Rule 21 Model Tariff Language

1. APPLICABILITY AND INTRODUCTION

2. GENERAL RULES, RIGHTS AND OBLIGATIONS

3. APPLICATION AND INTERCONNECTION PROCESS

4. GENERATING FACILITY DESIGN AND OPERATING REQUIREMENTS

Voltage at Point of Common Coupling

Maximum Trip Time

(Assuming 60 Cycles per Second)

Less than 60 Volts

10 Cycles

Greater than 60 volts but less than 106 volts

120 Cycles

Greater than 106 volts but less than 132 volts

Normal Operation

Greater than 132 volts but less than 165 volts

120 Cycles (30 cycles for facilities greater than 11kVA)

Greater than 165 volts

6 Cycles

5. INTERCONNECTION FACILITY OWNERSHIP AND FINANCING

6. METERING, MONITORING AND TELEMETRY

7. DISPUTE RESOLUTION PROCESS

8. DEFINITIONS

Active Anti-Islanding Scheme: A control scheme installed with the Generating Facility that senses and prevents the formation of an Unintended Island.

Applicant: The entity submitting an Application for Interconnection.

Application: The standard form CPUC-approved document submitted to the Electrical Corporation for electrical interconnection of a Generator with the Electrical Corporation.

Certification Test; A test adopted by an Electrical Corporation that verifies conformance of certain equipment with CPUC-approved performance standards in order to be classified as Certified Equipment. Certification Tests are normally performed by approved laboratories such as the Underwriter's Lab (UL).

Certification; Certified: The results of a successful Certification Testing. (Note: The details about the certification process will be part of a Supplemental Report.

Certified Equipment: Equipment that has passed the Certification Test.

CPUC: The Public Utilities Commission of the State of California.

Customer: The entity that receives or is entitled to receive Distribution Services through the Distribution System.

Dedicated Transformer: A transformer that provides Electricity Service to a single Customer. The Customer may or may not have a Generating Facility.

Distributed Generation: Electrical power generation by any means, including from stored electricity, that is interconnected to an Electrical Corporation at a Point of Common Coupling under the jurisdiction of the CPUC.

Distributed Generator: An individual electrical power plant, including required equipment, appurtenances, protective equipment and structures, that is capable of Distributed Generation.

Distribution Service: All services required by, or provided to, a Customer pursuant to the approved tariffs and rules of the Electrical Corporation.

Distribution System Island: A condition on the Distribution System in which one or more Distributed Generator(s), over which the utility has no direct control, and a portion of the Distribution System operate while isolated from the remainder of the Distribution System.

Distribution System: All electrical wires, equipment, and other facilities owned or provided by the Electrical Corporation by which an Electrical Corporation provides Distribution Service to its Customers.

Electrical Corporation: The entity that, under the jurisdiction of the CPUC, is charged with providing Electricity Distribution Service to the Customer.

Electricity Producer: The entity that executes an Interconnection Agreement with the Electrical Corporation. The Electricity Producer may or may not own or operate the Generating Facility, but is responsible for the rights and obligations related to the Interconnection Agreement.

Emergency: An actual or imminent condition or situation, which jeopardizes the Distribution System Integrity.

Field Testing: Testing performed in the field to determine whether equipment meets the Electrical Corporation's requirements for safe and reliable Interconnection

Generating Facility: All Distributed Generators that are included in an Interconnection Agreement.

Gross Nameplate Rating: The total gross generating capacity of the Distributed Generator as designated by the manufacturer of the Distributed Generator.

Host Load: Electrical power that is consumed by the Customer at the property on which the Generating Facility is located.

Initial Operation: The first time the Generating Facility is in Parallel Operation.

Initial Review: The review by the Electrical Corporation, following receipt of an Application, to determine the following:

Interconnection Agreement: An agreement between the Electrical Corporation and the Electricity Producer that gives each the certain rights and obligations to effect or end Interconnection.

Interconnection Study: A study to establish the requirements for Interconnection of an Electricity Producer.

Interconnection; (Interconnected): The physical connection of Distributed Generation in accordance with the requirements of these rules so that Parallel Operation with the utility system can occur (has occurred).

Interconnection Facilities: The electrical wires, switches and related equipment, that interconnect a Generating Facility to the Distribution System.

Island; Islanding: A condition on the Distribution System in which one or more Generating Facilities , deliver power to Customers using a portion of the Distribution System that is electrically isolated from the remainder of the Distribution System.

ISO: The California Independent System Operator, responsible for the management of electrical power flow through California's electrical transmission network.

Line Section: That portion of the Distribution System connected to a Customer bounded by automatic sectionalizing devices or the end of the line.

Metering Equipment: All equipment, hardware, software including meter cabinets, conduit, etc. that is necessary for Metering.

Metering: The measurement of electrical power flow in kW and/or kWh, and, if necessary, kVARat a point, and its display to the Electrical Corporation, as required by this rule.

