Word Document PDF Document

ALJ/CFT/jva Mailed 4/14/2006

Decision 06-04-018 April 13, 2006

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

In the Matter of the Application of Pacific Gas and Electric Company (U 39 E) for a Certificate of Public Convenience and Necessity Authorizing the Construction of the Jefferson-Martin 230 kV Transmission Project.

Application 02-09-043

(Filed September 30, 2002)

OPINION GRANTING INTERVENOR COMPENSATION
TO 280 CORRIDOR CONCERNED CITIZENS, CALIFORNIANS
FOR RENEWABLE ENERGY, AND WOMEN'S ENERGY MATTERS
FOR SUBSTANTIAL CONTRIBUTIONS TO DECISION 04-08-046

TABLE OF CONTENTS

Title Page

OPINION GRANTING INTERVENOR COMPENSATION TO 280 CORRIDOR CONCERNED CITIZENS, CALIFORNIANS FOR RENEWABLE ENERGY,
AND WOMEN'S ENERGY MATTERS FOR SUBSTANTIAL CONTRIBUTIONS
TO DECISION 04-08-046
22

TABLE OF CONTENTS

Title Page

TABLE OF CONTENTS

Title Page

Findings of Fact 7878

Conclusions of Law 7878

ORDER 7979

OPINION GRANTING INTERVENOR COMPENSATION
TO 280 CORRIDOR CONCERNED CITIZENS, CALIFORNIANS
FOR RENEWABLE ENERGY, AND WOMEN'S ENERGY MATTERS
FOR SUBSTANTIAL CONTRIBUTIONS TO DECISION 04-08-046

This decision awards 280 Corridor Concerned Citizens (280 Citizens), Women's Energy Matters (WEM), and CAlifornians for Renewable Energy (CARE) intervenor compensation for their contributions to Decision (D.) 04-08-046, in the following amounts: $718,501.61 to 280 Citizens, $126,713.40 to CARE, and $35,125.70 to WEM.

In their requests for intervenor compensation, these three parties cumulatively requested almost $1.6 million. We have scrutinized the requests closely, taking into account the complexity and the high degree of public interest in this proceeding, and as a result the awards granted to 280 Citizens, CARE, and WEM are approximately two-thirds, one-half, and one-third, respectively, of the amount requested. This proceeding is closed.

1. Background

In D.04-08-046, we granted a certificate of public convenience and necessity (CPCN) to Pacific Gas and Electric Company (PG&E) to construct a 230 kilovolt (kV) transmission line between PG&E's Jefferson and Martin substations, along with related facilities in the County of San Mateo. We found in D.04-08-046 that the Jefferson-Martin transmission project is needed in order to allow PG&E to continue to reliably meet electric demand in the San Francisco Peninsula area beginning in 2007. The project also has diversification, economic, and environmental benefits that warrant its construction more quickly than that. We found that a combination of the Jefferson-Martin project and additional transmission reinforcements north of the Martin substation and south of the Jefferson substation would allow closure of the Hunters Point power plant in San Francisco, bringing additional economic and environmental benefits. We adopted a construction cost cap of $206,988,000 for the authorized Jefferson-Martin project.

Responding to public concern regarding potential health effects from exposure to electric and magnetic fields (EMF), D.04-08-046 required several changes to PG&E's preliminary EMF management plan for the Jefferson-Martin project. Concurrent with D.04-08-046, we initiated Rulemaking (R.) 04-08-020 to consider potential improvements to our EMF regulations.

Several parties intervened and participated actively during the environmental review, evidentiary hearing, and briefing process in the subject proceeding. Like other intervenors, 280 Citizens, CARE, and WEM each took positions aimed at protecting the interests of its members. With different constituents, the positions taken by these parties were widely divergent. 280 Citizens sought to influence the route and timing of the new Jefferson-Martin transmission project in the southern portion of the area through which the line will be built. CARE wants the existing Hunters Point power plant to be shut down as quickly as possible and, with that goal in mind, opposed route alternatives that could delay construction of the Jefferson-Martin project. WEM likewise advocated for closure of Hunters Point, focusing on the extent to which the Jefferson-Martin line would change the load serving capacity of the transmission system in the project area. WEM also addressed distributed generation, energy efficiency, energy conservation, and demand response programs as alternatives to the transmission project, and raised concerns regarding potential conflicts of interest in the preparation of cost estimates for the Jefferson-Martin project.

PG&E opposes 280 Citizens' request for compensation in part, does not take a position on CARE's request, and opposes WEM's request in its entirety. PG&E argues that 280 Citizens exaggerated its influence on the D.04-08-046 and has not shown a substantial contribution on many issues for which it claims a contribution. PG&E asserts that the Commission did not adopt any of WEM's positions, in whole or in part, and that WEM did not make a substantial contribution to D.04-08-046 in any other respect.

Top Of PageNext PageGo To First Page