Constructability Review: The Parties in consultation with the Project manager and the Advisory Committee, in accordance with Best Industry Practices, shall appoint a qualified Person or committee of qualified Persons who is/are independent from any Person or Persons who have designed any portion of the Project Facilities to review each of the Preliminary Design Documents, Procurement Documents and 100% Construction Documents, as appropriate, in order to provide an effective constructability review to assure that (i) the project Facilities as detailed in the Preliminary Design Documents, Procurement Documents and 100% Construction Documents, can be constructed using construction methods, materials and techniques in compliance with Best Industry Practices; (ii) the Preliminary Design Documents and Procurement Documents provide the contractor or contractors, as applicable, with clear, concise information that can be utilized to prepare a competitive cost-effective proposal; (iii) the Regional Desalination Project when constructed in accordance with the Preliminary Design Documents, Procurement Documents and 100% Construction Documents will result in a Regional Desalination Project that can be maintained in a cost-effective manner by the Parties throughout the Term of this Agreement; and (iv) the Project Facilities when constructed shall consider the lowest achievable lifecycle cost to operate and maintain the Project Facilities over their useful life.57

Inspection and Audit Rights: Each Party and Project Manager shall have the right to review and audit the progress reports, progress payments, and other related information, including the right to independent inspection of each other Party's work in progress with respect to the Regional Desalination Project. During the progress of the work through Substantial Completion, each Party shall at all times during normal working hours afford the other Parties, their consultants, and Project Manager and appropriate regulatory representatives every reasonable opportunity for observing work in progress by such Party's contractors. . .58

All costs of the Parties pursuant to this Agreement shall be reasonably and prudently incurred. All payments made by CAW under this Agreement shall be deemed reasonable and to the extent practicable be included in the cost of Product Water. To the extent not already included in the CAW Product Water Contract approved rate recovery, any CAW costs, fees and expenses incurred under this Agreement that are not CAW Regional Desalination Project Related Expenses or CAW Project Administration and Oversight Expenses shall be included in the O&M Costs and shall be included in and recovered by CAW from the cost of the Product Water.

The basis for the Exhibit C costs is included in the April 15, 2010 Project Cost Comparison. The costs included in Exhibit C assume that the intake facilities will include all slant wells, that there will be a different connection point for introduction of the desalinated water in the MCWD distribution system that requires a 12,750 foot long, 24-inch diameter MCWD tie-in pipeline, that there will be no MCWD buy-in fees, and that the costs will be at the high end of the cost estimating range as established by the Association for the Advancement of Cost Engineering (AACE). The resulting cost estimate included in Exhibit C is $240 million for the most probable cost, and $282 million at the high end of the accuracy range. These costs include all costs of the Regional Desalination Project except the costs of the CAW facilities (i.e., they include the costs to deliver desalinated water to the Delivery Point, or otherwise stated, all project costs upstream of the Delivery Point). The Exhibit C costs in the WPA also include $15 million for the Reserve Fund Payment Account and the costs of obtaining indebtedness, bringing the total Exhibit C costs in the WPA to $297 million.76

CAW enjoys cost savings of $127 million on a present value basis by participating in the Regional facility rather than the North Marina project. This savings is attributed to scale economies, lower processing costs and MCWD's capital contribution. This corresponds to Lyndel Melton's Scenario 2 cost estimate89. . . Accounting for low cost municipal financing that would not be available absent MCWD participation results in savings of $493 million. Accounting for this financing and State Revolving Fund (SRF) funding and grants, savings grow to $578 million. This corresponds to Lyndel Melton's Scenario 690. . . At the same time, MCWD's savings are very modest. Economies of scale and process savings total about $7 million. Accounting for financing, MCWD's benefits total $27 million.

