3. Interruptible Programs

3.1. Extend Rolling Blackout Reduction Program


Issue: Should any program scheduled to terminate before December 31, 2001 be extended from its scheduled termination date to December 31, 2002.

3.1.1. Program Type, Cost, Pollution, and "Free Riders"

3.1.2. Relation to OBMC

3.2. Duration of All Programs


Issue: Should programs scheduled to terminate on December 31, 2002 be extended, and, if so, should megawatt and total program dollar limits adopted in D.01-04-006 be modified.

3.2.1. Extend to Next General Rate Case or Similar
Proceeding

3.2.2. Modified Capacity and Dollar Limits

3.2.3. Utility Reports

3.2.4. Program Consolidation

3.2.5. Cost Benefit Analysis

3.3. Bill Limiter


Issue: Should the bill limiter provision currently reflected in the interruptible program tariffs of SCE terminate on March 31, 2002.

3.3.1. Background

3.3.2. Termination

3.3.2.1. Public Utilities Code Section 368(a)

3.3.2.2. Bill Limiter Has Served Its Purpose

3.3.2.3. Bill Limiter and SCE/CPUC Settlement Agreement

3.3.3. Limited Opt-Out

3.4. Aggregation of More Than Two Circuits for
OBMC


Issue: Is it necessary or feasible to develop a tariff option for aggregation of more than two circuits with a single lead customer for the purpose of participation in the OBMC program (D.01-06-087, Ordering Paragraph 3).

3.5. Alternate Workweeks


Issue: Should the 10-day baseline for purposes of participation in the OBMC program recognize alternate workweeks, as proposed by Cal Steel (D.01-06-087, page 14).

3.6. Other Modifications


Issue: Should other modifications and consolidations be adopted.

3.6.1. SLRP


"...the energy usage during the on-peak period for the four weekdays following a curtailment, unaffected by program operations and excluding holidays, will be evaluated and cannot exceed the customer's posted baseline amount."


"...the energy usage during the on-peak period for the four weekdays following a curtailment, unaffected by program operations and excluding holidays, will be evaluated and cannot exceed the customer's posted baseline amount by more than 15%."

3.6.2. OBMC

3.6.2.1. Similar Days

3.6.2.2. Temperature Correction

3.6.2.3. Stage 1 and 2 Days

3.6.2.4. Real Time Profile Option

3.6.2.5. Days to Exclude From Baseline

3.6.2.6. Minimum 30-Minute Notice

3.6.2.7. Monthly Interruptible Contract Requirements

3.6.2.8. Lead Customer

3.6.2.9. Costs Allocated to Large Customers

3.6.3. CCPCFA Comments

3.6.3.1. Existing Programs and Load Aggregators


"create and fund through...[utility] rates an interruptible program that had a capacity payment either to an individual customer or an aggregator of customers in exchange for the right to interrupt load on short notice at a specified number of hours per year." (CCPCFA letter to Commissioner Wood dated October 30, 2001.)

3.6.3.2. Program Potential

3.6.3.3. Cycling of Air Conditioners


"The CEC estimates that 14,000 MW of air conditioning load (28% of total load) occurs during the state's summertime peak demand of 50,000 MW...


This is a potentially vast, untapped source of interruptible electricity. Properly partnered with companies such as Comverge, respondent utilities and ratepayers can enjoy benefits with the providing company taking the financial risk. This opportunity needs further exploration.


Therefore, we order PG&E and SDG&E to explore reasonable options for implementing air conditioner cycling, and other electric motor interruption, programs targeted to residential and commercial customers...


PG&E...and SDG&E shall each file and serve an advice letter no later than May 1, 2001. The advice letter shall analyze and report on alternatives, and seek approval of the most reasonable alternatives, including proposed tariffs for implementation...


We caution PG&E and SDG&E that we are convinced one or more air conditioning cycling programs should be approved in each service area. This is the opportunity for PG&E and SDG&E to propose what each believe are the best options for their areas. That is, the advice letters of PG&E and SDG&E should seek approval of the options that each utility finds most reasonable." (D.01-04-006, mimeo., pages 35-36; also see Ordering Paragraph 1 and Attachment A, Item 2.3.4.)

