Word Document PDF Document |
Decision PROPOSED ALTERNATE DECISION OF PRESIDENT PEEVEY
(Mailed 4/6/2004)
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Order Instituting Rulemaking to Establish Policies and Cost Recovery Mechanisms for Generation Procurement and Renewable Resource Development. |
Rulemaking 01-10-024 (Filed October 25, 2001) |
(See Appendix A for a list of appearances.)
OPINION APPROVING MOTION OF SAN DIEGO GAS & ELECTRIC
COMPANY (U 902 E) FOR APPROVAL TO ENTER INTO NEW
ELECTRIC RESOURCE CONTRACTS RESULTING FROM
SDG&E'S GRID RELIABILITY REQUEST FOR PROPOSAL
TABLE OF CONTENTS
Title Page
OPINION APPROVING MOTION OF SAN DIEGO GAS & ELECTRIC
COMPANY (U 902 E) FOR APPROVAL TO ENTER INTO NEW
ELECTRIC RESOURCE CONTRACTS RESULTING FROM
SDG&E'S GRID RELIABILITY REQUEST FOR PROPOSAL 2
I. Summary 2
II. Background 2
A. San Diego Gas & Electric Company 4
B. The Basis for SDG&E's RTP 5
C. Preparation and Circulation of the RFP 6
D. Bid Evaluation 8
E. Proposed Projects Resulting From the RFP Process 11
III. Summary of Parties' Positions 11
A. SDG&E 11
B. TURN/UCAN 12
C. ORA 13
D. PG&E 13
E. Coral Power 15
F. InterGen 17
G. Dynegy 18
H. Celerity 20
I. Nevada Hydro 22
J. SER 24
K. Calpine 24
IV. Discussion 25
A. Demand Response: Comverge 30
B. Renewable: Envirepel 33
C. Ramco 35
D. Palomar 44
E. Otay Mesa 50
a) Reasons to Approve the PPA 55
b) Commission Involvement 57
c) There Was No Unfairness in the RFP Process 60
d) Consideration of Otay Mesa Should Not Be Deferred
to the New LTRP Proceeding 63
e) SDG&E's Need for Otay Mesa Power 64
f) The Benefits of a 10-Year PPA 66
g) Transmission Upgrades 66
h) SDG&E's Conditions 67
F. The Value of This RFP Process 70
G. Procedural Issues 72
V. Comments on Proposed Decision 77
VI. Assignment of Proceeding 78
Findings of Fact 78
Conclusions of Law 83
ORDER 84
Appendix A - List of Appearances
OPINION APPROVING MOTION OF SAN DIEGO GAS & ELECTRIC
COMPANY (U 902 E) FOR APPROVAL TO ENTER INTO NEW
ELECTRIC RESOURCE CONTRACTS RESULTING FROM
SDG&E'S GRID RELIABILITY REQUEST FOR PROPOSAL
In this decision, we approve the five proposals that SDG&E presented to meet its short-term and long-term grid reliability needs. These proposals were the result of an open and competitive Request for Proposal (RFP) process that solicited bids from all qualified resources, including turn-key natural gas-fired generating units, power purchase agreements (PPA), demand response programs, and renewable resources. Out of 22 bids received, these five proposals were identified as conforming to the RFP specifications and were found to be the least cost/best fit choices for meeting the utility's need to have a diversified portfolio of resources to meet its customers grid reliability needs, are consistent with SDG&E's long-term resource plan (LTRP), benefit consumers, and are in the public interest. The proposals include a demand response program from Comverge, a renewable resource contract with Envirepel, and contracts for three gas-fired facilities, Ramco, Palomar, and Otay Mesa. Ramco is a turn-key combustine turbine intermediate unit, Palomar is a turn-key 500/555 MW combined-cycle power plant, and Otay Mesa is a 10-year PPA for a 485/573 MW combined cycle facility.