FOR APPLICATIONS TO INTERCONNECT
DISTRIBUTED GENERATION

Introduction:

This Initial Review Process was developed to create a path for selection and rapid approval of those Applications for Interconnection that do not require an Interconnection Study. The capitalized phrases used in this Appendix A have the same meanings as those in Section 8 of the proposed Rule 21.

Purpose:

The Initial Review determines:

NOTE:

Failure to pass any screen only means that further review, and/or studies, are required before the DG project will be approved for interconnection with the Electrical Corporation. It does not mean that the DG cannot interconnect.

INITIAL REVIEW PROCESS FLOW CHART

Provide Completed Application.

Follow Net Metering Process (per P.U. Code Sec. 2827)

1. Does the DG qualify for net metering?

1.

2.

3. Will Power be exported across the PCC?

4. Is the Interconnection Equipment Certified for Application? or
does Interconnection Equipment have Interim EC Approval?

5. Is the aggregate DG Capacity on the Line Section less than 15% of Line Section peak load?

6. Is the DG Capacity 11 kVA or less?

7. Is the Short Circuit Current Contribution screen met?

8. Is the Line Configuration screen met?

INITIAL REVIEW PROCESS DETAILS:

1. Does the DG qualify for net metering?

2. Is the Point of Common Coupling (PCC) on a Networked Secondary System?

3. Will power be exported across the PCC?

4. Is the Interconnection Equipment Certified for the Application or does the Interconnection Equipment have Interim EC Approval?

5. Is the aggregate DG Capacity on the Line Section less than 15% of Line Section Peak Load?

6. Is the DG Capacity 11 kVA or less?

7. Is Short Circuit Current Contribution screen met?

8. Is the Line Configuration screen met?

(END OF APPENDIX A)