3.6.3.4. CCPCFA Loan And Repayment

3.6.3.5. Capacity Payment

3.6.3.6. Conclusion

3.6.4. SDG&E EAEI Program

3.6.5. CEC Proposals

3.6.5.1. Surcharge

3.6.5.2. Replace DBP With VDRP

3.6.5.3. Pilot Test of Modified BIP

3.6.6. SCE Petition for Modification Regarding Changes
to FSLs

3.6.6.1. Background

3.6.6.2. Discussion


"It is reasonable to allow customers to periodically reassess their situations and either opt-out or change firm service levels to better match current market and business realities with their abilities to interrupt load." (Id., page 15.)


"In addition to this opt-out or readjustment, lifting the suspension means customers may annually reassess and make changes as necessary beginning in November 2001." (Id., page 17.)

6 In its November 16, 2002 Reply Comments, TURN states that energy payments paid to interruptible customers in a pay-for-performance incentive should be net of avoided energy charges. TURN's reply comments state that SCE's interruptible customers would avoid paying $0.20/kWh in energy payments during on-peak hours. Thus, it appears that TURN's new program might pay up to $0.80/kWh and $0.30/kWh (rather than up to $1.00/kWh and up to $0.50/kWh), at least on SCE's system. Assuming this is a correct reading of TURN's proposal, and that SDG&E's on-peak energy charges are similar to SCE's, TURN does not explain why $0.20/kWh for RBRP is excessive compared to a net payment of $0.80/kWh or $0.30/kWh. 7 SCE tendered a notice of intent (NOI) in December 2001 to file a general rate case (GRC) application. We expect a rate design decision for SCE by November 2003. PG&E has proposed that it tender an NOI by April 15, 2001. (See draft decision in I.01-12-010.) If PG&E's proposal is adopted, we expect a rate design decision for PG&E by December 2003. SDG&E will file a cost of service application about December 2002 for test year 2004 (D.01-10-030), and rate design will follow in a later phase of the cost of service application, or a rate design window proceeding. In either event, we expect a rate design decision for SDG&E by April 2004. Absent action to modify or terminate programs in those subsequent proceedings, we expect that programs will continue. 8 As discussed more below, PG&E Advice Letter 2110-E regarding a proposed air-conditioning cycling program will be addressed by a subsequent decision or resolution. That decision or resolution may include an increase in program limits for PG&E, if necessary. 9 Public Utilities Code Section 743.1(b) currently states in pertinent part that "[i]n no event shall the level of the pricing incentive for interruptible or curtailable service be altered from the levels in effect on June 10, 1996, until March 31, 2002." 10 Firm service level (FSL) is the load level to which the customer agrees to reduce when requested by the utility pursuant to interruptible service tariffs. 11 The VDRP was authorized in April 2001 (D.01-04-006), and replaced by the DBP in July 2001 (D.01-07-025). 12 The original VDRP, the DBP, and the CEC's proposed VDRP for 2002 all rely on a 10-day baseline to measure the customer's load reductions. (D.01-04-006, Attachment A, Item 2.2.2; D.01-07-025, Attachment A, Item 2.6.3.7.) 13 These are (1) former ISO demand relief participants, (2) existing CEC Assembly Bill 970 program participants, (3) prospective CCPCFA loan program participants, and (4) other participants with peak demand greater than 200 kW. 14 CEC reports that PG&E, SCE and SDG&E have about 14,435 customers in the 200 kW to 500 kW range. Program implementation costs for 14,000 new customer participants in this kW range at a cost of $2,500 per customer would be $35 million. Incentive payments of $7/kW-month for 14,000 customers each contributing an average of 75 kW of load reduction would be about $88 million per year. 15 See I.00-11-001. 16 Committed load reduction of 50 MW would require payments of $4.8 million per year at $8/kW-month. 17 SCE reports that its closed interruptible rate schedules are Schedules I-6, RTP-2-I, and TOU-8-SOP-I.

Previous PageTop Of PageNext PageGo To First Page