Net Energy Metering: Metering for the mutual purchase and sale of electricity between the Electricity Producer and the Electrical Corporation pursuant to the net metering tariff approved by the CPUC.

Net Generation Metering: The Metering of the net electrical energy output in kW and kWh from a given Generating Facility. This may also be the measurement of the difference between the total electrical energy produced by a Distributed Generator and the electrical energy consumed by the auxiliary equipment necessary to operate the Distributed Generator. For a Distributed Generator with no Host Load and/or Section 218 Load, Metering that is located at the point of Common Coupling. For a Distributed Generator with Host Load and/or Section 218 Load, Metering that is located at the Distributed Generator bus after the point of auxiliary load(s) and prior to serving Host Load and/or Section 218 Load.

Net Metering: Where electricity at a point may flow in both directions, the measurement of the net, or the algebraic sum, of electrical energy in kWh, that flows through that point in a given time-interval. Net Metering typically uses two meters, or in some cases a single meter with two or more registers, to individually measure a Customer's electric deliveries to, and consumption of retail service from, the Distribution System. Over a given time frame (typically a month) the difference between these two values yield either net consumption or net surplus. The meter registers are ratcheted to prevent reverse registration. If available, a single meter may be allowed spin backward to yield the same effect as a two meter (or register) arrangement.

Net Nameplate Rating: The Gross Nameplate Rating minus the consumption of electrical power of the Distributed Generator as designated by the manufacturer(s) of the Distributed Generator.

Network Service: More than one electrical feeder providing Distribution Service at a Point of Common Coupling.

Parallel Operation: The simultaneous operation of a Distributed Generator with power delivered or received by the Electrical Corporation while Interconnected. For the purpose of this rule, Parallel Operation includes only those generators that are so interconnected with the Distribution System for more than 60 cycles.

Point of Common Coupling Metering: Metering located at the Point of Common Coupling. This is the same Metering as Net Generation Metering for Generating Facilities with no Host Load and/or Section 218 Load.

Point of Common Coupling: The transfer point for electricity between the electrical conductors of the Electrical Corporation and the electrical conductors of the Electricity Producer.

Point of Interconnection: The electrical transfer point between an electrical power plant and the electrical distribution system. This may or may not be coincident with the Point of Common Coupling.

Power Purchase Agreement: An agreement for the sale of electricity by the Electricity Producer to the Electrical Corporation.

Protective Function(s): The equipment, hardware and/or software in a Generating Facility (whether discrete or integrated with other functions) whose purpose is to protect against Unsafe Operating Conditions.

Prudent Electrical Practices: Those practices, methods, and equipment, as changed from time to time, that are commonly used in prudent electrical engineering and operations to design and operate electric equipment lawfully and with safety, dependability, efficiency, and economy.

Scheduled Operation Date: The date specified in the Interconnection Agreement when the Generating Facility is, by the Electricity Producer's estimate, expected to begin Initial Operation.

Secondary Network: A network supplied by several primary feeders suitably interlaced through the area in order to achieve acceptable loading of the transformers under emergency conditions and to provide a system of extremely high service reliability. Secondary networks usually operate at 600 V or lower.

Section 218 Load: Electrical power that is supplied in compliance with California Public Utilities Code (PU Code) section 218. PU Code 218 defines an "Electric Corporation" and provides conditions under which a generator transaction would not classify a generating entity as an Electric Corporation. These conditions relate to "over-the-fence" sale of electricity from a generator without using the Distribution System.

Simplified Interconnection: Interconnection conforming to the minimum requirements under these rules, as determined by Appendix A.

Short Circuit Contribution Ratio (SCCR): The ratio of the Generating Facility's short circuit contribution to the Electrical Corporation's short circuit contribution for a three-phase fault at the high voltage side of the distribution transformer connecting the Generating Facility to the Electrical Corporation's system.

Special Facilities: Those facilities installed at the Electricity Producer's request which the Electrical Corporation does not normally furnish under its tariff schedule; or a prorata portion of existing facilities requested by the Electricity Producer, allocated for the sole use of such an Electricity Producer, which would not normally be allocated for such sole use.

Stabilization; Stability: The return to normalcy of an Electrical Corporation Distribution System, following a disturbance. Stabilization is usually measured as a time period during which voltage and frequency are within acceptable ranges.

System Integrity: The condition under which a Distribution System is deemed safe and can reliably perform its intended functions in accordance with the safety and reliability rules of the Electrical Corporation.

Telemetering: The electrical or electronic transmittal of Metering data on a real-time basis to the Electrical Corporation.

Unintended Island: The creation of an island, usually following a loss of a portion of the Distribution System, without the approval of the Electrical Corporation.

Unsafe Operating Conditions: Conditions that, if left uncorrected, could result in harm to personnel, damage to equipment, loss of System Integrity or operation outside pre-established parameters required by the Interconnection Agreement.

RULE 21 APPENDIX A: INITIAL REVIEW PROCESS

Previous PageTop Of PageGo To First PageNext Page