ALJ/DUG/avs Date of Issuance 1/11/2008
Decision 08-01-021 January 10, 2008
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
FINAL OPINION ON RECOVERY BY PACIFIC GAS AND ELECTRIC COMPANY FOR A CATASTROPHIC EVENT MEMORANDUM ACCOUNT RELATED TO THE 2005-2006 NEW YEAR'S STORMS
TABLE OF CONTENTS
Title Page
FINAL OPINION ON RECOVERY BY PACIFIC GAS AND ELECTRIC COMPANY FOR A CATASTROPHIC EVENT MEMORANDUM ACCOUNT RELATED TO THE 2005-2006 NEW YEAR'S STORMS 22
4.2. Standard for Approval of a Settlement 44
5.1. Eligibility for CEMA Recovery 77
5.2. The Settlement is Reasonable 99
APPENDIX A
FINAL OPINION ON RECOVERY BY PACIFIC GAS AND ELECTRIC COMPANY FOR A CATASTROPHIC EVENT MEMORANDUM ACCOUNT RELATED TO THE 2005-2006 NEW YEAR'S STORMS
This opinion allows Pacific Gas and Electric Company (PG&E) to recover the settlement amount for 2005-2006 New Year's Storms' costs recorded in a Catastrophic Event Memorandum Account (CEMA). The adopted electric revenue requirement is $12,138,000, including interest through December 31, 2010, franchise fees, and uncollectibles, to be collected in rates beginning January 1, 2008, with $9,333,000 collected in rates in 2008, $1,431,000 in 2009, and $1,374,000 in 2010. PG&E will record the CEMA revenue requirement in its Distribution Revenue Adjustment Mechanism ($11,460,000) and to the Utility Generation Balancing Account ($503,000) for rate recovery through the Annual Electric True-up advice letter. (Settlement, p. 3.) This decision also resolves PG&E's ex parte violations. This proceeding is closed.