1. Has an initial term of 34 years, with 6 automatic renewal terms of 10 years each;

2. Requires the construction of test wells, the data from which will be analyzed by MCWRA to ensure compliance with the Agency Act (such that groundwater is not exported from the Salinas Valley Groundwater Basin);

3. Addresses financing for the project facilities, which for MCWD and MCWRA is to include low-cost State Revolving Fund loans, as well as grants, where available, which is expected to lower the cost of the Regional Project. Cal-Am will provide shortfall financing for the project, if necessary;

4. Pursuant to the Outfall Agreement, MCWD will connect and use capacity in the ocean outfall components of MRWPCA's regional treatment plant to carry the reject water and brine discharged from the desalination plant. MCWD will pay all costs related to the construction of a connection to the MCWD facilities and a brine receiving facility that are attributable to and used for the discharged brine. The Outfall Agreement also provides for a one-time capacity charge that MCWD will pay to MRWPCA and fair and reasonable O&M costs attributable to MCWD's use of the brine-receiving facility and the outfall discharge, as well as capital repair and replacement costs. Like the Water Purchase Agreement, the term of the Outfall Agreement is 34 years, with 6 automatic 10-year renewals;

5. Whether the facilities are owned and operated by MCWD, MCWRA, or Cal-Am, the costs of the entire project are expected to be borne by Cal-Am ratepayers. MCWD's and MCWRA's costs of constructing and operating their portions of the Regional Project facilities will be included in the calculation of the costs of the desalinated water (or product water), which will be charged to Cal-Am under various provisions of the WPA. In addition, all costs incurred by MCWD under the Outfall Agreement will be included in the cost of the product water;

6. As proposed in the Settlement Agreement, all costs addressed in the Water Purchase Agreement or Outfall Agreement and any shortfall financing provided by Cal-Am will be considered to be reasonable and prudently incurred, if approved by the Commission. Costs for the Regional Project include capital costs, financing costs, costs of obtaining indebtedness, a reserve fund for needed replacements, contingency costs, and O&M costs;

7. Cal-Am proposes to recover the costs of the product water through a Modified Cost Balancing Account, which is currently used to recover the costs of purchased water;

8. For the Cal-Am facilities, Settling Parties propose that, once constructed, the conveyance, pumping, and reservoir facilities will be designated as used and useful for ratemaking purposes, even if the Regional Project is delayed for some reason. The parties contend that this approach is reasonable because these facilities provide important utility services that resolve two operational limitations of Cal-Am's existing distribution system: 1) the facilities will allow Cal-Am to maintain adequate water levels in the Forest Lake tanks during maximum day demand and 2) the facilities will allow Cal-Am to move water from the Seaside area to the rest of the Monterey Peninsula. Cal-Am states that resolving these operational issues will provide increased storage to meet emergency and fire conditions and will increase fire flow capability to Seaside, Monterey, and Pacific Grove. The transfer pipeline used to deliver desalinated water downstream from the delivery point to the Cal-Am facilities throughout its distribution system will not be deemed used and useful until the Regional Project is completed. Cal-Am will include costs related to the construction of its facilities in rate base, either as Construction Work in Progress or Utility Plant in Service. Settling Parties propose that all project costs will earn a return on the carrying costs for the project (i.e., Allowance for Funds Used During Construction (AFUDC) until such time as they are allowed in rate base;

9. Cal-Am plans to file semi-annual advice letters to move the costs into rate base and Cal-Am will continue to adjust base rates until the entire project is closed out to Utility Plant in Service. Cal-Am proposes to file Tier 2 advice letters to modify rate base and to adjust rates; and

10. Finally, Settling Parties recognize the significant rate impact of the Regional Project and recommend that the Commission expand eligibility of customers for Cal-Am's low-income ratepayer assistance program and adopt a more progressive rate design.

52 Motion to Approve Settlement Agreement at 5-6.

53 Exhibit 357.

54 Exhibit 361 at 2-3.

55 Although the Motion to Approve Settlement Agreement asks that the Commission approve both the Water Purchase Agreement and the Outfall Agreement, parties have clarified on the record that they do not expect the Commission to approve or have oversight over the Outfall Agreement, which is an agreement exclusively between MCWD and MRWPCA.

Previous PageTop Of PageNext PageGo To First Page