Requirements for Awards of Compensation

The intervenor compensation program, enacted in Pub. Util. Code §§ 1801-1812, requires California jurisdictional utilities to pay the reasonable costs of an intervenor's participation if the intervenor makes a substantial contribution to the Commission's proceeding. The statute provides that the utility may adjust its rates to collect the amount awarded from its ratepayers.

All of the following procedures and criteria must be satisfied for an intervenor to obtain a compensation award:


1. The intervenor must satisfy certain procedural requirements including the filing of a sufficient notice of intent (NOI) to claim compensation within 30 days of the PHC (or in special circumstances, at other appropriate times that we specify). (Section 1804(a).)


2. The intervenor must be a customer or a participant representing consumers, customers, or subscribers of a utility subject to our jurisdiction. (Section 1802(b).)


3. The intervenor should file and serve a request for a compensation award within 60 days of our final order or decision in a hearing or proceeding. (Section 1804(c).)


4. The intervenor must demonstrate "significant financial hardship." (Sections 1802(g), 1804(b)(1).)


5. The intervenor's presentation must have made a "substantial contribution" to the proceeding, through the adoption, in whole or in part, of the intervenor's contention or recommendations by a Commission order or decision. (Sections 1802 (h), 1803(a).)


6. The claimed fees and costs are comparable to the market rates paid to experts and advocates having comparable training and experience and offering similar services. (Section 1806.)

For discussion here, the procedural issues in Items 1-4 above are combined, followed by separate discussions on Items 5 and 6.