.cheng@cpuc.ca.gov
The web link is: http://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M190/K576/190576349.PDF
The Safety and Enforcement Division has prepared Draft Resolution ST-205 for the August 10, 2017, Commission meeting. This Resolution grants the San Francisco International Airport AirTrain (AirTrain) request for approval of its Safety Certification Plan for the AirTrain Extension and Improvements Program. Any questions or comments should be directed to Jamie Lau at jamie.lau@cpuc.ca.gov
The web link is: http://docs.cpuc.ca.gov/SearchRes.aspx?docformat=ALL&DocID=191445049
NONE
NONE
NONE
ADVICE LETTER FILINGSTo inquire
about a filing, call the Energy Division (703-1093), Communications Division
(703-3052) or Water Division (703-1133).
|
||
03/01/17 |
Telecom 46400 |
Pacific Bell, Contract (effective TBD) |
|
|
|
06/22/17 |
Energy 5100E |
Pacific Gas & Electric Company, Wishon Reservoir Land Retained - Request for Approval under Decision (D.) 08-11-043, D.10-08-004 and Public Utilities Code Section 851 (effective TBD) |
|
|
|
06/22/17 |
Energy 2588G |
San Diego Gas & Electric Company, May 2017 Standby Procurement Rate (anticipated effective 06/22/17) |
|
|
|
06/22/17 |
Energy 3621E |
Southern California Edison Company, Modifications to SCE's Renewable Market Adjusting Tariff and Bioenergy Market Adjusting Tariff Pertaining to Queue Management Procedures for a Change in Eligibility of an Applicant and/or Project in the Program Queue (anticipated effective 07/22/17) |
|
|
|
06/22/17 |
Energy 5153G |
Southern California Gas Company, May 2017 Standby Procurement Charges (anticipated effective 06/22/17) |
|
|
|
06/22/17 |
Telecom 594 |
Level 3 Telecom of California, LP, Local Exchange Services Tariff Revision (effective TBD) |
|
|
|
06/22/17 |
Water 67 |
Fulton Water Company, Request for CPI rate increase of 2.1 % (anticipated effective 06/22/17) |
|
|
|
06/23/17 |
Energy 3856G/5102E |
Pacific Gas & Electric Company, Establish Electric and Gas Executive Compensation Memorandum Accounts, in Compliance with the 2017 GRC D.17-05-013. (anticipated effective 01/01/17) |
|
|
|
06/23/17 |
Energy 5101E |
Pacific Gas & Electric Company, Submits Notice of Construction, Pursuant to General Order 131-D, for the Construction of Camanche Tap 115 kV Reconductoring Project in County of San Joaquin (anticipated effective 07/23/17) |
|
|
|
06/23/17 |
Energy 5103E |
Pacific Gas & Electric Company, Modifications to Electric Rule 21 to Enhance the Expedited Interconnection Storage Process for Non-Exporting Storage in Accordance with Advice 4941-E/E-A and D.16-06-052. (anticipated effective 07/23/17) |
|
|
|
06/23/17 |
Energy 3463E-B |
Southern California Edison Company, Supplements A.L.No.3463E, Submission of High Opportunity Projects and Programs Proposal Comprehensive Value Chain Heating, Ventilation, and Air Conditioning Program (anticipated effective 09/30/16) |
|
|
|
06/23/17 |
Energy 3622E |
Southern California Edison Company, Proposed Sale of Certain Southern California Edison Company's Distribution Assets to Eastern Municipal Water District (anticipated effective 07/23/17) |
|
|
|
06/23/17 |
Telecom 148 |
Charter Fiberlink CA-CCO, LLC, Establishment of services in new exchange areas (anticipated effective 06/01/17) |
|
|
|
06/23/17 |
Telecom 12756 |
Frontier California Inc., FCC ICC Reform (effective TBD) |
|
|
|
06/23/17 |
Water 1159-A |
California-American Water Company, Supplements A.L.No.1159, [Los Angeles] 2016 WRAM and MCBA (anticipated effective 03/31/17) |
|
|
|
06/26/17 |
Energy 3857G |
