Program process

The preferred approach is to operate the self-generation program through existing SPC program rules and procedures, where possible. The administrators, through the working group led by SoCalGas, should finalize all program details prior to program launch in each service territory. Additional requirements related to self-generation installations are included below.

The applicant must provide copies of the following information as proof of installation and parallel operation with the utility distribution grid:

_ the final purchase invoice of the self-generation system;

_ affidavit signed by the installer of the system and customer stating that the system has been purchased and installed, and that an administrator representative or contractor will be allowed to inspect or monitor the system;

_ the building permit showing final inspection signoff;

_ an interconnection agreement executed with the utility for the system (if applicable).