(Electric or street railroad, gas, electric, telephone, telegraph, or water utility.) This rule applies to applications, under Section 1001 of the Public Utilities Code, by any new public utility for a certificate to begin the construction of its plant or system, or by an existing public utility to begin construction of an extension of such a character as to require certification under Section 1001 of the Public Utilities Code. (See Rule 37.) In addition to being drafted to comply with Rules 2 through 2.6, 15 and 16, such applications shall contain the following data, either in the body of the application or in exhibits attached thereto:
(a) A full description of the proposed construction or extension, and the manner in which the same will be constructed.
(b) The names and addresses of all utilities, corporations, persons or other entities, whether publicly or privately operated, with which the proposed construction is likely to compete, and of the cities or counties within which service will be rendered in the exercise of the requested certificate. Whenever a public utility applies to the Commission to extend or establish its water service within a county water district, a public utility or municipal utility district, or other water or utility district, or any area served by such district, such district shall also be named, if it furnishes a like service. The application shall contain a certification that a copy of the application has been served upon or mailed to each such party named.
(c) A map of suitable scale showing the location or route of the proposed construction or extension, and its relation to other public utilities, corporations, persons, or entities with which the same is likely to compete.
(d) A statement identifying the franchises and such health and safety permits as the appropriate public authorities have required or may require for the proposed construction or extension.
(e) Facts showing that public convenience and necessity require, or will require, the proposed construction or extension, and its operation.
(f) A statement detailing the estimated cost of the proposed construction or extension and the estimated annual costs, both fixed and operating associated therewith. In the case of a utility which has not yet commenced service or which has been rendering service for less than twelve months, the applicant shall file as a part of the application supporting statements or exhibits showing that the proposed construction is in the public interest and whether it is economically feasible.
(g) Statements or exhibits showing the financial ability of the applicant to render the proposed service together with information regarding the manner in which applicant proposes to finance the cost of the proposed construction or extension.
(h) A statement of the proposed rates to be charged for service to be rendered by means of such construction or extension. If any increase in rates is proposed, comply with Rule 23.
(i) A statement corresponding to the statement required by Section 2 of General Order No. 104-A, as to all known matters which both (a) are designated by said section for inclusion in the annual report but occurred or were proposed subsequent to the period covered by the last previous annual report filed by the applicant and (b) are, or will be, connected with the construction or extension proposed in the application; or, if no such matters are known to have so occurred or are then known to be proposed, a statement to that effect; provided, that an applicant whose capital stock, or that of its parent company, is listed on a "national securities exchange," as defined in the Securities Exchange Act of 1934 (15 U.S.C. 78(a) et seq.), in lieu of the statement required by this rule shall include in the application a copy of the latest proxy statement sent to stockholders by it or its parent company if not previously filed with the Commission, provided, further, that an applicant whose capital stock, or that of its parent company, is registered with the Securities and Exchange Commission (SEC) pursuant to the provisions of Section 12 (g) of said Securities Exchange Act of 1934, in lieu of the statement required by this rule shall include in the application a copy of the latest proxy statement sent to stockholders by it or its parent company containing the information required by the rules of the SEC if not previously filed with the Commission.
(j) In the case of a telephone utility, the estimated number of customers and their requirements for the first and fifth years in the future.
(k) In the case of a gas utility seeking authority to construct a pipeline:
(1) Regarding the volumes of gas to be transported:
(A) A statement of the volumes to be transported via the proposed pipeline including information on the quality of gas and the maximum daily and annual average daily delivery rates.
(B) A statement that copies of summaries of all contracts for delivery and receipt of gas to be transported via the proposed pipeline and information on the reserves and delivery life pertaining thereto will be made available for inspection on a confidential basis by the Commission or any authorized employee thereof. The terms and provisions of individual contracts for gas supply and data as to reserves or delivery life of individual gas suppliers shall not be required to be stated in the application or in the record of the proceedings, and if disclosed to the commission or to any officer or employee of the Commission on a confidential bases as herein provided, shall not be made public or be open to public inspection.
(2) A summary of the economic feasibility, the market requirements and other information showing the need for the new pipeline and supply.