Pacific Gas & Electric Company, July 1, 2017 Noncore Gas Transportation Tariff Rate Changes Resulting from Implementing the 2017 General Rate Case Decision 17-05-013 and Self Generation Incentive Program Decision 17-04-017 (anticipated effective 07/01/17) |
|
|
|
06/26/17 |
Energy 3858G |
Pacific Gas & Electric Company, July 2017 G-SUR Rate Change (anticipated effective 07/01/17) |
|
|
|
06/26/17 |
Energy 3859G |
Pacific Gas & Electric Company, July 1, 2017 Gas Core Procurement, 2017 General Rate Case Decision 17-05-013 and Self Generation Incentive Program Decision 17-04-017 Gas Transportation Rate Changes (anticipated effective 07/01/17) |
|
|
|
06/26/17 |
Energy 5104E |
Pacific Gas & Electric Company, Submits Notice of Construction, Pursuant to General Order 131-D, for the Construction of Sobrante-R #1 & #2 115 kV Power Line Reconductoring Project in the Cities of Richmond and El Cerrito, Contra Costa County (anticipated effective 07/26/17) |
|
|
|
06/26/17 |
Energy 5105E |
Pacific Gas & Electric Company, Revisions to Electric Schedule RES-BCT to Remove the Power Charge Indifference Adjustment (anticipated effective 07/26/17) |
|
|
|
06/26/17 |
Telecom 257 |
Winterhaven Telephone Company, Modify Company's Intrastate Applicable Switched Access Rates (effective TBD) |
|
|
|
06/26/17 |
Water 2264 |
California Water Service Company, [Dominguez] Purchased Water and Pump tax Offset July, 2017 (anticipated effective 07/01/17) |
|
|
|
06/26/17 |
Water 2265 |
California Water Service Company, [Palos Verdes] Purchased Water Offset (July 2017) for Los Angeles County Region (anticipated effective 07/01/17) |
|
|
|
06/26/17 |
Water 2266 |
California Water Service Company, [Los Altos] Purchased Water and Pump tax Offset Juley, 2017 (anticipated effective 07/01/17) |
|
|
|
06/26/17 |
Water 1706-W |
Golden State Water Company, [Bay Point] increase base rates to offset the increase in a supply expense for purchased water & power (anticipated effective 07/10/17) |
|
|
|
06/26/17 |
Water 1707-W |
Golden State Water Company, [Simi Valley] increase base rates to offset the increase in a su pply expense for purchased water & purchase power. (anticipated effective 07/10/17) |
|
|
|
06/26/17 |
Water 1708-W |
Golden State Water Company, [Region 2] increase base rates to offset the increase in a supply expense for purchased water & power (anticipated effective 07/10/17) |
|
|
|
06/26/17 |
Water 1709-W |
Golden State Water Company, [REGION 3] increase base rates to offset the increase in a supply expense for purchased water & power (anticipated effective 07/10/17) |
|
|
|
06/26/17 |
Water 496 |
Golden State Water Company, [Los Angeles County and Fontana Water Company] (anticipated effective 07/01/17) |
|
|
|
06/26/17 |
Water 496 |
San Gabriel Valley Water Company, [Los Angeles County and Fontana Water Company] Implementation ofTY 2017-2018 Rates (anticipated effective 07/01/17) |
|
|
|
06/27/17 |
Energy 3623E |
Southern California Edison Company, SCE's Proposed Modifications to Electric Tariff Rule 21 to Incorporate Smart Inverter Settings and Other Supporting Implementation Related Revisions. (anticipated effective 07/27/17) |
|
|
|
06/27/17 |
Energy 3624E |
Southern California Edison Company, Modification of the Distribution Resources Plan Demonstration Balancing Account Pursuant to D.17-06-012 (anticipated effective 06/27/17) |
|
|
|
06/27/17 |
Energy 5154G |
Southern California Gas Company, Revision to Schedule No. G-BTS Pursuant to Decision (D.) 11-04-032 (anticipated effective 07/01/17) |
|
|
|
|
||
05/31/17 |
Energy 72E |
Liberty Utilities (CalPeco Electric) LLC. Automatic suspension extension. Date suspension ends: 11/27/17. |
|
|
|
