E. RSCD Report

The Presiding Officer and Assigned Commissioner issued a ruling on May 30, 2001 that directed RSCD to file and serve a report by June 7, 2001 with recommendations on the rail transit systems' petitions.

Although RSCD does not concur with the petitioners' proposal to fully exempt rail transit systems from rotating outages, RSCD does recommend an exemption from rotating outages for those sections of track to which emergency response personnel have limited access, such as exclusive right-of-ways, ballasted tracks, underground sections, tunnels, tubes, aerial structures, and control centers.

On June 26, 2001, the Presiding Officer and Assigned Commissioner issued a ruling that required RSCD to submit a supplemental report by July 9, 2001 listing specific facilities that meet its recommended exemption from rotating outages. The ruling asked all rail transit systems which had filed petitions to cooperate and assist RSCD in obtaining the supplemental information. The ruling also directed respondent utilities to use RSCD's supplemental report to conduct a load/reserve margin analysis by July 16, 2001 to determine the impact of RSCD's proposed partial rotating outage exemption on their total system load available for rotating outage. The ruling invited parties to file and serve comments on the RSCD and respondent utilities reports within three days from the date filed.

1. RSCD Recommendations

RSCD proposed the following recommendations.

a. Rail Transit Systems

b. Grade Crossing Warning Devices

c. Freight and Commuter Railroads

2. RSCD Supplemental Report

In its supplemental report, RSCD recommends that the entire SCE portion of LACMTA's Green Line and the SCE portion of LACMTA's Blue Line, except for the Blue Line street-running sections in Downtown Long Beach, be exempted from rotating outages, as detailed in Appendix A to this decision. For SCVTA, RSCD recommended that the SCVTA Control Center and those portions of SCVTA track that are exclusive right-of-way and ballasted be exempted from rotating outages, as detailed in Appendix B to this decision. RSCD made no recommendation for SDTI because SDTI did not submit sufficient information.

RSCD also recommends that the following common corridor mitigation measures be adopted.

RSCD received additional information from SDTI and filed a second supplemental report on July 31, 2001, that identified the specific SDTI facilities and sections of track that meet RSCD's rotating outage exemption criteria. (Appendix C.)

PG&E, SDG&E, and SCE timely filed and served their reports on the results of their load/reserve margin analysis and impact on total system load outages.

The following tabulation shows the number of circuits, megawatts, and total system load affected, excluding circuits already exempted, by RSCD's recommended exemption for rotating outages.

        Affected

Utility

Circuits

Megawatts

Load

PG&E5

26

17.3

.10%

SDG&E

15

93.8

2.00

SCE

217

46.8

0.21

5 PG&E included, in its report, circuits and megawatts already exempted from rotating outages for other purposes. Such circuits have no further impact on the utilities' total system load available for rotating outages. PG&E also included circuits that have back up circuits not requiring an exemption at this time. However, if the status of the back up circuits or exemption status of these already exempt circuits change, rail transit systems should continue to be granted an exemption from rotation outages on such circuits. 6 Although a total of 12 circuits are impacted, 5 circuits utilizing 73.9 MW have back-up circuits not requiring an exemption and 5 circuits utilizing 79.6 MW are already exempted. 7 A total of 39 circuits are impacted, of which 18 circuits are already exempt.

Previous PageTop Of PageNext PageGo To First Page