(3) Where the gas to be transported through the pipeline is to be purchased by the applicant from, or transported by the applicant for, an out-of-state supplier:
(A) A copy of the proposed tariff under which the gas will be purchased or transported.
(B) A statement that the out-of-state pipeline supplier has agreed: (1) to file with this Commission copies of annual reports which it files with the Federal Power Commission; (2) to file with this Commission monthly statements of its revenues, expenses and rate base components; (3) to file with this Commission copies of its tariffs as filed from time to time with the Federal Power Commission; and (4) at all times to permit this Commission or its staff reasonable opportunity for field inspection of facilities and examination of books and records, plus assurance that reasonable requests for operating information otherwise prepared in the course of business will be supplied in connection with any proceeding before the Federal Power Commission.
(l) In the case of an electric utility proposing to construct an electric generating plant:
(1) Load and resource data setting forth recorded and estimated loads (energy and demands), available capacity and energy, and margins for two years actual and three years estimated, on an average year basis.
(2) Existing rated and effective operating capacity of generating plants and the planned additions for a three-year period.
(3) Estimated capital and operating costs of power to be generated by the proposed plant for all competitive fuels which may be used under legislative restrictions in the proposed plant.
(4) For any nuclear plant, a statement indicating that the requisite safety and other license approvals have been obtained or will be applied for, and that a copy of the application to this Commission has been furnished to the State Coordinator of Atomic Energy Development and Radiation Protection.
(m) In the case of a water utility:
(1) An estimate of the number of customers and the requirements for water for the first and fifth years in the future, and the ultimate future development anticipated by applicant, together with a description of the proposed normal, and emergency standby, water facilities for production, storage and pressure to serve the area for which the certificate is sought.
(2) A statement of the estimated operating revenues and estimated expenses, by major classes, including taxes and depreciation, for the first and fifth years in the future attributable to operations in the proposed area.
(3) If the applicant has operated as a water utility elsewhere in the State of California for a period in excess of one year prior to filing the application, a general statement of the operating plans for the proposed area, including a statement whether a new area will be served by existing personnel or will constitute a separate district to be served by new personnel. If the applicant has not operated as a water utility elsewhere in the State of California for a period in excess of one year prior to filing the application, a description of the operating plans for the proposed area, including, to the extent available, but not necessarily limited to, such items as qualifications of management and operating personnel, proposed operating pressures for the system, plans for water treatment, availability of utility personnel to customers, billing procedures, emergency operation plans and provision for handling customer complaints.
(n) In the case of an application by a water utility in an area in which the facilities have already been constructed, extended or installed:
(1) A detailed statement of the amount and basis of the original cost (estimated if not known) of all plant and of the depreciation reserve applicable thereto.
(2) If the facilities have been rendering service in the area for which the certificate is sought, and
(A) The rates proposed are the same as the tariff rates in the district which includes the area to be certificated, the application shall also include a summary of earnings on a depreciated rate base with respect to such area for the test period or periods upon which applicant bases its justification for the rates to be applied in such area; otherwise
(B) The application shall also comply with Rule 23, including the furnishing of the information specified in subsections (e) and (f) thereof but made applicable to the proposed rates; provided, however, the information required by subsections (b) and (c) thereof need be furnished only when increases are proposed.
(o) In the case of an application to furnish one-way paging or two-way mobile radiotelephone service (other than cellular mobile radiotelephone service), the following requirements apply in addition to those enumerated in Rules 1 through 2.6, 15 through 17.1, and subsections (a), (b), (d), first sentence of (f), (g), (h) and (i) above:
(1) When an applicant files for the relevant construction permit from the Federal Communication Commission (FCC) and the FCC public notice period has expired, it may at any time thereafter submit its application to this Commission. The proposed new service area, or the effect of changed facilities on the utility's existing service area, if any, will be shown on a fully legible engineering service area contour map, of suitable scale, prepared in accordance with the applicable criteria set forth in 47 CFR 22. The use of aeronautical charts for this purpose is unacceptable.
(2) Each application shall address the following matters in a substantial manner and with particularity, consistent with the scope of the authorization sought:
(A) Demonstration that the proposed service is responsive to public need and demand.
(B) Technical feasibility of the proposed system and the technical competence of the applicant.