07/07/17 |
Energy 5015E |
Pacific Gas & Electric Company. Automatic suspension extension. Date suspension ends: 01/02/18. |
|
|
|
07/20/17 |
Telecom 21 |
TruConnect Communications, Inc.. Initial suspension on the following grounds: additional time is needed. Date suspension ends: 11/16/17. Note: Initial suspensions will be automatically extended for an additional 180 days if the Commission has not issued an order regarding the advice letter by the date the first suspension period ends. |
|
|
|
|
||
06/26/17 |
Energy 5080E |
Pacific Gas & Electric Company, Update to the 2017-2019 Nuclear Decommissioning Trust Revenue Requirements in Compliance with Decision 17-05-020 Late filed protest by TURN. |
NONE
NONE
NONE
|
|
07/10/17 |
R.15-03-010 (WS) - Order
Instituting Rulemaking to Identify Disadvantaged Communities in the San
Joaquin Valley and Analyze Economically Feasible Options to Increase Access
to Affordable Energy in those Disadvantaged Communities, |
|
|
07/12/17 |
A.17-04-028 (PHC) - In
the Matter of the Application of Pacific Gas and Electric Company for
Approval of its 2018-2020 Electric Program Investment Charge Investment
Plan. (U39E), A.17-05-003 |
|
|
07/13/17 |
ECP – C.17-03-015 (EH) - Joe
Bustard, Complainant vs Verizon Wireless (U3029C), Defendant [for Relief from
Call Block Services], |
|
|
|
|
|
|
ALJ Houck |
A.17-01-001 – Application
of Suburban Water Systems (U339W) for Authority to Increase Rates Charged for
Water Service by $11,020,932 or 15.25% in 2018, by $6,148,017 or 7.38% in
2019, and by $5,543,562 or 6.20% in 2020, |
|
|
ALJ Haga |
A.16-10-002 – In the
Matter of Application of Calaveras Telephone Company (U1004C) to Review
Intrastate Rates and Charges, Establish a New Intrastate Revenue Requirement
and Rate Design, and Modify Selected Rates, |
|
|
Dates in parentheses following the word “also” are subject to change without notice. The assigned Commissioner’s name is listed next to the proceedings as matter of record; the assigned Commissioner may not be present at the hearing.
(PHC) = Prehearing Conference |
(WS) = Workshop |
(OA) = Oral Argument |
(PPH) = Public Participation Hearing |
(STC) = Status Conference |
(SEC) = Settlement Conference |
(EH) = Evidentiary Hearing |
(L&M) = Law & Motion |
(CA) = Closing Argument |
|
|
06/29/17 |
A.16-10-003 (TELEPHONIC –
PHC) – In the Matter of Application of Sierra Telephone Company, Inc.
(U1016C) to Review Intrastate Rates and Charges, Establish a New Intrastate
Revenue Requirement and Rate Design, and Modify Selected Rates, |
|
|
06/30/17 |
I.17-04-009 (PHC) – Order
Instituting Investigation on the Commission’s Own Motion into Why the
Commission Should not Impose Appropriate Fines and Sanctions Against
Rasier-CA LLC for Violating the Commission’s Decision 13-09-045, Safety
Requirement D by Failing to Comply with The Zero Tolerance Rules and Public
Utilities Code 5381, |
|
|
07/05/17 |
A.14-10-015 (PHC) - In
the Matter of the Application of AVALON FREIGHT SERVICES, LLC, a limited
liability company, for a certificate of public convenience and necessity
authorizing service to transport freight by vessel on a scheduled basis
between Port of Los Angeles, California on the one hand, and the Santa
Catalina Island location of Avalon, on the other hand; and on a nonscheduled
charter basis between Port of Los Angeles, California and Avalon, Two Harbors
and all points on Santa Catalina Island, and between any points on Santa
Catalina Island, |
|
|
07/06/17 |
A.17-01-001 (EH) – Application
of Suburban Water Systems (U339W) for Authority to Increase Rates Charged for
