Word Document PDF Document |
ALJ/CAB/sid DRAFT Agenda ID #3438
Ratesetting
5/27/2004 Item 39
Decision PROPOSED DECISION OF ALJ BROWN (Mailed 4/6/2004)
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking to Establish Policies and Cost Recovery Mechanisms for Generation Procurement and Renewable Resource Development. |
Rulemaking 01-10-024 (Filed October 25, 2001) |
(See Appendix A for a list of appearances.)
OPINION APPROVING MOTION OF SAN DIEGO GAS & ELECTRIC
COMPANY (U 902 E) FOR APPROVAL TO ENTER INTO NEW
ELECTRIC RESOURCE CONTRACTS RESULTING FROM
SDG&E'S GRID RELIABILITY REQUEST FOR PROPOSAL
TABLE OF CONTENTS
Title Page
OPINION APPROVING MOTION OF SAN DIEGO GAS & ELECTRIC
COMPANY (U 902 E) FOR APPROVAL TO ENTER INTO NEW
ELECTRIC RESOURCE CONTRACTS RESULTING FROM
SDG&E'S GRID RELIABILITY REQUEST FOR PROPOSAL 2
I. Summary 2
II. Background 2
A. San Diego Gas & Electric Company 4
B. The Basis for SDG&E's RFP 7
C. Preparation and Circulation of the RFP 9
D. Bid Evaluation 11
E. Proposed Projects Resulting From the RFP Process 13
III. Summary of Parties' Positions 14
A. SDG&E 14
B. TURN/UCAN 14
C. ORA 15
D. PG&E 16
E. Coral Power 18
F. InterGen 19
G. Dynegy 21
H. Celerity 22
I. Nevada Hydro 24
J. SER 26
K. Calpine 26
IV. Discussion 27
A. Demand Response: Comverge 32
B. Demand Response: Celerity 36
C. Renewable: Envirepel 38
D. Ramco 39
E. Palomar 43
F. Otay Mesa 50
a) Reasons to Approve the PPA 56
b) Commission Involvement 57
c) There Was No Unfairness in the RFP Process 61
d) Consideration of Otay Mesa Should Not Be Deferred to the New LTRP Proceeding 63
e) SDG&E's Need for Otay Mesa Power 65
f) The Benefits of a 10-Year PPA 66
g) Transmission Upgrades 67
h) SDG&E's Conditions 68
G. The Value of This RFP Process 68
H. Procedural Issues 70
V. Comments on Proposed Decision 74
VI. Assignment of Proceeding 74
Findings of Fact 74
Conclusions of Law 80
ORDER 81
Appendix A - List of Appearances
OPINION APPROVING MOTION OF SAN DIEGO GAS & ELECTRIC
COMPANY (U 902 E) FOR APPROVAL TO ENTER INTO NEW
ELECTRIC RESOURCE CONTRACTS RESULTING FROM
SDG&E'S GRID RELIABILITY REQUEST FOR PROPOSAL
In this decision, we approve the five proposals that SDG&E presented to meet its short-term and long-term grid reliability needs. These proposals were the result of an open and competitive Request for Proposal (RFP) process that solicited bids from all qualified resources, including turn-key natural gas-fired generating units, power purchase agreements (PPA), demand response programs, and renewable resources. Out of 22 bids received, these five proposals were identified as conforming to the RFP specifications and were found to be the least cost/best fit choices for meeting the utility's need to have a diversified portfolio of resources to meet its customers grid reliability needs, are consistent with SDG&E's long-term resource plan (LTRP), benefit consumers, and are in the public interest. The proposals include a demand response program from Comverge, a renewable resource contract with Envirepel, and contracts for three gas-fired facilities, Ramco, Palomar, and Otay Mesa. Ramco is a turn-key combustion turbine intermediate unit, Palomar is a turn-key 500/555 MW combined-cycle power plant, and Otay Mesa is a 10-year PPA for a 485/573 MW combined cycle facility.
In addition, we authorize SDG&E to continue negotiations with Celerity on a demand response contract.