4. Curtailment Priorities

4.1. Hospitals With Fewer Than 100 Beds


Issue: What is the effect of including hospitals with fewer than 100 beds on the list of essential customers, including the effect on the number of circuits and megawatts that are available for rotating outage. (D.01-04-006, Ordering Paragraph 12, as renumbered by D.01-04-009.)


"...we have little specific information on the effect of this change. We order this change because we are persuaded by the limited information we now have that rural hospitals have an immediate need for protection during the crisis we face for Summer 2001. We will revisit this issue in Phase 2, however. We direct that respondent utilities submit specific information in Phase 2 on the effect this change has had on mandatory curtailments, and the effect on the number of circuits and megawatts that are available for rotating outage." (D.01-04-006, mimeo., page 64.)


Note: These results are based on assuming all customers conditionally awarded Category M status (D.01-09-020) submit their Statement of Authenticity and become fully included in Category M.

4.2. Skilled Nursing Facilities


Issue: What is the effect of including skilled nursing facilities on the list of essential customers normally excluded from rotating outages. (D.01-04-006, Ordering Paragraph 13, as renumbered by D.01-04-009.)

4.2.1. Background


"to provide specific information no later than in Phase 2 on the effect of extending this exemption [from rotating outages] to skilled nursing facilities, including the number of circuits and megawatts removed from rotating outages. The evaluation will include an estimate of the resulting effect, if any, on mandatory curtailments, and the 40% criterion. Finally, respondent utilities must also consider circuit reconfigurations in Phase 2 that would narrow exempted load by isolating skilled nursing facilities." (D.01-04-006, mimeo., page 66; Ordering Paragraph 13, as renumbered by D.01-04-009.)


"that the population within SNFs...is among the most vulnerable in our society. Some of these patients would have been in acute care hospitals a few years ago, but are now discharged to SNFs..." (D.01-09-020, mimeo., page 19.)

4.2.2. Data

4.2.3. DHS Certification and Category C

4.2.4. Circuit Reconfiguration Studies

4.2.5. Other Conditions

4.2.6. Self-Generation

4.3. Category M


Issue: What procedures, if any, should be adopted to consider continuing the essential customer status for those customers granted Category M status in D.01-09-020 past September 6, 2003.


Issue: What procedures, if any, should be adopted to consider additions to, or subtractions from, the list of Category M customers adopted in D.01-09-020 for the period after September 6, 2003.

4.3.1. Expiration on September 6, 2003

4.3.2. Backup or Self-Generation

4.3.3. Energy Efficiency Alternatives

4.3.4. Eliminate Category M

4.3.5. Reminder of Notice

4.4. Water and Sewer Utilities


Issue: What additional measures, if any, should the Commission adopt for normally exempting water and sewer utilities from rotating outages based on public health and safety.

4.4.1. Background

4.4.2. Notification and Testing of Category H Procedures

4.4.3. Backup Generation

4.4.4. LAC and SCE Proposed Language


"Water and sewage treatment utilities or firefighting entities may request immediate partial or complete rotating outage exemption from electric utilities in times of emergency identified as requiring their service, such as [fire] fighting fires." (Additions underlined, deletion in brackets.)

4.4.4.1. "Firefighting Entities"


"Respondent utilities should comply with valid orders of responsible police or fire authorities, and other authorities with emergency powers, to exempt a circuit from outage, or order a circuit re-energized, based on public health and safety. To the extent such orders are implemented, however, they must be executed to the extent reasonable and necessary in coordination with, and with the agreement and approval of, the California Independent System Operator (CAISO). The CAISO must be involved as necessary so that such action will not jeopardize a widespread system collapse.


"Respondent utility must coordinate as needed with the CAISO since a local emergency official cannot be expected to know and consider the status of the entire statewide electrical system. When properly coordinated and approved with the CAISO as needed, however, respondent utility should comply with valid orders of responsible local emergency officials.


"...we agree with SDG&E...that respondent utilities may implement a valid order from responsible police, fire, or similar authority with emergency powers, for immediate protection of public health and safety when jeopardy or danger is imminent, to the extent properly coordinated with the CAISO, as needed.


While we make this clarification at SDG&E's request, we decline to modify the list of essential customers. SDG&E does not allege that it lacks the authority to respond to a proper order of responsible local authority with emergency powers, and we are not convinced that respondent utilities lack that authority. To prevent any possible confusion, we clarify that respondent utilities may do so when properly coordinated with the CAISO. We are not convinced, however, that this must be explicitly stated in an amendment to the list of essential customers in the Priority System for Rotating Outages." (D.01-05-089, mimeo., pages 5-7.)

4.4.4.2. "Immediate"

4.4.4.3. "Fighting Fires"

4.4.4.4. Effort of Joint Parties

4.4.4.5. Decline Limited Permanent Exemption

4.4.5. Amount of Time for Service Restoration


"SCE and LAC are jointly developing an expedited notification process by which LAC can contact SCE at the time fire resources are dispatched, so that SCE can begin immediately processing the exemption request at the earliest opportunity after the fire emergency is identified." (Joint Supplemental Comments, December 21, 2001, page 4; emphasis added.)

18 The Energy Division Director has authorized the following circuit reconfiguration projects: 223 circuits representing 905 MW for PG&E, 169 circuits representing 575 MW for SCE, and 30 circuits representing 171 MW for SDG&E. This totals 422 circuits representing 1,651 MW. 19 With the exception of hospitals (essential customer Category C) and SNFs (which we address below), utilities must evaluate the adequacy of standby generating equipment for all essential use customers, and consider removing them from the list of essential customers. (D.82-06-021 (June 2, 1982), Findings of Fact 2 and 3, Cal. PUC LEXIS 537; D.01-04-006, mimeo., page 65.) 20 Category M provides an opportunity for an individual customer to be classified as an essential customer (i.e., normally excluded from rotating outage). To qualify, the customer must show that inclusion of the customer in a rotating outage presents unacceptable jeopardy, or imminent danger, to public health and safety. The jeopardy or danger must be beyond economic harm or inconvenience to the customer. Rather, it must be jeopardy or danger to wider public health and safety. (D.01-05-089, mimeo., page 3.) 21 The 40.6% result for PG&E may be closer to about 43%, however. This is because PG&E has already been authorized by the Energy Division Director to complete circuit reconfiguration projects on 223 circuits totaling 905 MW, and not all of those reconfigurations are reflected in the 40.6% result. 22 This reaffirms but does not increase existing dollar limits. 23 This is still the case today. SCE reports, for example, that it has nearly 9,000 water and wastewater service accounts, of which approximately 4,300 are subject to rotating outages, representing 7,000 MW, or 31% of SCE's load. 24 In many, if not all, instances this is actually re-notification. For example, SDG&E points out that it has formal procedures in place for water utilities to use when a Category H exemption is required, and has already informed water utilities of these procedures. 25 This includes public and privately owned utilities, agencies, districts, and any other water or sewer entity that is a customer of respondent utility. 26 Rule 2.3 of the Commission's Rules of Practice and Procedure. 27 LAC represents a large body of interests. According to LAC, the LAC Fire Department protects an area of 2,278 square miles with a population of 3.8 million people, of which a total of 998 square miles meets the criteria of Very High Fire Hazard Severity Zone, or Fire Zone 4. 28 SCADA stands for Supervisory Control and Data Acquisition (SCADA). SCADA-controlled circuit switching devices are remotely controlled.

Previous PageTop Of PageNext PageGo To First Page