Overall, MCWD's benefits are much lower than CAW's benefits because MCWD does not need desalination project water for an extended period - perhaps ten years or more - and as a consequence the savings must be discounted accordingly.91

In addition to considering the off-taker's credit rating, the rating agencies will consider the impact of the transaction, as either a capital lease or a take-or-pay contract, on California American Water in calculating the credit metrics of California American Water for purposes of financing the project. While the parties to the WPA will use reasonable efforts to obtain the maximum amount of financing on the best terms, it is reasonably possible that the cost of financing the project could range as high as nearly 9 percent. (footnote omitted.) The lenders would likely add a 75 basis point premium to the project financing, consistent with the rating agencies' cap of the overall rating of the project at two notches below the off-taker rating. (footnote omitted.) Thus, "given California American Water's position as the off-taker, the rating agencies would adjust the credit worthiness of the project if California American Water's credit rating is below the typical range, and thus the project financing would depend largely upon California American Water's credit quality."100 As such, the Settling Parties have recognized that it is critical for the Commission to address the financial viability of California American Water as a result of the transaction."101

In establishing rates for recovery of the costs of used and

useful water plant, the commission may utilize a capital structure and payback methodology that shall maintain the reliability of water service, shall minimize the long-term cost to ratepayers, shall provide equity between present and future ratepayers, and shall afford the utility an opportunity to earn a reasonable return on its used and useful investment, to attract capital for investment on reasonable terms and to ensure the financial integrity of the utility.

Unless consented to in writing by CAW, in no event shall MCWD seek or cause to have more than 1,700 AFY of Product Water (at the MCWD Meter) deemed to be MCWD Permanently Allocated Product Water or apply for or seek to obtain or establish any right, title, permit or permission to have more than an aggregate of 1,700 AFY of Product Water (at the MCWD Meter) deemed to be MCWD Permanently Allocated Product Water.125

56 Exhibit 301, Water Purchase Agreement, § 4.3(f) at 26. The Prime Agreements are construction contracts and service agreements required for the design, permitting, and construction of each Party's facilities (Water Purchase Agreement, § 4.4(b)).

57 Exhibit 301, WPA, § 4.6 at 28.

58 Id. § 4.11 at 31.

59 DRA Opening Brief at 2.

60 Exhibit 301, WPA § 11 at 53.

61 Exhibit 202 at 4-32, Footnote 44, 4-33, and DRA Opening Brief at 13.

62 Id.

63 DRA Opening Brief at 6, citing Settlement Agreement at § 10.1.

64 DRA Opening Brief at 8, citing Exhibit 204 at 18. Bureau of Reclamation (BOR) points out that annualized capital costs for this project exceed this formula.

65 Id.

66 DRA Opening Brief at 12.

67 DRA Opening Brief, citing Exhibit 201 at i.

68 MPWMD Opening Brief at 22.

69 Id. at 29.

70 Id.

71 Exhibit 319 at 26-28.

72 Exhibit 319 at 29, RT 1059 at 4-7.

73 Cal-Am Reply Brief at 9.

74 Exhibit 320 at 2.

75 Based on the most probable estimated costs, Exhibit 319 at 13 and MCWD Opening Brief at 44.

76 Exhibit 319 at 6-7.

77 Exhibit 319 at 23.

78 The Unified Financing Model was based on DRA's recommended approach to analyzing revenue requirements and was jointly developed by the parties during the May 2010 workshops.

79 In Section 11.3.1, we provide further discussion on the impact of various financing options, based on Appendix D, which is based on the various scenarios in Exhibit 113.

80 Exhibit 319 at 24.

81 Exhibit 202 at 4-34, citing Cal-Am Data Request Response CWP 54-2(a).

82 Exhibit 202 at 4-34.

83 DRA argues that the costs included in Table 2 for the Moss Landing Project and the North Marina Project are overstated by $14 million in pre-effective date costs for the Public Agencies, and notes that litigation costs are included only for the North Marina Project. These particular litigation costs appear to be associated with land condemnation and groundwater transfer out of the Salinas Basin (Zone C). If we removed the pre-effective date costs from the North Marina and Moss Landing Projects, the estimated costs of those projects would be reduced to $225 million and $252 million, respectively. If a litigation cost estimate were then added to each project, the estimated cost for the Regional Project with vertical wells would increase to $201.3 million, Regional Project with slant wells would increase to $245.3 million as compared to the North Marina Project ($225 million with adjustments) and the Moss Landing Project ($257 million, with adjustments). As we discuss, we must consider both the feasibility of constructing these projects in a timely way as well as the costs of the project.

84 D.03-12-035 at 27, citing Sale v. Railroad Commission (1940) 15 Cal. 2d y07 at 617 and Camp Meeker Water System, Inc. v. Public Utilities Com. (1990) 51 Cal.3d 850 at 861-862.