(C) Description of the proposed service including terms, conditions, area of coverage, quality, and features of service, and differences from any service presently provided in the proposed service area.
(D) Financial responsibility of the applicant.
(E) Economic feasibility of the proposed service in the market to be served.
(F) Present operations of the applicant and affiliated companies.
(3) Should an existing utility protest such application, the burden shall rest with the protestant to show that the application should not be granted by affirmatively establishing that granting the application will so damage existing service or the particular marketplace as to deprive the public of adequate service. The protest shall conform to Rules 44 through 44.6 of the Commission's Rules of Practice and Procedure. A service map of protestant's claimed service area shall be filed with the protest. Protests of a general or nonspecific nature will not be sufficient to warrant consideration by the Commission.
(4) Should an existing utility propose to provide service in an area contiguous to its authorized service area and not presently receiving radiotelephone service by any utility, an application for a certificate need not be made, but the engineering data required in (1) above shall be provided to the Telecommunications Division.
(5) Should an existing utility propose an extension of service area which it believes to be minor in nature, but to which (4) above is inapplicable, it shall submit the relevant engineering data to the Telecommunications Division, with a written request for determination of the necessity for a certificate application. Reply will be by letter from an authorized representative of the Commission's Telecommunications Division. In general, an extension will be considered minor if it does not overlap the radio service area of another utility by more than 10% of either utility's radio service area and also does not provide substantial coverage of additional major communities.
(6) Actions as described in (4) or (5) above, or actions such as construction of fill-in transmitting facilities which do not affect service area boundaries, shall be described in tariff revisions which shall be promptly filed by the utility.
(p) Such additional information and data as may be necessary to a full understanding of the situation.
Note: Authority cited: Section 1701, Public Utilities Code. Reference: Section 1001, Public Utilities Code.
All applications for common carrier certificates shall comply with Rules 2 through 2.6, 15, and 16. Highway common carrier applications shall be filed on the proper form available from the license section of the tariff and license branch of the Transportation Division. Vessel common carrier, express corporation, freight forwarder, passenger stage corporation, cement carrier, and highway common carrier applications shall contain the following data, either in the body of the application or in attached exhibits:
(a) The type of service being performed by applicant, a general description of it, and a reference to the authority under which existing service is performed.
(b) The specific authority requested and the particular statutory provision under which the certificate is requested.
(c) If a carrier of property, a description of specified commodities proposed to be transported, and, if general commodities with exceptions are proposed to be transported, a statement specifying such exceptions.
(d) The geographical scope of the proposed operation, including the termini and other points proposed to be served, and a concise narrative description of the proposed route.
(e) A map or sketch of the route and points to be served, drawn to suitable indicated scale, and showing present and proposed operation by distinctive coloring or marking.
(f) A statement of the rates or fares proposed to be charged and rules governing service. Applications for certificates need not contain tariffs, but shall indicate the level and nature of proposed rates and rules and may refer to tariffs on file with or issued by the Commission.
(g) A statement indicating the frequency of the proposed service. If "on call" service is proposed, the application shall set forth conditions under which such service would be performed.
(h) The kind and approximate number of units of equipment to be employed in the proposed service.
(i) A statement of financial ability to render the proposed service.
(j) Facts showing that the proposed operation is required by public convenience and necessity.
(k) Every applicant for a passenger stage certificate shall forward a copy of the application to each public transit operator operating in any portion of the territory sought to be served by the applicant. The applicant shall also mail a notice that the application has been filed with the Commission to all city and county governmental entities and regional transportation planning agencies within whose boundaries passengers will be loaded or unloaded. This notice shall state in general terms the authority sought, including the proposed routes, schedules, fares and equipment. Said notice shall also state that a copy of the application and related exhibits will be furnished by applicant upon written request. A copy of the notice and a certificate of service shall be filed with the application.
(l) Applicants shall mail or give a copy of their application to any potential competitor, governmental entity, or interested party
requesting a copy, and to any persons upon direction by the Commission or other Rules.
Note: Authority cited: Section 1701, Public Utilities Code; and Section 2, Article XII, California Constitution. Reference: Sections 701, 1007, 1010, 1032, 1062 and 1701, Public Utilities Code.