Water Service by $11,020,932 or 15.25% in 2018, by $6,148,017 or 7.38% in
2019, and by $5,543,562 or 6.20% in 2020, |
|
|
07/06/17 |
C.16-12-004 (EH) – DeJong
Brothers Farming, Robert Winters, Trustee of the Winters Revocable Trust,
Nicholas and Janie Gatzman, Trustees of the 2014 Gatzman Family Trust, and
Rhett and Ashley Burgess, Complainants, vs. Pacific Gas and Electric Company
(U39E), Defendant, |
|
|
07/10/17 |
A.15-09-013 (EH) – In
The Matter of the Application of San Diego Gas & Electric Company (U902G)
and Southern California Gas Company (U904G) for a Certificate of Public
Convenience and Necessity for the Pipeline Safety & Reliability Project, |
|
|
07/10/17 |
R.15-03-010 (WS) - Order
Instituting Rulemaking to Identify Disadvantaged Communities in the San
Joaquin Valley and Analyze Economically Feasible Options to Increase Access
to Affordable Energy in those Disadvantaged Communities, |
|
|
07/12/17 |
A.17-04-028 (PHC) - In
the Matter of the Application of Pacific Gas and Electric Company for
Approval of its 2018-2020 Electric Program Investment Charge Investment
Plan. (U39E), A.17-05-003 |
|
|
07/13/17 |
ECP – C.17-03-015 (EH) - Joe
Bustard, Complainant vs Verizon Wireless (U3029C), Defendant [for Relief from
Call Block Services], |
|
|
07/19/17 |
A.07-12-026 (PHC) - Application
of Calaveras Telephone Company (U1004C), Cal-Ore Telephone Co. (U1006C),
Ducor Telephone Company (U1007C), Happy Valley Telephone Company (U1010C),
Hornitos Telephone Company (U1011C), Kerman Telephone Co. (U1012C), The
Ponderosa Telephone Co. (U1014C), Sierra Telephone Company, Inc. (U1016C),
The Siskiyou Telephone Company (U1017C), Volcano Telephone Company (U1019C),
and Winterhaven Telephone Company (U1021C) for Ratemaking Determination
regarding Dissolution of Rural Telephone Bank, |
|
|
07/19/17 |
A.17-04-012 (TELEPHONIC –
PHC) - Application of Proper Sightseeing Corporation, a California
corporation, for Authority to Operate as a Scheduled Passenger Stage
Corporation with Hop On/Hop Off Service on Fixed Routes Between Points in
Hollywood, California and Santa Monica, California; and to Establish a Zone
of Rate Freedom, |
|
|
07/25/17 |
A.17-05-008 (PHC) - Application
of San Diego Gas & Electric Company (U902M) for Approval to Extend the
Mobilehome Park Utility Upgrade Program, A.17-05-007 |
|
|
07/27/17 |
R.16-02-007 (WS) - Order
Instituting Rulemaking to Develop an Electricity Integrated Resource Planning
Framework and to Coordinate and Refine Long-Term Procurement Planning
Requirements, |
|
|
07/27/17 |
A.16-06-013 (PPH) - Application
of Pacific Gas and Electric Company to Revise its Electric Marginal Costs,
Revenue Allocation and Rate Design. (U39M), |
|
|
07/28/17 |
A.17-04-024 (PHC) - In
the Matter of the Application of Mesa-Crest Water Company (U333W) and Liberty
Utilities (Park Water) Corp. (U314W) for an Order Authorizing Mesa-Crest
Water Company to Sell and Liberty Utilities (Park Water) Corp. to Purchase
the Utility Assets of Mesa-Crest Water Company, |
|
|
08/02/17 |
I.17-04-019 (PHC) - Order
Instituting Investigation to determine whether PacifiCorp (U901-E) engages in
least-cost planning on a control area basis and whether PacifiCorp's
Inter-Jurisdictional Cost Allocation Protocol results in just and reasonable
rates in California, |
|
|
08/03/17 |
A.17-02-003 (EH) - Joint
Application of Gill Ranch Storage, LLC, Northwest Natural Gas Company, NW
Natural Energy, LLC, and NW Natural Gas Storage, LLC for Change of Legal
Ownership and Control of Gill Ranch Storage, LLC Through a Corporate
Reorganization (U914G), |
|
|
08/03/17 |
A.16-10-020 (EH) - Application