85 Id, citing Arkansas Electric Coop. v. Arkansas Pub. Serv. Comm'n (1983) 461 U.S. 375, 377.

86 Exhibit 361 at 4.

87 Settlement Agreement, § 10.6 at 16.

88 Exhibit 319 at 13-14. Exhibit 204 at 16 discusses the utilization factor and explains that increasing plant utilization (as BOR recommends) is a way to reduce the unit cost of water.

89 Exhibit 319 at 23.

90 Id.

91 Exhibit 326 at 4-5.

92 Id.

93 Exhibit 600 at 8. If MCWD did not need its permanent allocation until 30 years from the date of operation, then MPWMD estimates that its proportionate share of debt service would be 11%.

94 MPWMD Opening Brief at 23.

95 MCWD Reply Brief at 9.

96 MCWD Reply Brief at 9-10.

97 Cal-Am Opening Brief at 52.

98 Exhibit 101 at 4, Exhibit 11 at 6-7.

99 Cal-Am Opening Brief at 56, citing RT at 1609.

100 Id. at 57, citing Exhibit 111 at 5.

101 Id.

102 Id. at 58.

103 Exhibit 202 at 4-34.

104 Exhibit 319 at 16.

105 Id. at 17. Based on the legal requirements for the Public Agencies, our understanding is that their respective boards must approve the financing plan ultimately recommended for the Regional Project.

106 Id. at 4-27-28.

107 Exhibit 202 at 5-38 states that 2009 revenue requirement for the Monterey District is $42.7 million. Based on the 9% revenue growth rate included in the Unified Financing Model assumptions, the revenue requirement without the plant addition is $70.4 million in 2015.

108 The Commission is not an ordinary administrative agency, but a constitutional body with broad legislative and judicial powers. (Southern California Edison Company v. CPUC (102 Cal.Rptr.2d 684.))

109 Motion to Approve Settlement Agreement, Exhibit 1, Section 5 at 8.

110 In reply comments to the proposed decision and alternate proposed decision, Cal-Am, MCWD, and MCWRA state that they would not object to the Cities of Carmel-By-The-Sea, Pacific Grove, Sand City, Seaside, and Del Rey Oaks adding the City of Monterey to this group. We encourage the Cities to consider this addition.

111 Id. § 6.2 at 35.

112 MPWMD Opening Brief at 10 - 11, citing Exhibit 602 at 15.

113 MCWD Reply Brief at 28.

114 City of Monterey Comments to Amendment to Section 6 of the Water Purchase Agreement at 1.

115 MPWMD's Board of Directors includes a mayoral representative and a representative from the Monterey County Board of Supervisors, in addition to the directly-elected members of the Board.

116 All status reports should be provided to all members of the Advisory Committee, including the Municipal Advisor.

117 See, e.g., MCWD Opening Brief at 38.

118 D.02-08-071, Finding of Fact 18 at 38; D.07-12-052 at 119 et seq.

119 Exhibit 500 at 13.

120 MCWRA Opening Brief at 39.

121 FEIR, Appendix Q at Q-76.

122 FEIR, Appendix Q at Q-7.

123 Exhibit 500 at 14; MCWRA Reply Brief at 20.

124 Exhibit 306 at 10-11, 21.

125 Exhibit 301 at 49.

126 Exhibit 301, §8.2(a) at 45.

127 Exhibit 301, §10 at 52-53.

128 Exhibit 204 at 6.

129 DRA bases this analysis on Exhibit 301, Exhibit E.

130 DRA Opening Brief at 29, citing Exhibit 320 which calculates the total cost for energy, chemicals and brine disposal divided by plant production of 10,500 afy to derive $740 per acre-foot estimate. DRA uses the following formula to calculate the annual savings: (1,138 afy * $740/acre-foot incremental cost) - 1,138 * $148/acre-foot to be paid by MCWD) = $647,000.

131 FEIR at 13.6-2 and 3.

132 Exhibit 500 at 7 explains some of the projects that have assisted MCWRA in slowing seawater intrusion in the Salinas Valley Ground Water Basin.

133 See Chapter 13.6 of FEIR.

134 FEIR at 5-2.

135 FEIR, Chapter 13.6.

136 MCWD Opening Brief at 75, citing Exhibit 319 at 32.

Previous PageTop Of PageNext PageGo To First Page