of San Pablo Bay Pipeline Company LLC (PLC29) for authority, pursuant to
Public Utilities Code Section 455.3, to increase its rates for pipeline
transportation services within California, |
|
|
08/07/17 |
A.16-09-003 (EH) - Application
of Southern California Edison Company (U338E) for Approval of its 2016 Rate
Design Window Proposals, |
|
|
08/08/17 |
R.14-10-003 (WS) - Order
Instituting Rulemaking to Create a Consistent Regulatory Framework for the
Guidance, Planning and Evaluation of Integrated Distributed Energy Resources, |
|
|
08/09/17 |
A.16-12-002 (EH) - Joint
Application of Southern California Edison Company (U338E) and San Diego Gas
& Electric Company (U902E) For Cost Recovery Of The Wheeler North Reef
Expansion Project Marine Mitigation Costs, |
|
|
08/14/17 |
A.17-01-005 (EH) -
Application of the San Diego Association of Governments for an order
authorizing construction of two light-rail vehicle tracks grade separated
above I-5 (South), I-5 (North) and grade separated below I-8, SR-52 in the
City of San Diego, San Diego County, California, |
|
|
08/14/17 |
A.16-06-013 (PPH) - Application
of Pacific Gas and Electric Company to Revise its Electric Marginal Costs,
Revenue Allocation and Rate Design. (U39M), |
|
|
08/15/17 |
A.16-06-013 (PPH) - Application
of Pacific Gas and Electric Company to Revise its Electric Marginal Costs,
Revenue Allocation and Rate Design. (U39M), |
|
|
08/17/17 |
A.15-07-019 (EH) - Application
of California-American Water Company (U210W) for Authorization to Modify
Conservation and Rationing Rules, Rate Design, and Other Related Issues for
the Monterey District, |
|
|
09/05/17 |
A.16-10-019 (EH) -
Application of Pacific Gas and Electric Company to Recover Costs Recorded in
the Catastrophic Event Memorandum Account Pursuant to Public Utilities Code
Section 454.9(U39E), |
|
|
09/06/17 |
A.17-02-005 (EH) - Application
of Pacific Gas and Electric Company for Compliance Review of Utility Owned
Generation Operations, Electric Energy Resource Recovery Account Entries,
Contract Administration, Economic Dispatch of Electric Resources, Utility
Owned Generation Fuel Procurement, Diablo Canyon Seismic Studies Balancing
Account, and Other Activities for the Period January 1 through December 31,
2016 (U39E), |
|
|
09/11/17 |
C.17-05-002 (PHC) - Tara
Broadcasting, LLC dba KAKZ Television, Complainant vs Southern California
Edison Company (U338E), Defendant [for Relief that the Billing Corrections
for the Period of November 1, 2013 though and Including April 4, 2017 be
vacated and cancelled.], |
|
|
09/12/17 |
A.16-10-019 (EH) - Order
Instituting Rulemaking to Implement Portions of AB 117 Concerning Community
Choice Aggregation |
|
|
09/18/17 |
A.16-03-004 (EH) - Joint
Application of Southern California Edison Company (U338E) and San Diego Gas
& Electric Company (U902E) For the 2015 Nuclear Decommissioning Cost
Triennial Proceedings, A.15-01-014 |
|
|
09/25/17 |
A.17-01-020 (EH) - Application
of San Diego Gas & Electric Company (U902E) for Approval of SB 350
Transportation Electrification Proposals, |
|
|
10/17/17 |
A.07-01-031 (EH) - In
the Matter of the Application of Southern California Edison Company (U338E)
for a Permit to Construct Electrical Facilities with Voltages between 50kV
and 200 kV: Valley-Ivyglen 115 kV Subtransmission Line Project, |
|
|
10/24/17 |
A.16-03-004 (STC) - Joint
Application of Southern California Edison Company (U338E) and San Diego Gas
& Electric Company (U902E) For the 2015 Nuclear Decommissioning Cost
Triennial Proceedings, |
|
|
(A quorum of Commissioners and/or their staff may attend All-Party Meetings noticed on the Daily Calendar.)